Citation : 2009 Latest Caselaw 5296 Del
Judgement Date : 18 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.S. (OS) No.775-A of 1994
%
M/S. KAMAL CONSTRUCTION COMPANY ......Petitioner
Through: Mr. Raman Kapur, Advocate.
Versus
DELHI DEVELOPMENT AUTHORITY & ANR. ......Respondents
Through: Mr. Ajay Verma, Advocate.
Date of Reserve: 7th September, 2009
Date of Order: 18th December, 2009
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment? Yes.
2. To be referred to the reporter or not? Yes.
3. Whether judgment should be reported in Digest? Yes.
JUDGMENT
1. By this petition under Sections 14, 17 and 29 of the Arbitration Act, 1940
(hereinafter referred as „the Act‟), the objector/respondent (DDA) has filed objections
under Sections 30 and 33 of the Act against Award dated 30th December, 1993 given by
the Sole Arbitrator, Sh. R.C. Malhotra (respondent No.2 herein).
2. The brief facts relevant for the purpose of deciding this petition are that the
petitioner entered into a contract with DDA for construction of houses under S.F.S.
Scheme at Tughlakabad opposite Hamdard Nagar on Mehrauli Badarpur Road vide an
agreement No.17/EE/HD-XXXV/85-86. In terms of this agreement, 108 dwelling units
and 72 car garages with internal development were to be constructed. The dwelling units
included 36 Category II and 72 Category III units. However, due to some reasons, there
was delay in making the site for construction available to the contractor. The contractor
vide letter dated 4th November, 1986 asked DDA to allot it an alternate site for the
construction of the dwelling units. In this letter, he assured DDA that he would not claim
any loss or damage, etc., in respect of the work previously allotted to him. After this
request of the contractor, the DDA awarded a new contract vide a letter of award dated
10th February, 1987 to the contractor for construction of same number of dwelling units at
Sai-Dul-Jaib opposite Saket. The work was covered under the new agreement
No.16/EE/UVD-I/DDA/86-87. The work under this agreement was completed by the
contractor on 20th February, 1989 against stipulated date of completion of 19th May, 1988.
The contractor had raised 18 running bills during the continuation of the work and 19th
bill was the final bill raised by him and paid to him by the DDA. The bill was accepted
as full and final. However, after acceptance of the bill as full and final, the contractor
invoked arbitration vide his letter dated 19th September, 1989 and on his invoking
arbitration, the Persona Designate appointed an Arbitrator to go into the claims of the
contractor. The learned Arbitrator entered into reference on 26th July, 1990 and gave the
impugned Award allowing various claims raised by the contractor and rejecting some of
the claims raised by the contractor. The DDA assailed the Award on the ground that the
Award passed by the Arbitrator was not based on any evidence as no evidence was
produced in support of the claims by the petitioner. The Award was also not justified
being contrary to terms and conditions of agreement and the claims raised by the
contractor were barred by period of limitation. The claims were also not covered under
the agreement. The DDA has raised claim-wise objections, apart from making general
objections. The claim-wise objections are being dealt with here under.
3. Claim No.2, allowed by the Arbitrator is for Rs.713.99 on account of penal rate
recovery of steel and other materials. A perusal of claim made by the contractor would
show that contractor has not given any detail as to how the claim was justified. Similarly,
perusal of Award shows that the Arbitrator has not stated how the consumption of steel
was within permissible variations. The only observation made by the Arbitrator is that no
notice under Clause 42 for return of the surplus material was made. A perusal of Clause
42 of the contract would show that there is no provision for giving a notice by DDA to the
contractor. What is provided is that the contractor has to draw only required quantities of
material from DDA and return the unused quantities at a place to be told by the DDA.
The consumption of the material has to be calculated on the basis of theoretical formula
as applicable for civil constructions on the basis of CPWD statement of quantities or on
the basis of Delhi Schedule of Rates, 1981 with variations as provided under the contract.
4. This court had time and again emphasized that where the reasons are to be given
by the Arbitrator, the Arbitrator has not only to give his conclusion, but the verdict given
by the Arbitrator must have a rational nexus between the amount awarded and the
evidence placed on record. In the case of College of Vocational Studies Vs. S.S. Jaitley;
AIR 1987 Delhi 134, a Division Bench of this court deprecated the habit of giving mere
conclusions and the verdict, without giving any reasons and observed that reasons are the
links on the material documentary or oral evidence adduced before the Arbitrator, on
which certain inferences are drawn and calculations are made. The Arbitrator may not set
out every process of reasoning or may not deal with every point raised but must, when he
is called upon to give reasons, tell the reasons why he came to a particular conclusion.
