Citation : 2009 Latest Caselaw 5344 Del
Judgement Date : 22 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ COMPANY PETITION NO. 469 OF 2009
AND
COMPANY APPLICATION NOS.1549-1550/2009
Reserved on : November 23, 2009
Date of Decision : December 22, 2009
M/S RITIKA PVT. LTD.
........Petitioner
Through Mr. Dinesh Agnani, Advocate
Versus
M/S OMAXE CONSTRUCTION LTD.
......Respondent
Through : None.
CORAM :
HON'BLE MR. JUSTICE SUDERSHAN KUMAR MISRA
1. Whether Reporters of local papers may be allowed to see the
judgment?
2. To be referred to the Reporter or not ?
3. Whether the judgment should be reported in the Digest ?
SUDERSHAN KUMAR MISRA, J.
1. This is a petition under S.433 of the Companies Act, 1956
for winding up of M/s Omaxe Construction Ltd, along with
CA.No.1549/09 for appointment of a Provisional Liquidator. The
respondent company carries on the business of construction and is
stated to have been incorporated under the Companies Act, 1956 in
1989 and has its registered office in New Delhi.
2. On 23rd June, 2006, the petitioner company/Intending
Lessee entered into an unregistered Agreement to Lease with the
respondent company/Intending Lessor for opening a showroom in
premises bearing No. GF 37, located on the Ground Floor at Plot
No.3/26, Bye-pass Road, Ward Hari Parwat, Agra, Uttar Pradesh, having
a super area of approximately 204.51 square metres. The said
Agreement has been annexed to the petition as "Annexure B". Clause
3 thereof states that the lease was initially for a period of 3 years, to
be calculated from the date of the grant of a Completion Certificate by
the concerned authorities, to be renewed for a further 2 terms of 3
years each at the option of the Intending Lessee, on terms and
conditions to be mutually decided as per the Agreement. The
respondent company was to undertake the construction of a Mall at
the Demised Premises, which would thereafter enable the Intending
Lessee to carry on the business of garments and apparel under the
brand/trade name of „Ritu Kumar‟. Clause 2 of the Agreement states
that the said Mall was to be constructed by the Intending Lessor by 31st
March, 2008, which would be extended in the case of force majeure
circumstances and/or reasons beyond the control of the Intending
Lessor.
3. The petitioner company, as per its obligations under Clause
6 of the Agreement, paid the respondent a total sum of Rs. 4,62,276/-
vide Cheque Nos. 788104 and 412218, drawn on Citi Bank, Delhi,
towards an interest-free security deposit equivalent to three months‟
rent. Part of this payment was made prior to the signing of the
Agreement, and the balance was paid at the time of signing of the
Agreement. The petitioner states that the second cheque was
encashed on 1st June, 2006, and that the said deposit was subject to
compliance with the terms and conditions stipulated in the Agreement
to Lease dated 23rd June, 2006.
4. The respondent company did not complete the
construction of the Demised Premises/Mall by the stipulated time.
Consequently, the petitioner company sent a registered legal notice
dated 8th December, 2008 to the respondent company, a copy of which
has been annexed to the petition as "Annexure C", stating that the
respondent company had defaulted in fulfilling its obligations under the
Agreement, and that the petitioner company was no longer interested
in taking possession of the Demised Premises. By that notice, it was
also stated that the petitioner company terminated the Agreement to
Lease, and asked for a refund of the security deposit from the
respondent within 15 days of receipt of the notice by the respondent.
Proof of service of this notice is also on record.
5. It is the case of the petitioner that more than 17 months
have lapsed since the date on which the Mall was supposed to be
constructed and that, till date, the petitioner has not been handed over
possession of the Demised Premises. A personal inspection of the
construction site by officers of the petitioner company, photographic
evidence of which has been annexed as "Annexure D" to this petition,
reveals, according to the petitioner, the fact that the said Mall is
nowhere near completion.
6. In reply dated 2nd March, 2009 to the aforesaid legal notice,
the respondent claimed that there had been a short delay in the
completion of the project on account of reasons beyond its control.
Clause 2 of the Agreement to Lease is relied on by the respondent in
support of the contention that the stipulated time to complete the
project is extended on account of these „force majeure‟ circumstances
and/or reasons beyond the control of the respondent. However, the
respondent has not given any specific reasons in the reply dated 2 nd
March, 2009 in support of this contention. It is also claimed by the
respondent that the construction is on in full swing, and is very nearly
completed. Further, the respondent admits that the payment made by
the petitioner towards the security deposit is a matter of record, and
that after completion of the construction, will be utilized in obtaining a
number of approvals from the concerned authorities.
