Citation : 2009 Latest Caselaw 5244 Del
Judgement Date : 16 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. No.517A/2000 and 638A/2000
December 16, 2009
1.O.M.P. No. 517A/2000
PARDES DEHYDRATION CO. ...Petitioner
Through: Mr. Shiv Khorana, Advocate.
VERSUS
UNION OF INDIA ....Respondent
Through: Ms. Geeta Sharma, Advocate.
2.O.M.P. No.638A/2000
UNION OF INDIA ....Petitioner
Through: Ms. Geeta Sharma, Advocate.
VERSUS
PARDES DEHYDRATION CO. ...Respondent
Through: Mr. Shiv Khorana, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
OMP No.517A/2000 & 638A/2000 Page 1
% JUDGMENT(ORAL)
VALMIKI J. MEHTA, J.
1. Suit No. 638A/2000 was filed for summoning of the Award. The
Award has been requisitioned from the Arbitrator. No objections were filed in
this Suit No.638A/2000 and objections were in fact filed by the
respondent/Union of India against the Award dated 11.2.2000 in Suit
No.517A/2000 which was a petition filed by the contractor under Sections 14
and 17 of the Arbitration Act, 1940. I note that these objections ought to have
been numbered as an I.A. but the same have not been numbered. Accordingly,
let the Registry give a number to these objections filed by the Union of India
under Sections 30 and 33 of the Arbitration Act, 1940.
2. The facts of the case are that the contract was awarded by the
objector/Union of India to the contractor/Pardes Dehydration Company
whereby the latter was to supply dehydrated potatoes. The contract in question
is dated 23.3.1990 (date of letter of acceptance) and under which a total of 43
metric tonnes(MT) of potatoes were to be supplied in four months viz 10 MT up
to 30.4.1990, 10 MT up to 31.5.1990, 13 MT up to 30.6.1990 and the balance
10 MT up to 31.7.1990.
OMP No.517A/2000 & 638A/2000 Page 2
3. It is an undisputed fact that the contractor could not supply the
goods in question. The contractor asked for and got three extensions, the last of
which is dated 31.1.1991 for supply up to 28.2.1991. Even up to 28.2.1991 the
contractor failed to supply the dehydrated potatoes.
4. The objector, therefore, filed its claim before the Arbitrator on
account of having procured the dehydrated potatoes at the risk and cost of the
contractor. Before I advert to the merits of the case and the Award I do find it
surprising that in a case where the contract in question in fact provides for
liquidated damages, the Union of India did not seek liquidated damages but in
fact asked for general damages on the basis of a risk purchase tender. Not only
this, the Union of India which could have asked for liquidated damages as an
alternative relief to the relief of general damages yet it did not pray for this
alternative relief of liquidated damages. By the Award, the Arbitrator has
dismissed the claim of Union of India on two main grounds that firstly the time
of performance was not the essence of the contract and secondly that the Union
of India has failed to prove the rates of dehydrated potatoes in and around the
date of breach.
5. A reading of the Award and the facts of the case show that under
the contract, there was a clause for liquidated damages. This clause of
liquidated damages is provided under clause 14(7)(i) of the General Conditions
OMP No.517A/2000 & 638A/2000 Page 3 of Contract (Form DGS &D-68-Revised). Once there is a clause for entitlement
of liquidated damages, then in view of the judgment of Supreme Court reported
as Hind Construction Contractors Vs. State of Maharashtra AIR 1979SC
720, time of performance is not the essence of the contract and so accordingly
held by the Arbitrator. The judgment in Hind Construction Contractors
(supra) case has been followed by a Learned Single Judge of this Court in the
case reported as Union of India Vs. Panipat Foods Ltd. 60(1995)DLT 258 and
which has been relied upon by the Arbitrator . Once time of performance is not
the essence of the contract, it was incumbent upon the Union of India to issue a
notice making time of performance the essence of the contract and which
admittedly was not done. In view of the aforesaid facts, the Arbitrator has
given, inter alia, two findings as under:
" v) The respondent had sought extension on 28.2.91 that they have commenced the production and placed order for procurement of ISI confirming tins, therefore, delivery be given upto 30.4.91 but the claimant had cancelled the same as late as on 30.5.91 instead of granting the period and placed the order of R/P on 19.9.91. In "UOI Vs. Panipat Foods Ltd. and others", it is held that the time in this type of contract is not essence of the contract and the claimant should have given the opportunity to the respondent by granting the period as was requested for and making the time essence of the contract upto 30.4.91.
vi) In respect of claim of general damages, the claimant has failed to file any document which establishes the market rate on date of breach as per the Judgment of Supreme Court in AIR-1962, SC-366 and followed by High Court of Delhi, Universal Woollen Mills Vs. UOI, reported in 1995(1) Arbitration Law Reporter 59, the date and place of the breach or near about has to be produced but the same has not been established by UOI."
OMP No.517A/2000 & 638A/2000 Page 4 The aforesaid finding of the Arbitrator is justified and I do not find that
the same can in any manner be faulted with. Even if two views are possible,
this Court will not interfere merely because another view is possible than the
view as taken by the Arbitrator. The Arbitrator, therefore, has rightly rejected
the claim of the Union of India for general damages.
6. Before parting with the case, I must express my anguish that in a
case of this nature where ex-facie the contractor is at fault and has committed
default in performance of his obligations yet he is being allowed to go scott free
because the Union of India did not take the correct remedy of seeking liquidated
damages in alternative to general damages. If I was sitting as a Civil Court
hearing first appeal under Order 41 of Civil Procedure Code, 1908, it could
have been possible for me to have taken a different view because under the
various provisions of Order 41, including Order 41 Rule 33, of Civil Procedure
Code, I could have in fact made any such orders in the interest of justice as
found just an appropriate in the facts and circumstances of the case, however, I
am handicapped because I am hearing objections to an Award under Section 34
and my jurisdiction as such is indeed limited. I can only hope that the Union of
India would be well advised in future for at least filing proper claim petitions so
that when huge losses are caused to it, it can recover the same and not be
frustrated as per the situation which has been emerged in the present case.
OMP No.517A/2000 & 638A/2000 Page 5
7. In view of the above, the objection petition is dismissed leaving the
parties to bear their own costs. The Award is made a rule of the Court. This
order shall dispose of Suit No. 517A/2000 and the unnumbered I.A. under
Sections 30 and 33 of the Arbitration Act, 1940 and the Suit No.638A/2000.
VALMIKI J.MEHTA, J
December 16, 2009
Ne
OMP No.517A/2000 & 638A/2000 Page 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!