5. In the present case, the Arbitrator while awarding this amount has just given his
conclusion without showing how the quantity was within permissible variations when the
agreement specifically provided what were the variations available at the theoretical
quantities. I, therefore, consider that the Award against claim No.2 was not tenable being
contrary to arbitration clause wherein it is provided that the Arbitrator is supposed to give
reasons. The total Award in this case has gone in lacs but the Arbitrator has not adhered
to this clause of giving reasons.
6. Claim No.3 is allowed by the Arbitrator for a sum of Rs.67,281.21. This amount
was deducted by the DDA on account of sub-standard work against certain items done by
the contractor. The plea taken by the Arbitrator is that the completion certificate recorded
by the Engineer in-charge, after the work had been completed, does not indicate the
defects on account of which rates were reduced. Surprisingly, the Arbitrator has become
oblivious to the fact that deductions were not made just before grant of completion
certificate but these deductions were made because of sub-standard work done by the
contractor during the progress of the work while approving the running bills. In case of
civil constructions, the work done at different stages gets concealed because of the
subsequent work which is required to be done. When foundation is dug and laid, the
foundation is inspected and running bill for foundation up to DPC level is raised and is
required to be approved. The Engineer In-charge or the Superintendent Engineer has to
consider the defects in the foundation at that time or if any sub-standard material had
been used and deductions are made at that time. Once the work starts above foundation,
the foundation gets covered from both the sides by soil and from top by walls and pillars
which are erected over the foundation and all defects of sub-standard material of the
foundation get concealed. Similarly, when walls are erected and say bricks or other
materials of sub-standard quality is used, the Superintendent Engineer or Engineer In-
charge can deduct the amount from running bill on account of sub-standard material used.
Once the walls are covered by plaster, nobody can find out whether the bricks used on the
wall were of sub-standard or requisite quality. Similarly, in case where bill for plaster is
to be raised whether the workmanship of the plaster is of the requisite quality, the
thickness of plaster was the same as required under the agreement can be checked at the
stage when plaster is just over by scratching the plaster from different places and
measuring the depth of the plaster and looking at the quantity. However, once the plaster
is complete and the wall is covered with distemper, POP and other inner finishes, nobody
can find out from looks whether the plaster was of requisite depth and was of proper
finish and equal depth at all places. It is for this reason that Clause 25 (B) of the
agreement provides that „the decision of superintending Engineer regarding the quantum
of reduction as well as justification thereof in respect of rates for sub-standard work
which may be decided is to be accepted as final and would not be open to arbitration‟.
Despite Clause 25 (B) being there in the contract regarding reductions, learned Arbitrator
entered into the area which was not within his jurisdiction and for which he had no means
to find out whether the reduction was made rightly or wrongly.
7. I, therefore, consider that Award of the learned Arbitrator in respect of Claim
No.3 awarding amount of the reductions made for sub-standard work is unjustifiable,
without jurisdiction and liable to be set aside. A completion certificate is not supposed to
contain those defects which were found by the Superintendent Engineer during progress
of the work. A completion certificate only specifies the final stage of completion and the
deficiencies to be made up by the contractor at the final stage. The deficiencies which
existed at different stages of construction are to be taken care of at those stages only and
all deductions made by Superintendent Engineer out of the running bills regarding sub-
standard workmanship or sub-standard material cannot be assailed after the final bill or at
final stage. A contractor may very well raise objection against the deductions
immediately with the Superintendent Engineer when deduction is made. The
Superintendent Engineer being the final authority has to decide if the deduction was
justifiably made or not. The Arbitrator cannot enter into this area. I, therefore, consider
that Award of the Arbitrator regarding Claim No.3 for Rs.57,043.09 is liable to be set
aside on this ground.
8. Claim No.14 of the claimant as made by the contractor was for Rs.9,300/- on
account of render/plastering RCC in shelves. The claim has been allowed by the
Arbitrator on the ground that respondent did not produce records to ascertain the
admissibility of the claim. It is very surprising that a claim can be allowed in such a
manner. A claimant, who files the claims, has not only to give reasons for the claim but
produce evidence in proof of it. The only reason given by the claimant in the statement of
claim is "contractor claims a sum of Rs.9,300/- on account of render/plastering RCC in
shelves. No justification is given and no measurement of RCC shelves plaster is given.
