Citation : 2009 Latest Caselaw 5250 Del
Judgement Date : 16 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) No.1168/1994
16th December, 2009
M/S BHARAT BUILDERS ...Petitioner
Through: Mr. Sandeep Sharma, Mr. Vikas
Sharma and Ms. Mugdha Pandey,
Advocates.
VERSUS
DELHI DEVELOPMENT AUTHORITY ....Respondent.
Through: Mr. Ajay Verma, Advocate
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL)
VALMIKI J. MEHTA, J.
I.A.No.2336/1995 in CS(OS) No.1168/1994
1. This application contains the objections on behalf of the
respondent/applicant/DDA under Sections 30 and 33 of the Arbitration Act, 1940
against the Award dated 9.5.1994 of the sole Arbitrator. The Award has been
CS(OS) No.1168/1994 Page 1 passed with respect to the disputes which arose between the parties under the
contract awarded to the petitioner by the objector for the construction of Local
Shopping Centre at Block-J, Vikas Puri, New Delhi.
2. The counsel for the objector has only pressed the findings on the preliminary
objections as recorded by the Award and sub-claims Nos. 4,15,17 of Claim No.1,
Claim Nos.6 and 9 with relation to interest and counter-claim No.7.
3. Though at the outset, the counsel for the objector also sought to press
objections with respect to certain other minor claims and which were indeed of
insignificant amounts of Rs.6869/-, Rs.3461/-, Rs.1050/- etc, however, since the
same could not be effectively argued in view of the findings contained in the
Award, the said objections were not pressed.
4. I would now take each objection as raised by the objector and deal with the
same.
5. The first objection which was pressed was that the Arbitrator has
misconducted himself and the proceedings by giving a finding on preliminary
objection No.1 that the claims made by the contractor are not barred by Clause 25 as
per which the claims have to be made within 90 days of receiving the intimation of
preparation of the Final Bill. The factual position is that the measurements were
recorded in February 1991 and thereafter final bill in this case was paid in October,
1992, the Arbitration was already invoked on 30th March, 1991, and the reference is
CS(OS) No.1168/1994 Page 2 dated 3rd May, 1991. Accordingly, there is no scope for the applicability of Clause
25 as admittedly, in this case, the disputes have been raised much before the period
specified under Clause 25 viz on 30.3.1991 i.e even before the final bill has been
prepared after March, 1992 after the measurements were taken in February, 1991.
Accordingly, there is no substance in this objection which is rejected.
6. The next objection which was with respect to preliminary objection No.2, in
which it is recorded that measurements have been accepted by the
contractor/petitioner, however, according to the counsel for the objector while
dealing with sub claim no.4 of claim No.1, the Arbitrator has taken the
measurements as not final. I would deal with this aspect when I deal with the
objections to the sub-claim No.4 of Claim No.1.
7. The final preliminary objection which was decided by the Arbitrator against
the objector, was with regard to the issue of rescission. What the counsel for the
objector has contended is that in view of the decision of the Supreme Court in the
case of Vishwanath Sood Vs. UOI 1989 (1) SCC 657 since, there is a levy of
penalty on the contractor and which decision of the Superintending Engineer is
final, therefore, it is not permissible for the Arbitrator to enter into this dispute with
regard to whether the contractor or the objector is guilty of delay for the same
period. This contention is not correct because as rightly argued by the counsel for
the non-objector that this contention of the counsel for the objector is negated by a
CS(OS) No.1168/1994 Page 3 Division Bench judgment of this court in the case reported as DDA Vs. Bhagat
Construction Co. Pvt. Ltd. 2004 (3) Arb. LR 548 and in para 13 of which judgment,
a Division Bench of this court has considered the judgment of Supreme Court in
Vishwanath Sood's case (supra) and has laid down that what is final is only the
levy of penalty and it is not that the Arbitrator is prevented from going into the
aspect of who is responsible for delay in performance of the contract and its
consequences. Accordingly, in view of the aforesaid Division Bench Judgment, in
the case of Bhagat Construction Company (supra), I reject the objection of the
objector. I may only add that if the contractor had gone to the Civil Court on this
aspect of wrong imposition of damages he was surely entitled to challenge the
imposition of liquidated damaged i.e. decision of the imposition of levy of
liquidated damages is not final and which challenge would include challenge before
the Civil Court of wrongly holding the contractor liable for delay on the basis of
which damages have been awarded. What I am stressing is that what is final is only
the levy of liquidated damages and that the issue of delay is not barred for decision
on the ground of res judicata or issue estoppel, even in arbitration proceedings.
