Citation : 2009 Latest Caselaw 541 Del
Judgement Date : 16 February, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ A.A. No.273/2008
% Date of Decision: 16.02.2009
M/s.Agni Constructions Pvt. Ltd. .... Petitioner
Through Mr.Shiv Khorana, Advocate.
Versus
M/s.GNB Brothers Pvt. Ltd. .... Respondent
Through Mr.Subodh Kumar, Advocate
CORAM:
HON'BLE MR. JUSTICE ANIL KUMAR
1. Whether reporters of Local papers may be YES
allowed to see the judgment?
2. To be referred to the reporter or not? NO
3. Whether the judgment should be reported in NO
the Digest?
ANIL KUMAR, J.
*
1. This is petition under Section 11 of Arbitration and Conciliation
Act, 1996 by the petitioner seeking appointment any of the three
suggested persons named in the notice dated 12th June, 2008 as an
arbitrator in place of the Arbitrator appointed by the respondent.
2. The petitioner contended that an inquiry was issued by Corozo
Fashion Clothing through their architect, M/s. Sachdeva Consultants,
for the civil and plumbing works involved in the construction of an
industrial building at Manesar. The work was sub divided into two
phases. The petitioner contended that after discussions and
negotiations, the petitioner was awarded work by Corozo Fashion
Clothing on 14th August, 2006. The work letter contained an arbitration
clause in terms of clause 5.9.5. The petitioner under the terms of the
work letter was entitled for two percent bonus on completion of the
work within the scheduled time.
3. It is asserted by the petitioner that though the work was awarded
to them by Corozo Fashion Clothing, due to paucity of funds, Corozo
Fashion Clothing had entered into some arrangements with M/s. GNB
Brothers Pvt. Ltd., the respondents herein.
4. The plaintiff has contended that though the terms of payment in
the work letter dated 14th August, 2006 were in accordance with
clauses 5.7 and 5.7.3 of the tender enquiry, later on an agreement,
dated 17th November, 2006, for item rate contract within the rate for
recovery of material to be supplied by the respondent was entered into
with the respondent. It is contended that though the petitioner had
already executed work worth 62 lacs by the time the agreement dated
17th November, 2006 was entered into, the petitioner was only paid 25
lacs and the balance was retained by the respondent.
5. The petitioner has contended that even though the various
hindrances and delays on the part of the respondent, which had
brought about a delay in the completion of phase I of the work, were
brought to the notice of the respondent, they failed to rectify the same.
It was also contended that on account of the delay the petitioner had to
execute additional work and submitted bills for the same, however, the
same has not been paid by the respondent. The allegation has also
been made by the petitioner that the respondent committed breach of
contract by non certifying bills, the details of which are given by the
petitioner in the petition.
6. The petitioner has contended that despite the breaches
committed by the respondent, he further failed to release the payment
for the work already executed and made the petitioner to sign an
agreement dated 25th October, 2007 which contained an arbitration
clause which is reproduced below.
"Arbitration Clauses:-
In the event of any dispute arising out of any way connected with M/s. Agni Constructions Pvt. Ltd., its terms and conditions or its interpretation or validity, such disputes shall firstly be attempted to be sorted out amicably, falling which they shall be referred to the sole arbitration of M/s. G.N.B. Bros Pvt. Ltd. The arbitration shall be conducted at Delhi under the terms of the arbitration and conciliation Act, 1996 and the award of the arbitration shall be final and binding on both the parties. The arbitrator shall be appointed by G.N.B. Bros. Pvt. Ltd. who shall have the sole discretion to appoint the arbitrator in the event of any of the above said party raising disputes under this contract.
The court of contempt jurisdiction shall be exclusively that of our registered head office (Delhi at present) even when there are several defendants or in the case of an appeal.
However we can also take our suppliers/service providers to the court corresponding to their own registered offices. Neither our notes nor our acceptance of payment shall represent either a novation or derogation to the clause allocating the jurisdiction"
7. The petitioner contended that the contract with him was
terminated by the respondent by a letter dated 21st April, 2008 and
after termination petitioner submitted a bill for Rs.44,958,325/- dated
6th May, 2008, however, the amounts were not paid and the disputes
arose between the parties.