No calculation giving the quantity of plaster and the rate of plaster is given as to how this
claim arises. Similarly, learned Arbitrator also gives no reasons why he was allowing
Rs.7,136/- as to what was the quantity of plaster, how many under shelves were there,
what was the rate of plaster and how he arrived at this figure. No evidence whatsoever is
on record.
9. Claim No.15 is in respect of cutting chase in masonry. The Arbitrator has found
that 108 meters of chase was admissible and awarded Rs.318.60 considering the rate of
chase. Cutting chase for laying RCC shelves is part of the process for laying RCC
shelves and cannot be considered a separate item. Chase is cut so that steel reinforcement
has a grip in the wall and to give support to RCC shelves. Cutting chase cannot be treated
as a separate item. The Award is liable to be set aside.
10. Claim No.16 was made by the claimant for Rs.4,288.17 on account of under
payment of quantity against laying wearing coarse. While the claim was only for
Rs.4,288/-, the Arbitrator awarded a sum of Rs.9,564/-. The Arbitrator had given no
reason except that the payment for the item has not been made correctly. I consider that a
contractor is most careful and knows much better about payment made and due.
However, the contractor asked for additional claim of Rs.4,288/- on the ground of under
payment and he got almost double the amount without any reason given by the Arbitrator
and without evidence. The Arbitrator is not supposed to give his conclusions but is
supposed to give reasons. The Arbitrator in this case has not given what was the payment
already received, what was the payment due in terms of the agreement and how the
payment already received was short. I, therefore, find that Award of this claim is without
evidence or reasons and also beyond the claim and is liable to be set aside.
11. Claim No.19: The claimant had claimed Rs.38,86,227/- on account of infructuous
expenditure and damages sustained by the claimant due to various breaches. The claim of
damages was made by the claimant/contractor in respect of original agreement dated
25th January, 1986 as well as in respect of the subsequent agreement dated 10th February,
1987. The plea taken before the Arbitrator was that the letter written by the contractor to
DDA, that contractor shall not claim any loss or damages if an alternate site is allotted,
was written under coercion and, therefore, this letter was of no value and effect and the
contractor was entitled for damages because the site under the earlier contract was not
allotted to the contractor within time. The learned Arbitrator observed that it was hard to
believe that anyone would give such a undertaking of foregoing a claim of loss, which
was on account of serious breach of contract on the part of DDA. He concluded that he
was fully convinced that undertaking was given under coercion and undue influence and
claim of claimant cannot be set aside on the basis of arguments advanced by the DDA
that no damages can be allowed in respect of previous contract.
12. It is apparent that the learned Arbitrator grossly misconducted himself in arriving
at this conclusion. The earlier contract between the parties had come to an end, the
moment a new contract was issued by the DDA in favour of the contractor for
construction of the same number of houses at a new site. This new contract was awarded
to the contractor since DDA was, for whatever reasons, not able to offer the earlier site
for construction. The contractor had allegedly made arrangements for working at the
earlier site. When he found that earlier site was not likely to be available soon, he wrote a
letter to the DDA that he should be given alternate site with the same amount of work and
he would not raise any claim for damages. The letter dated 4th November, 1986 written
by DDA makes it abundantly clear that this letter was written by the contractor not after
any negotiations with DDA or after any pressure from DDA but the letter was written by
the contractor after making it known to DDA that DDA had not been able to give site to
him to undertake the work despite exchange of correspondence between the parties and
despite contractor raising claims of damages against DDA. The contractor made it clear
to DDA that since he was class I registered contractor, he was ready to work on the
alternate site if it is given to him by 5th December, 1986 and shall not claim from DDA
any loss or damages incurred by him such as for setting up office, stores, stacking of
material, labour huts, water tanks or making any arrangement/commitment in this
connection. He specifically wrote that the correspondence exchanged between the parties
upto that date shall stand superseded automatically in case DDA gives an alternate site.
He further made it clear that the offer was unilateral without any reservations.
13. The statement of law regarding coercion has been given in following terms in
Halsbury‟s Laws of England :-
"By duress is meant the compulsion under which a person acts through fear of personal suffering as from injury to the body or from confinement, actual or threatened. A threat of a criminal prosecution for which there is sufficient ground is not such duress as will vitiate a contract made in consequence thereof, provided that there is valuable consideration for the contract, and that there is no agreement to stifle the prosecution. There is no duress simply because a party has to enter into a contract by reason of statutory compulsion, or the fact that the other party is a monopoly supplier. Moreover, as a general rule, a threat of civil proceedings or bankruptcy proceedings does not amount to duress, whether there is good foundation for the proceedings or not; but it may do so if it is intended and calculated, having retard to the circumstances, to cause terror in the particular case. The question whether imprisonment or threatened imprisonment does or does not constitute duress depends upon whether the imprisonment is lawful or unlawful.