8. Before I take up each claim and the arguments with respect thereto, I must
deal with one basic issue which permeates the findings of the Arbitrator and which
is that the objector has been held guilty of wrongly rescinding the contract.
The detailed discussion on this aspect is found in as many as nine pages i.e
CS(OS) No.1168/1994 Page 4 from internal page 4 to 13 of the Award, and in these pages the Arbitrator after
discussing the various contentions and the issues has come to a finding that both the
objector and the present petitioner were guilty of breaches by delaying the
performance of the contract. On the one hand, the objector has been held guilty of
delay in supplying of the drawings, delay in issue of the cement, delay in making
the payments and so on, the petitioner has also been held responsible for certain
delays in performance of the contract. The Arbitrator has held that both the parties
are responsible for delay in the performance of the contract, though it is also clear
that major defaults were attributable to the objector. After giving such a finding the
Arbitrator then has held that time of performance was not the essence of the contract
and was in fact repeatedly extended. In view of the aforesaid findings that the time
of performance was not the essence of the contract, a final conclusion is given by
the Arbitrator at internal pages 12 and 13 of the Award and which runs as under:-
"Thirdly time for performance if not of essence or no longer of the essence because of election, rescission is only permitted after giving a notice requiring performance of the notice. In this case vide C-115 respondent asked claimants to complete work by 15/12/90 by a notice dated 28/11/90. Whereas as per press notice No.17 PWD6 No.22/92-93 for Rs. 68436/- work recoverable from M/s Bharat Builders 5 months is time allowed. This means time of 17 days allowed to claimant was totally unreasonable."
The aforesaid findings cannot be faulted with because this finding is based on
the judgment of the Supreme Court reported as Hind Construction Contractors Vs.
State of Maharashtra, AIR 1979 SC 720 and in which judgment the Supreme Court
CS(OS) No.1168/1994 Page 5 has laid down that where time of performance is not the essence of the contract, it is
necessary that before the same is made of the essence, a party must give a notice of
a reasonable time so as to make the time essence of the contract. In the present
case, time of performance was from the inception not of the essence of contract
because there was a clause of liquidated damages and which as per the judgment in
Hind Construction Contractors case (supra) makes time of performance not to be
of the essence even though it is specified to be of the essence of contract. There is a
finding of fact that no reasonable notice has been given for making time the essence
of the contract, and which is required in terms of the aforesaid judgment in Hind
Construction's case. This being a finding of fact, and not shown to me to be
perverse in any manner, as Arbitrator has held that notice though given was in fact
not a notice of a reasonable period and hence amounts to not giving the legally
required notice. For arriving at the conclusion of unreasonable period of the notice,
the Arbitrator notes that the date of the notice is 28.11.1990 and by which the work
was directed to be completed by 15.12.1990 i.e within a period of 17 days. This
period of 17 days, the Arbitrator has then compared with the time which was given
to the substitute contractor for completing the balance work in as many as 5 months.
In fact, this work of five months was also completed in 7 months by the substitute
contractor. Thus, the finding of the Arbitrator is wholly justified because once there
is a notice which requires fixing of the time as the essence of the contract such
CS(OS) No.1168/1994 Page 6 notice must necessarily fix a reasonable period of time. This is also in terms of
Section 46 of the Contract Act, 1872 which specifies that where no time is fixed for
performance, then performance must be within a reasonable period of time.
Therefore, in view of the above factual and legal position, I do not find any fault
whatsoever in this finding of the Arbitrator that the period fixed is not a reasonable
period. Even if, two views were possible from this situation, I do not think that the
view adopted by the Arbitrator can be said to be the view of an unreasonable man
which no person could have arrived at. Therefore, while hearing objections under
Sections 30 and 33, I would not venture to set aside the findings and the conclusions
of the Arbitrator merely because there is another possible view. In any case, I have
already held that the Arbitrator is justified in holding that the period fixed making
time the essence of the contract, was not a reasonable period. In view of the above,
there is no merit in the objection that the Arbitrator has wrongly held that the
contract was not properly rescinded by the objector.
