Citation : 2009 Latest Caselaw 5401 Del
Judgement Date : 23 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.S. (OS) No.3023 of 1992
% 23.12.2009
SHRI VASUDEV ......Petitioner
Through: Mr. B.K. Dewan, Advocate.
Versus
DELHI DEVELOPMENT AUTHORITY ......Respondents
Through: Ms. Alpana Pandey for Mr. D.S.
Mahendru, Advocate.
Date of Reserve: 19th August, 2009
Date of Order: December 23, 2009
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment? Yes.
2. To be referred to the reporter or not? Yes.
3. Whether judgment should be reported in Digest? Yes.
JUDGMENT
1. By this order I shall dispose of objections made by the DDA under Sections 30
and 33 of the Arbitration Act against an Award of the Sole Arbitrator, Sh.R.C. Malhotra,
dated 29th June, 1992.
2. The brief facts relevant for the purpose of deciding these objections are that the
contractor, Mr. Vasudev, was awarded a civil contract for construction of sewerage at
Hudson Lines, Kingsway Camp vide an agreement dated 30th September, 1987. The
work was to be completed by 4th July, 1988. However, the work did not complete by the
stipulated time and the DDA rescinded the contract vide letter dated 23rd February, 1991.
The contractor raised a dispute and sought reference of his claims to the Arbitrator. In all
28 claims were raised by the contractor and were referred to the Arbitrator. The DDA
also raised counter claims and the Award deals with these claims and counter claims. The
objections against the Award have been filed claim wise so they are being dealt with
claim wise.
3. Under claim No.1, the claimant claimed a sum of Rs.99,785/- on account of
refund of security deposit. The Arbitrator upheld the claim to the tune of Rs.90,000/-
holding that rescission of the contract on 23rd February, 1991 was unjust and wrongful
and forfeiture of security was, therefore, unjust. The Arbitrator has given reasons and
referred to the various correspondences between the parties. On the other hand, no
ground is made out by the respondent/DDA to set aside Award of this claim. This court
cannot act as a court of appeal hearing arguments on merits of the decision. The
Arbitrator's decision is based on evidence and, therefore, has to be respected.
4. Claim No.2 is for refund of Rs.70,000/- which was wrongfully withheld from the
second running bill. The Arbitrator has allowed this claim on the basis of respondent's
own documents wherein the respondent's Engineer had recommended for refund of this
amount. I find no reason made out by the respondent for setting aside this claim. The
claim is based on evidence as adduced before the Arbitrator.
5. Claim No.3 is in respect of Rs.5,000/- wrongly recovered from the 6th running
bill. This amount was recovered from 6th running bill in anticipation of grant of extension
of time. There is no provision in the Agreement between the parties that an amount can
be recovered from the bill in anticipation of granting extension. As and when the
extension is applied by the contractor, DDA can either extend the contract conditionally
or unconditionally or refuse an extension. If a condition is imposed of imposing penalty
at the time of extension, that penalty can be recovered subsequently from the bill but an
amount cannot be deducted from the bill in anticipation that a penalty would be imposed
without considering the grounds for extension. I, therefore, find no ground to set aside
award on this claim.
6. Claim No.4 was made by the claimant for refund of recovery of Rs.13,700/- at
double the issue rate of cement. The Arbitrator held that the respondent could not prove
the use of excess cement and the recovery at twice the issue rate was wrongful. The
recovery for cement could only be made at issue rate. He, therefore, allowed Rs.6,850/-
against this claim. It is contended by the respondent/DDA that Arbitrator has given no
reasons for awarding Rs.6,850/-. I find this argument baseless since the Arbitrator has
given reasons.
7. Claim No.5 made by the claimant was for Rs.35,000/- on account of balance
payment of the work done. The Arbitrator allowed payment of Rs.30,297/- against this
claim after considering the bill raised by the claimant and the fact that the payment was
not made against the bill. The DDA's contention is that according to the bill of the
claimant, the gross amount payable was shown as Rs.30,861/-. Out of this bill, 10 per
cent was to be deducted by way of security deposit, Rs.618 was to be recovered on
account of income tax and Rs.670/- was to be recovered on account of recovery for
cement and Rs.7,620/- on account of secured advance. The amount of Rs.10,295/- was
ultimately reflected under claim No.1 as the said amount of security deposit was put
under the said head and was released to the petitioner on furnishing the bank guarantee.