A contract obtained by means of duress exercised by one party over the other is at very least voidable, and may perhaps be void, but if it is voluntarily acted upon by the party entitled to avoid, it will become binding on him. The duress must be actually existing at the time of the making of the contract, and the personal suffering may be that of the husband or wife or near relative of the contracting party, but that of a stranger or a master is not sufficient."
14. The above legal position regarding coercion has been held by various courts and
by this court in M/s. Democratic Builders Vs. Union of India reported in 1996 I AD
(Delhi) 1061. I consider that in view of the above legal position, the conclusion arrived
at by the learned Arbitrator that there was a coercion exercised on the claimant in writing
the letter to DDA is farfetched and a biased conclusion. It is not that the contractor has
filed this arbitration claim for the first time against DDA. This contractor being first class
contractor had filed numerous arbitration claims against DDA prior to that letter and after
that letter. Filing claim for damages is a routine matter for contractors. Almost in every
contract where even full and final payment is received, an arbitration claim is raised by
the contractors as a gamble and whatever they get through arbitration Award is
considered additional profit. Most of the time, the Arbitrators give Award closing their
eyes to the terms of the contract. They even do not tend to look into other details of the
contract and pass an Award merely on the basis of presumptions.
15. The learned Arbitrator in this case awarded a sum of Rs.2,75,685/- in respect of
the contract No.17/EE/HD-XXXV/85-86 which was superseded by the subsequent
contract and for which the contractor had given a specific undertaking that he will not
make any claim. Against the second part of the claim related to the contract for
construction of houses at Sai-Dul-Jaib, the Arbitrator had awarded a sum of Rs.3,16,000/-
In the entire Award for claims on infructuous expenditure, which is a term invented by
the contractors, the Arbitrator has comfortably become oblivious to the fact that DDA had
already paid an amount of Rs.8,46,412/- to the contractor under Clause 10CC which was
a specific clause under the contract to compensate a contractor for delay occurred in
execution of the work. The extension of time was granted by DDA without any levy of
compensation and that is the reason that DDA also paid additional amount to the
contractor under Clause 10CC. After payment of these additional amounts by the DDA
to the contractor under Clause 10CC, there could have been no justification for awarding
any further amount to the contractor in the name of infructuous expenditure as claimed.
The contract in its entirety takes care of the increase in prices during subsistence of the
contract or during extended period. It also takes care of the extra items and extra
expenditure to be incurred by the contractor.
16. Moreover, while considering any claim for loss or damages in respect of idle
labour or other expenditure, the Arbitrator is supposed to look into the evidence. The
contractor cannot be allowed to get himself enriched in the name of workmen to whom he
might not have paid even a single paisa. If any claim is made by a contractor regarding
idle labour, idle machinery or deployment of his engineers and supervisors during idle
period, he is supposed to prove the same by way of evidence as to how much work force
was employed by him during that period and he is also supposed to prove that he actually
paid salaries to that work force and the work force was on monthly salary and not on
daily payment basis. The contractor has to prove that he has been forwarding account of
work force employed from time to time to the DDA in accordance with the terms of the
agreement. In absence of compliance of the terms of agreement regarding maintenance of
labour attendance, forwarding this attendance to the DDA and in absence of any evidence
regarding loss suffered, no court or Arbitrator can grant any amount on account of
damages or losses suffered. The damages are required to be proved and not only asserted.
There is no formula provided under the agreement for calculation of damages neither
Arbitrator could have resorted to any formula for calculation of the damages. Since
damages were claimed by the petitioner on account of certain heads; payments made by
the contractor to the workmen, to the Engineer, Supervisor, their attendance and hire
charges if paid by the contractor were required to be proved.
17. The Arbitrator has granted these damages without evidence on the basis of
presumption. The claim No.19 allowed by the Arbitrator is not sustainable and is
contrary to the law. The Award passed by the Arbitrator is hereby set aside for the
reasons stated above.
18. The petition stands disposed of accordingly.
SHIV NARAYAN DHINGRA J.
DECEMBER 18, 2009 'AA'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!