7. It is also averred by the respondent that the said
Agreement to Lease could not be terminated by the legal notice dated
8th December, 2008 sent by the petitioner, since, according to the
respondent, the Agreement to Lease specifically provided for
arbitration to resolve any disputes and differences arising between the
parties, in Clause 20 thereof. Therefore, the respondent alleges that,
as the Agreement to Lease could not be terminated by a legal notice,
there is no question of refund of the aforesaid security deposit.
8. The petitioner then delivered a notice of winding up dated
2nd May, 2009 at the registered office of the respondent company in
Delhi, proof of which is annexed to the petition as "Annexure F", calling
upon the respondent to refund the amount of Rs.4,62,276/-, and
interest @ 1.5% from the date of the notice, as well as costs of sending
the legal notices, which amounted to Rs.11,000/-. The respondent did
not reply to the said notice of winding up.
9. At the outset, it is a well-known principle that the
respondent‟s failure to reply to the notice of winding up does not mean
that winding up orders must invariably be passed. This Court has held
in Resham Singh & Co Pvt Ltd v Daewoo Motors India Ltd,
[2003] 116 CompCas 529 (Delhi), that "where no response had been
made to the statutory notice the Respondent Company runs the risk of
a winding-up petition being admitted for hearing at the threshold stage
itself." It has further been held, in the same case, that "Normally, the
Company Judge considers it prudent in the first instance to issue notice
to the Respondent so that its defense to the possible far-reaching and
fatal winding-up orders can be considered. The admission of the
Petition at its first hearing is possible because, by virtue of Section 434
of the Companies Act, a presumption of the indebtness can be
legitimately drawn by the Court where no Reply to the statutory notice
is forthcoming. The risk of the admission of the Petition, as well as the
appointment of a Provisional Liquidator is thus broodingly and
ominously present in all those cases where the Respondent Company
neglects to send any Reply to the winding-up notice. But this is as far
as the danger extends."
10. The Agreement to Lease is an unregistered document. As
per Clause 19 of the Agreement to Lease, it is clear that the
Agreement is to be treated as a binding contract enforceable between
the parties till the execution of the Lease Deed. Clause 16 of the
aforesaid Agreement also stipulates that the Intending Lessor and the
Intending Lessee undertook to execute the Lease Deed after the grant
of a Completion Certification from the authorities concerned. However,
as construction of the Mall is yet incomplete, therefore, there is no
question of grant of a Completion Certificate or the consequent
execution of the Lease Deed.
11. An order of winding up on the ground that a company is
unable to pay its debts is a discretionary remedy. In the instant case,
the petitioner had deposited a certain amount of money as a security
deposit, in terms of the Agreement between the parties. On the
respondent‟s failure to fulfill its obligations under the said Agreement,
the petitioner chose to terminate the Agreement by a written notice,
and called for refund of the security deposit. In view of the fact that the
Agreement to Lease was an unregistered document, as well as the fact
that month-to-month leases may be terminable by 15 days‟ notice, it is
clear that the said Agreement was terminated unambiguously by the
petitioner, once it became apparent that the respondent was unable to
hand over possession of the Demised Premises within the stipulated
time. Further, in reply to the legal notice, the respondent has not
denied the fact of the payment of the security deposit by the
petitioner.
12. In Polaroid India Pvt Ltd. v Nav Nirman Co & Ors,
[2001] 105 Comp Cas 683 (Bom), the Bombay High Court admitted a
winding up petition on the ground of non-payment of a security deposit
in consideration of a leave and license agreement, despite termination
of the same by a written notice.
13. The remedy of arbitration is not an alternative to the
initiation of winding up proceedings. In Haryana Telecom v Sterlite
Industries India Ltd, AIR 1999 SC 2354, it has been held, in
paragraph 6 thereof;
„The claim in a petition for winding up is not for money. The petition filed under the Companies Act would be to the effect that the company has become commercially insolvent and, therefore, should be wound up. The power to order winding up of a company is contained under the Companies Act and is conferred on the court. An arbitrator, notwithstanding any agreement between the parties would have no jurisdiction to order winding up of a company.‟
14. Therefore, it is within the discretion of the Company Court
to entertain the company petition, even if there is an arbitration clause
in the Agreement between the parties.
15. I therefore feel, prima facie, that the claims raised by the
respondent in reply to the legal notice are not within the domain of
bona fide and substantial defences. In that view of the matter, let
notice issue to the respondents to show cause why the company be
not wound up, returnable for 4th May, 2010.
SUDERSHAN KUMAR MISRA, J.
December 22, 2009 sl
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!