Citation : 2009 Latest Caselaw 5083 Del
Judgement Date : 8 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELH
+ A.A. No.424/2008
8th December, 2009
Engineering Development Corporation ...Petitioner
Through: Ms. Anusuya Salwan, Advocate
VERSUS
Municipal Corporation of Delhi & Anr.
....Respondents
Through: Mr. Nalin Tripathi, Additional
Standing Counsel for the MCD.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL)
VALMIKI J. MEHTA, J.
*
1. This is a petition under Section 11 of the Arbitration and
Conciliation Act, 1996 for the appointment of an Arbitrator.
2. A contract was entered into between the parties vide Work Order
No.EE (Pr) SZ/2002-2003/63 dated 1.10.2002. The contract was for
construction of 12 class rooms and two toilets blocks. The petitioner A.A.424/2008 Page 1 claims that time was extended provisionally up to 31.7.2004 and
thereafter the work was completed to the entire satisfaction of the
respondent on 11.9.2005. On 28.2.2005 the respondent prepared their
5th R.A bill. This R.A. bill shows that the date of completion is shown as
'work in progress'.
3. In a petition under Section 11, the court has to basically see four
aspects. The first is whether there is an arbitration agreement
between the parties. The second is whether the disputes fall within the
scope of the agreement. The third aspect to be seen is whether the
petition has been filed within the limitation period and finally whether
the claims are live claims.
4. In the present case the first two of the above stated aspects are
not in dispute. What has been canvassed by the counsel for the
respondent is that the petition is barred by time and that the claims
are not live claims.
5. As regards the limitation issue, the right to file a petition for the
appointment of an Arbitrator arises when a claim which is raised by
one party is opposed and denied by the other party, I put a specific
query to the counsel for the respondent as to when the claim of the
petitioner for the work done was denied by the respondent, however,
the respondent failed to point out any letter by which the claim of the
A.A.424/2008 Page 2 petitioner for work done under the subject contract was denied. If that
be so, I fail to understand how the petition is barred by time. It has
been held by the Supreme Court in the judgment reported as Union of
India Vs. L.K.Ahuja 1988(1) Arb.LR 375 (SC) that unless and until
disputes arise, limitation cannot be said to begin for the purposes of
Article 137 of the Limitation Act. The counsel for the petitioner has
rightly relied upon two judgments of this court reported as Pandit
Munshi Ram Associates Pvt. Ltd. Vs. DDA 2002 (Suppl.) Arb. LR
659 (DB) and also an unreported decision dated 20.9.2007 titled
D.Pal Company Vs. MCD (DB). Both these judgments are relied
upon for the proposition that unless and until disputes arise, the
limitation does not commence for filing of a petition for the
appointment of an Arbitrator. The counsel for the petitioner has
further relied upon the judgment of the Supreme Court in the case of
Utkal Commercial Corporation Vs. Central Coal Fields Ltd.
(1999) 2 SCC 571 for the same proposition and has drawn my
attention to para 10 wherein the Supreme Court has referred to its
earlier judgment in the case of Major (Retd.) Inder Singh Rekhi vs.
DDA 1 (1988) 2 SCC 338 to hold that a dispute arises only where
there is a claim by one party denial/repudiation of such a claim by the
other party.
A.A.424/2008 Page 3 In view of the aforesaid judgments and the fact that in the
present case, the counsel for the respondent has failed to show me
any letter whereby the respondent has disputed and denied the claim
of the petitioner for the work done under the contract and I do not find
that the petition is barred by limitation.
6. The second issue which has been urged by the counsel for the
respondent is that by virtue of clause 9 of the contract, the claims are
no longer live claims. As per clause 9, no further claim shall be made
by the contractor after submission of the final bill and such claims as
not stated in the final bill shall be deemed to have been waived and
extinguished.
In the present case, I have not seen any final bill which has been
annexed by the respondent. The only bill which is the last bill prepared
is 5th running bill which in fact states that the work is in progress. The
bill itself factually does not state that it is a final bill. Therefore, there
is no question of application of clause 9. In any case, I am of the view
that any clause in the contract which artificially curtails the period of
limitation is of no effect by virtue of Section 28 of the Contract Act,
1872. This has been so held in two recent judgments of this court
reported as Biba Sethi and Nitin Sethi Vs. Dyna Securities
Limited MANU/DE/1325/2009 and Pandit Construction Co. Vs.
A.A.424/2008 Page 4 DDA 2007(143)DLT270. Accordingly, I do not agree that the claims
are not live claims.
7. So far as the present contract is concerned clause 25 requires
appointment of the Arbitrator by the Commissioner, MCD. The
Supreme Court in its recent judgment reported as Indian Oil
Corporation Vs. Raja Transport 2009 (8) SCC 520 has held that
even if the respondent fails to appoint an Arbitrator after service of the
notice and the petition under Section 11 is filed in the court, the court
would only direct that the Arbitrator be appointed in terms of the
agreed clause between the parties. In accordance with the aforesaid
judgment it is the Commissioner MCD who is to appoint the Arbitrator.
8. Accordingly, this petition is allowed with costs of Rs. 25,000/-
and in terms of clause 25, the Commissioner MCD is directed to
appoint an Arbitrator to decide all the
disputes/differences/claims/counterclaims/issues as arriving between
the parties under the subject work order within a period of four weeks
from today.
DECEMBER 08, 2009 VALMIKI J. MEHTA, J. ib A.A.424/2008 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!