Citation : 2009 Latest Caselaw 3208 Del
Judgement Date : 18 August, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Ex.P. 102/2006
% Date of decision: 18th August, 2009
UZI JUSTMAN ....Decree Holder
Through: Mr. Rajiv Tyagi and Ms Chanchal
Biswal, Advocates
Versus
M/S TELEPHONE CABLES LTD & ANR ... Judgment Debtors
Through: None.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. Execution is sought of an arbitral award having the force of a
decree under the provisions of the Arbitration Act, 1996. The
arbitral award is for payment of US $1,80,000/- by the judgment
debtor to the decree holder. The execution petition was originally
filed in the court of the District Judge, Chandigarh in or about the
year 2000. The judgment debtor filed objections to the execution.
The decree holder applied to the Supreme Court for transfer of the
execution petition outside Chandigarh and vide order dated 9th
December, 2002 the said transfer petition was allowed and the
execution proceedings transferred to the District Court, Delhi. While
the execution proceedings were pending before the Additional
District Judge, on 16th August, 2000 issues were framed as to
whether the award is liable to be set aside. Some witnesses were
also examined before the learned Additional District Judge.
2. The judgment debtor on or about 3rd July, 2003 filed an
application under Section 22 of the Sick Industrial Companies
(Special Provisions) Act, 1985 stating, inter alia, that the reference
of the judgment debtor dated 21st October, 2002 before the BIFR had
been registered as case No.712/2002 and praying for suspension /
stay of the proceedings in the execution. However, subsequently
realizing that the decree sought to be executed was for an amount
beyond the pecuniary jurisdiction of the Additional District Judge,
the Execution proceedings were in or about the year 2006
transferred to this court and are pending since then.
3. The counsel for the decree holder, on 9th April, 2009 informed
this court that the BIFR had granted permission to the decree holder
to execute this decree against the judgment debtor but the said
order of the BIFR had been stayed by the AAIFR. He, however,
contended that the bar of Section 22(1) will not come in the way of
the present execution. Thereafter also the proceedings were
adjourned on 6th July, 2009 on the ground that the decree holder has
moved an application before the AAIFR for vacation of the order of
stay of the permission granted by the BIFR to pursue the present
proceedings.
4. Today also the counsel for the decree holder has, at the outset,
requested that the proceedings be adjourned. He has contended
that the arguments before the AAIFR have been concluded and the
order is awaited. However, since it was his contention on 9 th April,
2009 (supra) that the provisions of Section 22(1) of the Act do not
come in the way of this execution, rather than adjourning the matter,
arguments have been heard inasmuch as proceedings cannot be kept
indefinitely before the court; if the counsel for the decree holder is
able to satisfy that the provisions of Section 22(1) do not come in the
way of the execution, the execution will proceed irrespective of the
proceedings aforesaid before the BIFR and AAIFR, else this
execution is barred by Section 22(1) of the Act.
5. The counsel for the decree holder has contended that the
decree holder, a foreign national was an employee of and worked
with the judgment debtor company; However, since difficulties were
being faced in payment of remuneration to the decree holder owing
to his foreign citizenship, and to enable requisite permissions to be
obtained in this regard, the modality of arbitration was adopted and
the claims of the decree holder against the judgment debtor were
referred to arbitration; in accordance with the understanding
aforesaid, a settlement agreement dated 30th November, 1999 was
arrived at between the parties and an arbitral award pronounced in
terms thereof. The counsel for the decree holder has submitted that
however thereafter the intentions of the judgment debtor turned
dishonest and the agreed awarded amounts were not paid to the
decree holder leading to the filing of the execution aforesaid.