9. Sub Claim No.4 of Claim No.1 pertains to the claim of the contractor for
short payment. The Arbitrator has awarded a total of Rs.27,641/- for the short
payment under this head. There were three sub heads of this claim, two of which
pertain to RCC work in the foundation. Mr. Verma contends that once the
Arbitrator has held at internal page 4 of the Award that the final measurements were
accepted by the claimant without any protest on 8.2.1992, then there cannot be a
CS(OS) No.1168/1994 Page 7 different conclusion adopted by the Arbitrator that fresh measurements can be
adverted to by the claimant for making claims for short payment due to incorrect
measurements. Mr. Verma is both right and wrong. He is right that measurements
were taken as final and he is wrong because the Arbitrator records that the
respondent/objector itself has made fresh measurements for the RCC work after the
final measurements were accepted. If, therefore a fresh measurement is made after
preparation of the final bill, then, surely there can come into effect additional
measurements for seeking payments on such basis. Once again, I feel that, even if
two views are possible, it cannot be said that the decision of the arbitrator is so
perverse that it can be held that he has misconducted himself or the proceedings.
These additional measurements were with respect to RCC work and therefore so far
as the two sub heads under this subject claim no. 4 is concerned, namely serial no.1
and 2 for RCC works are justified. However, so far as the brick work foundation is
concerned, there cannot be retraction with respect to the measurements already
recorded in the measurement books which have become final. Accordingly,
awarding of this claim is partially modified in that out of the amount of Rs.27,641/-
and amount of Rs.14,992.28 shall stand reduced.
10. The next dispute pertains to sub claim No.15 of Claim no.1. This claim
pertains to the cost of work done. The respondent admits that the amounts due for
the balance work is of Rs.1,54,528/-, however, what has been argued by Mr. Verma
CS(OS) No.1168/1994 Page 8 is that this amount in fact has been paid in the final bill and therefore there is no
question of the Arbitrator awarding this claim again which will amount to double
payment. Mr. Sharma on the other hand refutes this contention and states that this
amount has not been paid in the final bill. I therefore, need not to say anything
except the fact that since this amount of Rs.1,54,528/- is payable to the petitioner,
if the same has been paid under the final bill, the same shall stand deleted from the
awarded amount but if not paid shall be liable to be paid.
11. Sub claim no.16 pertains to the refund of the security deposit. I have already
held that the rescission of contract by the objector was not justified and the
Arbitrator is correct in holding that the rescission was illegal. The challenge to this
sub-claim therefore automatically falls because once the rescission is not justified,
the petitioner was entitled to refund of the security deposit.
12. The next claim in dispute is sub claim no.17 whereby the Arbitrator has
awarded escalation under Clause 10CC for the extended period of the contract. I
may note that the claim which was made by the petitioner was for a sum of Rs.8
lacs and this was thereafter reduced to Rs.6,42,466/-. In view of my finding with
respect to preliminary objection no.2 on the aspect of non applicability of the
judgment of the Supreme Court in Vishwanath Sood case (supra), while deciding
this sub-claim-17 it was open to the Arbitrator to proceed on the basis of the
findings of breaches of the objector due to delays so that escalation can be granted
CS(OS) No.1168/1994 Page 9 for delayed period. The escalation in this case is claimed after 1.10.1988. The
contractor has already got escalation for the period before May, 1987. In terms of
judgment of the Division Bench of this Court in Bhagat Construction Co.(supra),
the Arbitrator was well justified in arriving at a finding and which he has done by
holding that the objector was guilty of delay on account of various aspects such as
delay in issuance drawings, delay in issuance of cement or delay in making the
payments and so on. Mr. Verma has sought to contend that once it is held that both
the parties are responsible for delay, then, such a claim could not have been
awarded under Clause 10CC. I am afraid I cannot agree because under Clause
10CC once it is held that the respondent is liable to compensate for the increase in
prices towards material and labour in the extended period when there is a default or
delay in performance by the objector, I do not think that the Arbitrator is wholly
unjustified in awarding this claim. Of course, there is an issue of calculation when
both the parties are responsible for delay as to what should be the amount which the
Arbitrator could have awarded. The arbitrator in this case is a technical person
namely Sh. A.C Panchdhari who is a retired Director General (Works) of CPWD
and he is therefore possessed of necessary knowledge to arrive at a finding. It has
been repeatedly held by this court that some leeway is permissible when the
Arbitrator is a technical man who is well versed in knowledge of execution of the
construction works. I cannot probe into the mental process of the Arbitrator as to
CS(OS) No.1168/1994 Page 10 how this figure has been arrived at. It is settled law that once there are certain
materials available before the Arbitrator, the Arbitrator is competent to make an
honest guess work on the basis of such material available before him. This is so
held by the Supreme Court in the Case of Mohd. Salamatullah vs. State of A.P.,
AIR 1977 SC 1481 and M/s A.T Brij Paul Singh Vs. State of Gujrat, AIR1984 SC
1703.Therefore, even if on the first blush, the argument of Mr. Verma may appear
to be attractive however, while hearing objections to the Award, I do not find such
gross perversity for this court to hold that the Arbitrator has misconducted himself
and the proceedings. Objections to this claim are therefore not sustainable and
hence dismissed.