The Arbitrator has under claim No.1 directed the release of amount of bank guarantee,
however, the Arbitrator overlooked and did not take into consideration the other three
recoveries, namely, income tax, recovery for cement and recovery for secured advance
which were given by the DDA to the contractor and has taken into consideration the gross
amount of bill irrespective of recoveries. The learned Arbitrator has not rejected or
accepted the recoveries and observed that the recoveries shown in the bill were unjust and
thus, left the matter undecided. The recoveries to be effected from the contractor were to
the tune of Rs.19,903/- thus, the net amount payable to the respondent against the bill was
Rs.10,958/-. Out of this the credit of Rs.1,370/- as allowed by the Arbitrator has to be
adjusted and thus, the only amount which could have been awarded by the Arbitrator was
Rs.10,958/- minus Rs.1,370/-. The contention of the contractor is that only recovery of
Rs.1,370/- against cement was admissible. Rests of the recoveries were unjust and that is
why the Arbitrator has allowed the claim of the contractor. It is further submitted that the
security deposit of Rs.10,295/- could not be enforced since the claimant had furnished
bank guarantee for security deposit and the learned Arbitrator had discharged the bank
guarantee which was given in the form of security deposit. Thus, the amount of
Rs.10,295/- was not admissible. It is stated that the award of the Arbitrator on this count
has become final. However, the claimant has not refuted the contention of the respondent
that out of the bill raised by the contractor, the respondent was liable to deduct income tax
and recovery of Rs.7,620/- on account of secured advance. It is not disputed that before
the start of contract, advance was paid to the contractor which was to be adjusted out of
the running bill raised by the contractor, therefore, this secured advance had to be
deducted out of the bill of the contractor. Obviously, the Arbitrator has not taken into
account the recovery of income tax and secured advance. Maybe Rs.10,295/- by way of
security deposit was not liable to be recovered but rest of the recoveries were to be made
and the Arbitrator ignored this fact.
8. I, therefore, consider that this award of the Arbitrator is required to be modified
and out of the amount of Rs.30,297/- allowed by the Arbitrator, a deduction of Rs.7,620/-
towards secured advance, Rs.618/- as income tax are additionally required to be
recovered. The Award of the Arbitrator against this claim is, therefore, modified and a
sum of Rs.21,959/- is upheld as the justified amount payable to the claimant.
9. Claim No.7 made by the claimant was for Rs.13,000/- on account of extra cement
concrete. The Arbitrator has allowed this claim. The contention of the respondent is that
the Arbitrator has failed to give reasons as to how he found the said claim to be payable.
A perusal of the Award shows that the Arbitrator has referred to the order book and
instructions given to the respondent for providing extra 6" thick C.C. cover collars. Since
the claimant had fulfilled these instructions, the claimant was entitled for the payment on
this count and the Arbitrator had come to a conclusion that the claim made by the
claimant of Rs.13,000/- was on the lower side and was to be allowed. I find no reason to
disturb the Award.
10. Claim No.8 was made by the claimant for Rs.99,840/- on account of providing
SFRC manhole covers. The learned Arbitrator after considering the evidence awarded a
sum of Rs.75,473.65 in favour of the claimant. The objection of DDA is that the analysis
given by the claimant of Rs.520/- per cover was not supported by any cogent evidence.
Secondly, manhole No.157 was not constructed and the petitioner could not have
provided 191 numbers of covers and at the best it could have been 190 covers. The
Arbitrator has considered the entire evidence even if it is considered that instead of 191 it
were 190 covers, the difference in cost was around Rs.400/-. Thus, the award allowed by
the Arbitrator would have gone down by Rs.400/-. It is true that the Arbitrator had taken
full 191 covers instead of 190 covers. The difference between the cost of SFRC cover
and RCC cover being only Rs.395.15, the Award made by the Arbitrator is modified to
the extent that instead of Rs.75,473.65, the claimant would be entitled to Rs.75,078.50.
11. Claim No.9 was made by the claimant for Rs.1,75,000/- on account of execution
of work beyond the stipulated date of completion by claiming 25 per cent extra on
contract rate. There is no provision in the contract that if the work goes beyond the
stipulated date, the contractor would be entitled for extra rates @ 25 per cent of the work.
