Citation : 2009 Latest Caselaw 5076 Del
Judgement Date : 8 December, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARBITRATION PETITION NO.173/2008
PUNJ LLOYD LTD. AND ANOTHER .. APPLICANTS
Through: Mr.Dhirendra Negi, Advocate
VERSUS
NATIONAL HIGHWAY AUTHORITY
OF INDIA .. RESPONDENT
Through: Mr.Sumit Gahlawat, Advocate
CORAM
HON'BLE THE CHIEF JUSTICE
ORDER
% 8.12.2009
1. This is an application under Section 11 of the Arbitration
and Conciliation Act, 1996 to appoint an independent person as
presiding arbitrator and thereby constitute an arbitral tribunal.
2. The facts giving rise to this petition are as follows:
The joint venture formed by applicants in the name of "Punj
Lloyd Ltd. - Progressive Constructions Ltd. JV" had entered into a
contract dated 8th October, 2001 for construction of an access
controlled four lane divided carriageway with six lane structures
of Jaipur Bypass, Phase II, Zone D, 34.7 KM long, KM 220 of NH-8
(Delhi-Jaipur road) at Chandwaji and KM 246 of NH-11 (Jaipur-
Sikar Road) at Harmara.
3. Certain disputes arose in the course of the execution of the
contract and the applicants took recourse to provisions of the Arbitration Petition No.173/2008 page No.1 of 4. arbitration agreement contained in clause 67.3 of the contract.
The relevant portion of clause 67.3 is reproduced below:
"Sub-Clause 67.3: Arbitration This Sub-Clause shall read as below: Any dispute in respect of which the decision, if any, of the Engineer has not become final and binding pursuant to Sub-Clause 67.1, shall be finally settled as set forth below:
i) the dispute with the Contractor, whether Indian or foreigner, shall be finally settled by arbitration in accordance with the Indian Arbitration and Conciliation Act, 1996, or any statutory amendment thereof. The arbitration tribunal shall consist of three arbitrators, one each to be appointed by the Employer and the Contractor; the third arbitrator shall be chosen by the two Arbitrator so appointed by the parties and shall act a presiding Arbitrator. In case of failure of the two Arbitrator, appointed by the parties, to reach upon a consensus within a period of 28 days from the appointment of the Arbitrator appointed subsequently, the Presiding Arbitrator shall be appointed by the President, Indian Road Congress. For the purposes of this Sub-Clause, the term "Indian Contractor" means a Contractor who is registered in Indian and is a juidic person created under Indian Law as well as a joint venture between such a Contractor and a foreign Contractor."
4. On October 16, 2007, the applicants, in accordance with the
above clause, gave notice of commencement of arbitration and
appointed Mr.V.K. Shrotriya as their nominee arbitrator. On
November 13, 2007, the respondent appointed Mr.K.K. Verma as
its nominee arbitrator. As per the agreement, the third arbitrator
was to be chosen by the two arbitrators appointed by the parties
and in case of failure of the two arbitrators appointed by the
Arbitration Petition No.173/2008 page No.2 of 4. parties to reach upon a consensus within 28 days from the
appointment of the arbitrator appointed subsequently, the
presiding arbitrator was to be appointed by the President, Indian
Roads Congress. It is seen from the records that the second
arbitrator Mr.K.K. Verma claimed that one Mr.G.S. Tawarmalani
has been appointed as presiding arbitrator with the consent of
the first arbitrator. The first arbitrator, however, has taken a
consistent stand that he had not given his consent for
appointment of Mr.Tawarmalani as the presiding arbitrator. On
the other hand, according to him during the discussions between
the two nominee arbitrators, he had suggested three other
names to the second arbitrator for appointment of the presiding
arbitrator. It is seen that thereafter a considerable
correspondence was exchanged between the parties. The
applicants had also approached the President, Indian Roads
Congress for appointment of the presiding arbitrator but due to
the objection raised by the respondent - NHAI, the Indian Roads
Congress returned the request for appointment of the presiding
arbitrator.
5. I have heard the counsel appearing for both the parties. A
preliminary objection is raised by the counsel for the respondent
about the maintainability of the petition on the ground that this
Court has no territorial jurisdiction to entertain the petition as the
subject matter of the dispute is situated at Jaipur, Rajasthan and
Arbitration Petition No.173/2008 page No.3 of 4. payments were also made at Rajasthan. This objection is without
any merit inasmuch as the tender for work in question was
floated in Delhi, the pre-bid meeting for the works was held at
Delhi, the letter accepting the bid was also issued from Delhi and
the agreement between the parties was also signed at Delhi.
Thus substantial part of the cause of action has taken place in
Delhi.
6. After hearing the counsel appearing for the parties I am
satisfied that this is a fit case to direct the President, Indian
Roads Congress to appoint the presiding arbitrator in accordance
with the provisions of clause 67.3 of the contract. The President,
Indian Roads Congress, Kama Koti Marg, Sector 6, R.K. Puram,
New Delhi is hereby directed to consider the request of the
applicants for appointment of the presiding arbitrator afresh and
make the appointment of presiding arbitrator within a period of
four weeks from the date of communication of this order.
7. The Registry is directed to forward a copy of this order to
the President, Indian Roads Congress.
8. The petition stands disposed of in terms of the aforesaid
order.
Chief Justice 8th December, 2009 "nm"
Arbitration Petition No.173/2008 page No.4 of 4.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!