13. The next claim which was argued was Counter-claim no.7 whereby the
Arbitrator has dismissed the Counterclaim of the Objector on account certain
deficiency in the work of the contractor. The Arbitrator has in arriving at the
conclusion of dismissal of the Counterclaim by specifically referring to Contractual
Clause 14 which requires that notice has to be issued to the contractor giving the
details of various defects in the work and only thereafter can the objector make
deduction/claim for any defects in the work. The Arbitrator has arrived at a finding
of fact that no notice for deficiency/defective work was ever issued to the
petitioner/contractor. Mr. Verma has also not shown to me any notice which has
been issued specifically pointing out any specific deficiency in the work which is
CS(OS) No.1168/1994 Page 11 done by the contractor. Accordingly, this finding of fact is not in any manner
perverse for this court to hold that the Arbitrator has misconducted himself or the
proceedings. Objection to this claim is therefore is rejected.
14. The counter claim No.9 was on account of the claim of the objector because it
had to complete the work allegedly at the risk and cost of the contractor. This claim
for Rs.7,01,191/- has been rejected by the Arbitrator because he has held that the
rescission of contract was not justified. I have already dilated on this aspect while
considering the preliminary objection no.3 and the issue of rescission with respect
to other claims. No fault can therefore be raised against dismissal of this Counter
claim no.9.
15. The last issue which therefore remains is the rate of interest which ought to
be awarded and the rate of interest which the Arbitrator has awarded @ 12% . The
Supreme Court in the recent catena of judgments reported as Rajendra
Construction Co. Vs. Maharashtra Housing & Area Development Authority &
ors.2005 (6) 678, McDermott International Inc. Vs. Burn Standard Co. Ltd.& ors
2006 (11) SCC 181, Rajasthan State Road Transport Corpn. Vs. Indag Rubber
Ltd. (2006) 7 SCC 700 and Krishna Bhagya Jala Nigam Ltd. Vs. G.Harischandra,
2007 (2) SCC 720, has held that the courts should in view of the consistent fall in
the rates of interest take into account the changed ground realities and reduce the
higher rates of interest granted under the Award. The Supreme Court has further
CS(OS) No.1168/1994 Page 12 mandated that this becomes all the more necessary when a considerable period of
time elapses from the date of the Award till the disposal of the objections by the
court. I may note that the Award in this case is of the year 1994 and in which year
the objections were also filed. Today were are at the end of 2009. The Supreme
Court, in fact, in the case of State of Rajasthan Vs. Ferro Concrete Construction
Pvt. Ltd (2009) 3 Arb. LR 140 (SC) has also reduced the rate of interest for the pre-
reference period. Accordingly, wherever the Award has granted interest @ 12 %
per annum for pre-reference period or pendente lite period or thereafter till making
of the Award rule of the court, I reduce the rates of interest uniformally to 9% per
annum simple. In case, the payment is made under the present judgment within a
period of 90 days from today then rate of interest shall be continue to remain 9%
simple from the date of this judgment, however, in case the payment is not made
within the aforesaid period of 90 days, then interest from the date of this judgment
shall run at 11% per annum. I may lastly clarify that in case the payment of
Rs.1,54,528/- under sub claim no.15 of claim no.1 is, already received by the
petitioner, the petitioner will not be entitled to the same again in terms of the present
judgment, but, in case, however, this amount is not received by the petitioner in the
final bill, the petitioner will be entitled to such amount.
16. With the aforesaid observations, the Award dated 9.5.1994 is made a rule of
the court except with regard to the variation of the limited extent of sub head (4) of
CS(OS) No.1168/1994 Page 13 claim no.1 and the reduced rate of interest. Parties are left to bear their own costs.
December 16, 2009 VALMIKI J.MEHTA, J Ne/ib CS(OS) No.1168/1994 Page 14
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!