The contract vide clause 10C specifically deals with situation if there is an escalation in
the price of labour and material during progress of the contract and clause 10CC
specifically deals with the escalation in the wages of labour and the price of material
during the extended period. Once period of contract is extended and if there is escalation
in the price of labour and material, the contractor can only lay claim under Clause 10C or
10CC but there is no provision that where period of contract is extended or the contract
gets prolonged, the contractor's tender rates shall stand increased by 25 per cent or the
quantity rates shall increase by 25 per cent. It is settled law that an Arbitrator is prisoner
of the contract and he cannot grant compensation, which is not provided by the contract.
The Arbitrator in this case had allowed the claim of the contractor under Clause 10CC
vide claim No.11. I, therefore, consider that the award of Rs.1,35,511/- allowed by the
Arbitrator against claim No.9 was not tenable and contrary to the contract.
12. Claim No.10 was made by the claimant/contractor for a sum of Rs.31,506.25 on
account of execution of work under water. The claimant's claim was that he was entitled
for additional payment apart from contractual amount since he had to work under water
for excavation of trenches and laying of pipes. The learned Arbitrator allowed this claim
of the claimant in toto saying that it was a justified claim. It is submitted by DDA that
the letter on which the Arbitrator had relied does not give any details with regard to the
claim and the learned Arbitrator has based his decision on non-existent material and there
was gross application of mind. The contention of the claimant is that the learned
Arbitrator has decided the claim on the basis of evidence, namely, letters C-44, C-39 and
C-32 and the court cannot upset the Award as the court cannot go into merits. There was
no error apparent on the face of the award. The contractor in this case was awarded
contract of laying sewerage lines. The trenches, etc., were to be dug for laying the
sewerage lines. All rates in respect of digging trenches were agreed between the parties.
In all other claims wherever the contractor had made a claim for extra item, the contractor
had relied upon an order book or measurement book. In this case, there is no evidence of
execution of the work by the contractor by way of measurement book nor there is any
evidence on record that the trenches were dug under water and work was done under
water. It would be seen that the contractor had been writing letters to DDA during
progress of the work making various claims and seeking additional payment in respect of
various things. Mere writing of letter by contractor seeking additional payment does not
amount to evidence of the contractor of performing additional work or work beyond the
contracted items. If any contractor claims that he had executed work beyond the contract
or in respect of some item which was not provided for under the contract, he is supposed
to prove his claim by measurement book or by an order placed on him. Self-supporting
letters are not the evidence of extra items. I, therefore, consider that the learned
Arbitrator in this case allowed this claim without there being any evidence and the award
on this count is liable to be set aside.
13. Claim No.11 was made by the claimant for a sum of Rs.90,000/- on account of
reimbursement of increase in cost of work under Clause 10CC of the contract. The
learned Arbitrator after considering the cost index and taking into account the stipulated
date of completion and the actual date of completion had allowed an amount of
Rs.17,143/- in favour of the claimant. The respondent has raised objection that the
Arbitrator has not given reason as to how he arrived at the said figures. A perusal of the
proceedings shows that the Arbitrator did take into account the relevant index and the
charges. I, therefore, find no reason to set aside this Award under claim No.11.
14. Claim No.12 is for Rs.5,831.48 on account of extra waste for laying C.C. under
pipes due to revision of slopes. The Arbitrator allowed this claim. The respondent's
contention is that the Arbitrator has not given reasons and, therefore, the Award was
liable to be set aside. I find that the Arbitrator has given reasons and relied upon the
document showing that the respondent had revised the gradient for laying pipes. The
claimant had also furnished details about this revision of gradients and the amount spent
by the claimant. I find no reason to set aside the Award.
15. Claim No.13 was made by the claimant for a sum of Rs.19,062.83 on account of
extra brick work in the manholes. The learned Arbitrator allowed claim of Rs.15,690.11.
A perusal of contract (item 5) would show that the item provided "construction of brick,
circular type manhole with FPS bricks with 90 cm internal diameter at the bottom and 90
cm depth with C.I. frames of heavy duty on the top." The thickness of RCC cover is
given as 12 cm, however, there is no thickness of the brick work provided under this item
and it is obvious that the manhole was supposed to be heavy duty and strong enough to
bear the burdens of vehicles passing over it. This claim could have been allowed only if
the contractor had done something extra than what was provided in the contact. The
contract does not provide that the thickness of the wall of manhole was to be 9 inch.