8. The plea of the petitioner is that in order to sort out the disputes,
a meeting was called on 11th March, 2008. It is pleaded that the
respondent prepared an incorrect minutes of the said meeting and,
therefore, petitioner did not sign the same and wrote to the respondent
a letter dated 12th March, 2008 to have further meeting at a neutral
venue. The petitioner, without disclosing the details of the letters
written to him by the respondent, has alleged that the respondent
threatened the petitioner. It is also alleged that by a letter dated 22nd
April, 2008 the respondent had asked the petitioner to agree with the
choice of arbitrator of the respondent or else the petition would be filed
for the appointment of arbitrator under the provisions of Arbitration
and Conciliation Act, 1996. According to the petitioner, he did not
accept the appointment of arbitrator by respondent and issued a letter
to the respondent, dated 5th May, 2008, indicating the same. The
petitioner contends that the claims of the petitioner are absolutely
technical in nature and the disputes relate to construction work of an
industrial unit and the nature of the claims are engineering and
technical, therefore, it is essentially necessary to have an arbitrator who
is a civil engineer and well experienced. According to the petitioner by
notice dated 12th June, 2008, petitioner suggested three names, i.e.,
Mr.C.B. Lal, Retired Director General, CPWD; Mr.M.K. Goyal, Retired
Chief Engineer, CPWD and Shri Ganu Lal, Superintendent Engineer,
and asked the respondent to choose any of the names within seven
days of the receipt of the notice. The petitioner has also raised the
disputes which are detailed in para 7 (B) of the petition and the present
petition under Section 11 of the Arbitration and Conciliation Act, 1996
was filed on 29th July, 2008.
9. The petition for appointment of arbitrator is contested by the
respondent contending inter alia that according to the terms of the
agreement between the parties, the arbitrator is to be appointed by the
respondent. The respondent has contended that it had appointed
Hon‟ble Mr. Justice K. Ramamoorthy (retired Judge of the Delhi High
Court) as the sole arbitrator in terms of clause of 5.9.5 of the tender
document read with amended arbitration clause in agreement dated
25th October, 2007 forming part of the contract for civil and plumbing
work of industrial building at Plot No.14, IMT Maneshar, Gurgaon, to
resolve the disputes arising under the said contract. Despite the letter
dated 22nd April, 2008 appointing the said arbitrator, the petitioner
wrote a letter dated 12th June, 2008 and sought appointment of any one
of the three names indicated by him in his communication as the
arbitrator. The respondent contended that the appointment of arbitrator
by it is in consonance with the arbitration agreement and the petitioner
cannot insist for appointment of any other person as an arbitrator, in
the facts and circumstances.
10. Relying on National Highways Authority of India v. Bumihiway
DDB Ltd, (2006) 10 SCC 763 and Rite Approach Group Ltd. v.
Rosoboronexport, (2006) 1 SCC 206, it was contended that unless the
arbitrator appointed according to the terms of the arbitration agreement
fails to exercise its jurisdiction, the Court cannot assume jurisdiction
under Section 11(6) of the Arbitration & Conciliation Act, 1996.
11. The respondent contended that the petitioner has no cause to file
the present arbitration petition as the petitioner is accepting the
appointment of arbitrator in terms of the arbitration clause in
agreement dated 25th October, 2007 and is also trying to have his
appointment superseded by filing petition under Section 14 of
Arbitration and Conciliation Act, 1996 which is also pending
adjudication in this court. In the circumstances it has been
contended that attitude of the petitioner is malafide and his conduct is
illegal. The respondent also contended that facts in issue in the present
petition are substantially similar to the facts of the claim filed by the
respondent before the arbitrator and there cannot be two different
arbitration proceedings going on simultaneously. The respondent also
contended that the petitioner had filed an application under Section 16
of the Arbitration and Conciliation Act, 1996 raising objection to the
jurisdiction of the sole arbitrator. The application of the petitioner
under Section 16 was heard by the learned Arbitrator and the objection
was dismissed on 27th August, 2008.
12. The respondent also contended that the arbitrator had been
appointed pursuant to communication dated 22nd April, 2008, however,
this fact has been concealed by the petitioner who had deliberately
made a wrong averment in para 4 of the petition alleging that no
arbitrator is appointed to adjudicate the claims of the petitioner.
13. In the circumstances, it is prayed that the petition be dismissed.
14. Learned counsel for the petitioner had contended vehemently that
fees demanded by the Arbitrator appointed pursuant to letter dated
22nd April, 2008 is exorbitant and, therefore, the arbitration by such an
Arbitrator be superseded and has relied on Bharat Sanchar Nigam Ltd.
and another v. Motorola India Pvt. Ltd., 2008 (3) Arb.L.R. 531 (SC);
Union of India v. Bharat Battery Manufacturing Co. (P) Ltd., 2007 (3)
Arb.L.R. 282 (SC); Datar Switchgears Ltd. v. Tata Financial Ltd. and
another, (2000) 8 SCC 151; Harcharan Das Gupta v. Govt. of NCT of
Delhi and another, AA No.349/2006, decided on 19th December, 2007;
Shri Satya Pal Gupta v. Municipal Corporation of Delhi, AA
No.437/2006, decided on 14th December, 2007.
14. Learned counsel for the petitioner has also referred to arbitration
clause 5.9.5 which has been referred to by the learned Arbitrator while
dealing with the application under Section 16 of the Arbitration and
Conciliation Act, 1996 which was dismissed by order dated 27th August,
2008.
