Citation : 2009 Latest Caselaw 3275 Del
Judgement Date : 20 August, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: August 11, 2009
Date of Order: August 20, 2009
+ CS(OS) 789/1991
% 20.08.2009
M/s Assam Import Agency ...Plaintiff
Through: Mr. J.N. Aggarwal, Advocate
Versus
Cement Corp. of India Ltd. ...Defendant
Through: Mr. Ajay Verma, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this order, I shall dispose of the objections filed by the
plaintiff/petitioner under Section 30, 34 of the Arbitration Act, 1940 against an
award dated 31st December 1991 whereby the claim of plaintiff was rejected
and a NIL award was passed.
2. Brief facts relevant for the purpose of deciding this suit are that the
plaintiff entered into a contract with defendant for handling of the cement.
The relevant clauses of contract are as under:
"Clause (i). That you are awarded the work of handling cement at Jogighopa Dump at Rs.17 PMT as per terms and conditions of our Tender as further modified and agreed to during discussions on 07.10.1983.
Clause (iv). In case the cement is supplied to the Consignee
CS(OS) 789.91 M/s Assam Import Agency v. Cement Corp. of India Ltd. Page 1 Of 4 directly from the wagons you will be paid the rate of Rs.8/50 PMT.
Clause (v). The loading charges from the railway wagons or from your godowns to the Consignee/lorry will be reinstated at the rate per MT approved by the State/ Central Govt.
authorities."
3. In the contract, the quantity stipulated was 47,000 MT, however, this
quantity was variable. The contract was granted for one year. The contention
of plaintiff is that the actual quantity forwarded by defendant and handled by
plaintiff was much less. The plaintiff had made arrangement for stipulated
quantity and incurred expenditure for handling large quantity of 47,000 MT
whereas the quantity forwarded was 16650/- MT. The plaintiff raised a bill of
Rs.2,99,004/- on the basis of expenditure incurred by it for the contracted
quantity. The defendant took a stand that this bill was not payable as the
plaintiff had been paid handling charges in accordance with the contract.
Ultimately, the dispute was referred, at the instance of the plaintiff, to the
arbitrator. Before the arbitrator, the plaintiff raised a claim of Rs.8,12,715/-
towards loss because of expenditure incurred by plaintiff on godown etc and
raised a claim of Rs.3,18,692/- on the ground that he was not paid full amount
for the quantity of cement handled. The petitioner/plaintiff also claimed a sum
of Rs.8,50,000/- under clause 4 on the ground that the plaintiff was also
entitled to payment @ Rs.8.50 PMT for quantity supplied directly by
defendant /respondent to the consignees by wagons. The plaintiff also
claimed interest over this amount. The learned arbitrator found the claim
made by the plaintiff as untenable. It is also observed by learned arbitrator
that during continuation of arbitral proceedings parties had settled their
accounts in respect of other things and in view of settlement arrived at, he
was only to give an award in respect of unresolved disputes regarding
CS(OS) 789.91 M/s Assam Import Agency v. Cement Corp. of India Ltd. Page 2 Of 4 applicability of clause iv.
4. The plaintiff had argued before the arbitrator that it was entitled to
claim handling charges even for that cement which directly went to the
consignee without having been handled by the plaintiff @ Rs.8.50 PMT. The
learned arbitrator after considering clauses (i), (iv) and (v) came to conclusion
that there was two kinds of handling to be done by plaintiff; one where the
cement was to arrive at the railway station and was to be taken by the
plaintiff to his godwon and then supplied to the consignees. In such a case,
the plaintiff was entitled for handling charges @ Rs.17 PMT and the second
type of handling was one where the cement arrived at the railway station
from wagons and it was not to be taken to the godown but from wagon itself
it was loaded to the trucks of the consignees directly. For such a handling, the
plaintiff was entitled for Rs.8.50 PMT. The learned arbitrator turned down the
plea of petitioner that the petitioner was also entitled to handling charges in
respect of those consignments which were not handled by the petitioner in
anyone of the above two manners and the consignment went directly to the
consignee through wagons itself.
5. I consider that the contract between petitioner and respondent could
not have been interpreted in any other manner. The petitioner was given
contract of handling the cement and if cement was not to be handled by the
petitioner in any manner, the petitioner was not entitled for any handling
charges.
6. The learned counsel for petitioner argued that no amount was paid in
respect of the settlement and the arbitrator should have mentioned the
CS(OS) 789.91 M/s Assam Import Agency v. Cement Corp. of India Ltd. Page 3 Of 4 amount to be paid to petitioner under the settlement. Counsel for respondent
submitted that the amount as agreed during settlement was paid to the
petitioner after the settlement was arrived at and the learned arbitrator was
only to give an award in respect of unresolved dispute regarding applicability
of clause iv on consignment of cement which directly went to the consignee
and no handling was done by the petitioner.
7. I have perused the record and the reply filed by respondent. The
respondent had given details of the handling charges payment made by
respondent to the petitioner under the contract. Thus, the plea of plaintiff that
it was not paid the amount on account of handling charges is baseless. I also
find that the award passed by learned arbitrator suffers from no infirmity and
the learned arbitrator did not misconduct himself nor the award suffers from
an error on the face of it. The allegations made by the plaintiff against the
arbitrator that the award was ante-dated is also baseless . I find no force in
the petition. The petition is hereby dismissed. No orders as to costs.
August 20, 2009 SHIV NARAYAN DHINGRA J. rd
CS(OS) 789.91 M/s Assam Import Agency v. Cement Corp. of India Ltd. Page 4 Of 4
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!