Normally in all manholes, the thickness of wall is to made in accordance with the location
of the manhole i.e. if the manhole was to come in between the road or it was to remain at
an isolated place where no vehicle was to pass. "There was no specification given in the
contract that the manhole was to have side wall thickness only of 9 inch. The contractor
was told that thickness of 9" being provided by him was not suitable for the structure
consideration and he was advised to provide first course of 18 inches, second course of 13
½ inches and then start 9 inches brick work. This does not amount to any additional work.
The contractor had not specified in his tender that in the manhole, he was only going to
provide 9 inches wall throughout and he was not going to give first course of 18 inches
and second course of 13 ½ inches and then course of 9 inches brick work which is the
normal mode of construction of manholes. The claim of the claimant was, therefore, not
tenable in view of the contract between the parties. Thus brick work cannot be termed as
an extra work. If the DDA had pointed out that manhole was not of requisite strength and
needed additional strength that does not mean that the respondent had asked the
contractor to do additional work. The award against claim No.13 is, therefore, liable to
be set aside.
16. Under claim No.15, claimant claimed Rs.78,000/- and the Arbitrator allowed this
amount to him despite observing that the work was executed by the claimant as per
agreement item No.4. A perusal of agreement item No.4 would show that this item
included "providing and laying (light duty) non-pressure NP2/NP3 class, S & S R.C.C.
pipe with rubber ring confirming to ISI standard". A perusal of claim of the claimant
would show that the claimant had asserted that in the tender, schedule of quantity
contemplated provision of non-pressure NP2/NP3 class S & S RCC pipe with rubber ring.
However, his contention is that he was invited for negotiation and for reduction of rate
and he reduced rate from 38.5 per cent to 34 per cent and he clarified the rate for item
No.4 of schedule of quantities would be for NP2 class pipe. He submitted that in NP2
class pipe no rubber rings are required, but in the present case in addition to cement
concrete in the joints, he also provided rubber rings and, therefore, he was entitled for
additional amount of Rs.78,000/-. The respondent had raised objection that the Arbitrator
despite observing for the item was executed as per agreement had allowed claim of
Rs.78,000/- and this was an error apparent on the fact of it. There was no question of
awarding any extra amount since the work had been executed as per the agreement. The
contractor has refuted this and stated that he had made it clear that he would be using only
NP2 pipe, during negotiation. A perusal of the negotiation letter written by the contractor
during negotiation would show that the contractor had agreed for reduction of his rates
and observed that he would be using NP2 pipes, however, he had not stated that he would
not be using rubber rings for joints while using NP2 pipes. There is no dispute that he has
used NP2 pipes but he staked an additional claim for using rubber rings at the joints. It
was made clear in the tender document and in the contract which he signed after
negotiations that the joints are to be made by rubber and concrete. The specification
clearly shows S & S NP2 pipe with rubber. Thus, there was no confusion at the time of
execution of the contract. The item was executed as per the contract. There was no
reason for the Arbitrator to award additional amount. The award under claim No.15 is,
therefore, liable to be set aside.
17. Claim No.16 was raised by the claimant for Rs.12,783.60 as an extra amount for
excavation of malba. The Arbitrator allowed a sum of Rs.7,348.44 after relying upon the
letters written by the claimant that there was some malba in the alignment of the
sewerage line over the area. The claim has been allowed without any evidence of
removal of malba, only on the basis of analysis. I consider that no claim for extra work
can be allowed without proof of the work having been done, only on the basis of analysis.
In all civil works which are awarded by DDA to the contractor, a measurement book is
maintained and execution of all works, step by step are recorded in the measurement book
whenever an extra work is required to be done an order is to be placed by Engineer In-
charge and a cost analysis is to be given by the contractor and the Engineer In-charge has
first to accept the cost analysis in terms of clause 12. An extra work may be withdrawn
from the contractor if cost analysis is not acceptable to the Engineer In-charge. However,
there is required to be evidence that extra work was ordered to be done and it was
executed in terms of the order. In absence of evidence, mere correspondence of the
contractor that he had to do extra work cannot be a ground for allowing the claim by the
Arbitrator. The Arbitrator is bound by the contract and no extra item can be allowed by
the Arbitrator unless it has been executed in accordance with the contract and evidence is
produced before the Arbitrator of execution of the extra work. I, therefore, consider that
Award of Rs.7,348.44 for removal of malba from the site is not tenable.