15. Learned counsel for the petitioner cannot deny the appointment
of Arbitrator in terms of arbitration clause in agreement dated 25th
October, 2007, as by letter dated 5th May, 2008. The petitioner had
sought appointment of arbitrator by mutual consent or by the court.
16. If the arbitrator was not appointed by the respondent in terms of
the arbitration clause, only then would the petitioner have had a lis to
approach this court for appointment of an arbitrator in terms of the
arbitration agreement. Arbitration agreement contemplates sole
arbitration by M/s. G.N.B. Bros. Pvt. Ltd. who had to appoint an
arbitrator at their sole discretion which had been done by them. The
arbitration clause in the award of work dated 14th August, 2006 and
subsequent agreement dated 17th November, 2006 shall stand modified
by the arbitration clause in the agreement dated 25th October, 2007.
17. Learned counsel for the petitioner has also vehemently contended
that the disputes of the petitioner are not being adjudicated by the
Arbitrator. The contention of the petitioner is misleading and contrary
to the petitioner‟s stand. The petitioner has not filed his claims before
the Arbitrator nor has the Arbitrator refused to adjudicate the disputes
raised by the petitioner. Rather, the petitioner has filed an application
under Section 16 of Arbitration and Conciliation Act, 1996 seeking
dropping of the arbitration proceedings on the ground that the
Arbitrator has no jurisdiction till this Court passes an order in the
application filed by the respondent under Section 11 of the Act.
18. Since the respondent had invoked the arbitration agreement in
terms of arbitration clause and appointed the sole arbitrator as
contemplated under the agreement, there was no necessity for the
respondent to approach this court for appointment of the arbitrator. If
the appointment of the Arbitrator was not in consonance with the
arbitration clause in the agreement dated 25th October, 2007, only then
the petitioner could have approached this Court for appointment of an
arbitrator in terms of the arbitration clause between the parties. The
petitioner is taking contradictory stands as the petitioner has also filed
a petition to terminate the mandate of the Arbitrator under Section 14
of the Arbitration and Conciliation Act, 1996 on the ground that the
fees demanded by the Arbitrator is prohibitory and consequently the
arbitration be superseded as Arbitrator has become de jure or de facto
unable to perform his functions. The plea for the terminating the
mandate of the arbitrator is pending separately before this Court,
however, that does not entitle the petitioner to get an arbitrator
appointed under Section 11 of the Arbitration and Conciliation Act,
1996 so long as the appointment of the Arbitrator is in accordance with
the arbitration clause.
19. The petitioner has also made incorrect averments in the petition.
By a letter dated 22nd April, 2007, the Arbitrator was appointed,
however, in para 4 of the petition which is also verified by the petitioner
it is stated that no Arbitrator had been appointed to adjudicate the
claims of the petitioner. The precedents relied on by the petitioner also
do not support the claim of the petitioner.
20. In Bharat Sanchar Nigam Ltd. (supra), it was held that the
disputes raised by the petitioners were not „excepted matters‟ and that
the respondents were not to decided whether they were excepted
matters and whether they were excepted matters was also to be
adjudicated before the Arbitrator. Apparently, the ratio of the case relied
on by the petitioner is not relevant to the present facts and
circumstances. In Union of India v. Bharat Battery Manufacturing Co.
P. Ltd. (supra), Union of India had failed to appoint an Arbitrator within
30 days of invocation of the arbitration agreement and the petition
under Section 11(6) of the Arbitration and Conciliation Act, 1996 was
filed on 30th March, 2006. The Union of India, however, appointed an
Arbitrator after the petition under Section 11(6) of Arbitration and
Conciliation Act, 1996 was filed. It was held that the Union of India had
lost its right to appoint an Arbitrator and that the appointment of the
Arbitrator by the court was justified. The other decisions relied on by
the petitioner, Harcharan Das Gupta (supra) and Shri Satya Pal Gupta
(supra) are also distinguishable and on the basis of the ratio of the said
judgments, the petitioner is not entitled to have another Arbitrator
appointed under Section 11 of Arbitration and Conciliation Act, 1996
after challenging his jurisdiction under Section 16 of the Arbitration
and Conciliation Act, 1996 before the Arbitrator and on account of
pendency of another petition under Section 14 of the Arbitration and
Conciliation Act, 1996 seeking termination of his mandate.
21. In the totality of facts and circumstances, the petition under
Section 11 of the Arbitration and Conciliation Act, 1996 by the
petitioner is an abuse of process of law and is without any merit and it
is, therefore, dismissed with a cost of Rs.10,000/- payable by the
petitioner to the respondent. The cost be paid to the respondent within
four weeks.
February 16, 2009 ANIL KUMAR, J. 'Dev'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!