18. Claim Nos.21 and 22 are in respect of allowing interest by the Arbitrator over the
withheld amount. After perusal of the Award, I find that the Arbitrator has justifiably
allowed amount against both these claims as I find that the DDA had wrongfully withheld
the amounts of the second running bill and released the amounts belatedly. I find no
reason to justify the Award of these two claims.
19. Claim No.24 has been allowed by the Arbitrator for a sum of Rs.12,000/- on the
basis of record maintained by the respondent. The respondent has stated that the
Arbitrator had not given any reasons for allowing the claim. I find that this contention
untenable since the Arbitrator had given reasons and relied upon the documents showing
the execution of the work. I, therefore, find no reason to justify the Award against this
claim.
20. Claim No. 26 has been allowed by the Arbitrator on account of damages on the
ground that the contractor had to maintain his establishment unproductively beyond the
stipulated rate of completion since it was DDA who was responsible for the delay in the
work. The claim had been allowed on hypothetical grounds without their being any
material before the Arbitrator that the establishment was actually maintained by the
contractor. There is no presumption that a contractor undertakes only one civil work at a
time and he maintains his establishment for that purpose. A contractor may be having at
hand at one point of time many contracts. It is more likely so because looking into the
manner in which payments are released by the DDA and the pace of work, it is not
possible that a contractor and his staff could survive with one work. The contractor is to
maintain his establishment for all works which he has at hand at one point of time. If a
contractor claims that he kept his staff that is Engineer, Supervisor, Mechanic, etc., posted
at the site idle, he is supposed to prove the same in order to claim the damages on account
of maintaining the establishment. The contract between the parties specifically provides
that the contractor shall maintain attendance register of all the workmen and he shall
submit this attendance register to the employer, that is, DDA from time to time. He is
also supposed to maintain wage book of each worker with full particulars of the employee
employed by him. Unless and until the contractor placed before the Arbitrator the names
of the persons employed by him and kept posted at site with sufficient evidence that those
employees and Engineers remained idle and did not work at his other works and he had
engaged separate Engineer and Supervisor for his other works, he cannot claim damages
on account of keeping idle establishment. Keeping an establishment idle cannot be a
presumptive factor. It is a real factor and has to be proved by real evidence. Cost
analysis of keeping an establishment cannot be a basis for awarding an amount to a
contractor. This will rather to be a premium on delaying the work. A contractor would
deliberately delay the work and then claim that he has to keep his establishment idle. He
would also claim damages under Clause 10 CC and it is not a difficult task to delay the
work when we have departments like DDA and MCD where the work culture is so
helpful to the contractor that every contractor ends up not only receiving with the
contractual amount but receiving almost equal amount through arbitration awards. I,
therefore, consider that the claim allowed by the Arbitrator under Claim No.26 is not
tenable and not as per terms of the agreement and liable to be set aside.
21. Claim No.27 has been allowed by the Arbitrator for a sum of Rs.2,275/- on
account that the contractor had to pay extra commission during prolongation of the
contract for maintaining bank guarantee. The contractor produced a bank certificate of
Rs.2,275/-. Since it has been held by the Arbitrator that the contract got prolonged due to
fault of DDA, I consider that the Arbitrator rightly allowed this amount.
22. Claim No.28 is in respect of allowing interest. The Arbitrator has awarded
interest @ 14 per cent per annum from 3rd September, 1990 till date of Award and he
allowed further interest of 14 per cent from the date of Award till realization. I consider
that the rate of interest @ 14 per cent upto the date of Award was justified in view of the
interest regime prevalent earlier. However, rate of interest @ 14 per cent per annum from
the date of Award till realization is on higher side in view of the fact that interest regime
changed in this country in late Nineteen. I consider that an interest of 10 per cent per
annum on the awarded sum including interest upto the date of Award will be a reasonable
interest. I, therefore allow 10 per cent interest on the awarded amount from the date of
Award till realization.
23. The Arbitrator also dealt with counter claims and rejected all counter claims of the
respondent holding that it was respondent due to whom the contract got prolonged. I find
no reason to set aside the award on counter claims.
24. Subject to the modifications in respect of claims set aside by this court or
modified by this court, the Award made by the Arbitrator is made Rule of the court. The
objections are allowed to the extent observed above.
25. The petition stands disposed of accordingly.
SHIV NARAYAN DHINGRA J.
DECEMBER 23, 2009 'AA'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!