6. The contention of the counsel for the decree holder qua non-
applicability of the bar of Section 22 of the SICA are two fold. Firstly
it is contended that the bar in Section 22(1) to proceedings for
execution does not apply to execution of arbitral award. Attention is
invited to Section 22(3) providing for the BIFR to order or declare
that the operation of any award to which a sick company is a party
shall remain stayed. It is contended that admittedly neither is there
any order of the BIFR nor has the judgment debtor company made
any application to the BIFR for stay of operation of the arbitral
award under execution. It is further argued that since the provision
with respect to arbitral award has been made in Section 22(3), it has
to be necessarily held that the reference in Section 22(1) to the
execution does not include the reference to the execution of an
award. Reliance in this regard is placed on the judgment of the
Division Bench of this court in M/s Lloyd Insulations (India) Ltd
Vs Cement Corporation of India Ltd ILR (2001) 1 Delhi 62 and
Morgan Securities and Credit Pvt Ltd Vs Modi Rubber Ltd AIR
2007 SC 683.
7. I do not find the contention raised by the counsel for the
decree holder to have been the subject matter of adjudication in
either of the aforesaid two decisions. It thus cannot be said that the
question raised is covered by either of the said judgments. All that
M/s Lloyd Insulations (supra) holds is that Section 22(1) does not
apply to a proceeding under Sections 14 and 17 of the Arbitration
Act 1940. The reason given therefore is that a petition under
Sections 14 and 17 of the Act is not a suit (though registered as a
suit). However, while holding so, another reason given is that the
arbitral awards are covered by Section 22(3) of the Act. The Division
Bench held that stay of the proceedings under Sections 14 and 17 of
the Arbitration Act, 1940 for making the arbitral award a rule of the
court, could be under Section 22(3) of the Act.
8. Similarly in Morgan Securities (supra) also no arbitral award
for execution was for consideration. What the Supreme Court held
in that case was that the bar of Section 22(1) of the Act did not come
in the way of a petition under Section 34 of the 1996 Act unless the
BIFR passes an order under Section 22(3) of the Act. While holding
so also the Supreme Court in para 68 of the judgment held that upon
the rejection of the objections to the award, the question of
enforceability of the award would come into being and once the
arbitral award having the force of a decree is put into execution sub-
Section (1) of Section 22 of SICA would come in its way from being
enforced.
9. It would thus be seen that the judgment of the Supreme Court
in Morgan Securities and Credit Pvt Ltd (supra) rather than
helping the decree holder is against the decree holder.
10. Even otherwise, a judgment is a precedent only on the matter
arising for consideration before the court. In neither of the aforesaid
judgments was the question of applicability of Section 22(1) to the
execution of arbitral award as a decree was before the court.
Nevertheless the observations aforesaid came to be made by the
Supreme Court and which, in my opinion, cannot also be brushed
aside as obiter.
11. Even otherwise the arbitral award under the Arbitration Act,
1996, as the award in the present case is, under Section 36 of the
Act is given the force of and made executable as a decree. Once the
same is executable as a decree, the effect of Section 22(1) of SICA
cannot be whittled down. Even otherwise considering the object of
enacting SICA and Section 22, there is no reasonable basis/ nexus
for carving out a distinction between execution of a decree and of an
arbitral award having the force of the decree. The purport is to
protect the properties of a sick company under rehabilitation from
being attached / sold in execution at the instance of the individual
creditors and which would come in the way of rehabilitation in the
larger interest. The said object would be defeated equally if
execution is permitted of an arbitral award and it does not make any
sense to prohibit execution of the decrees of the court but not of
awards of the arbitrator.
12. The Supreme Court in Jay Engineering Works Ltd Vs
Industry Facilitation Council AIR 2006 SC 3252 was concerned
with an award under the provisions of the Interest on Delayed
Payments to Small Scale and Ancillary Industrial Undertakings Act,
1993. The High Court held the said Act to be prevailing over the
SICA and held the award to be executable notwithstanding Section
22(1). The Supreme Court reversed the order of the High Court and
held that once the award is being executed as a decree before a civil
court, it will definitely attract Section 22 of SICA, even though
adjudicatory process of making an award under the aforesaid 1993
Act may n ot come within the preview of SICA but once an award is
made and sought to be executed, Section 22 of SICA will come into
play. Reference was also made to Section 32 of SICA making
provisions thereof notwithstanding inconsistencies with other laws.
13. The second contention of the counsel for the decree holder is
that the arbitral award in the present case is for recovery of dues of
the decree holder who was an employee of the judgment debtor
company. It is urged that Section 22 of SICA is not a bar for
recovery of dues of an employee of a sick company. Reference in
this regard is placed on Mideast India Ltd Vs Shri K.M. Unni
2002 IV AD Delhi 157 wherein a Single Judge of this Court in view of
and following judgments in Rajnagar Textiles Mills No. 1 Vs
Textile Labour Association (1998) 93 Company Cases 447; Shree
Chamundi Mopeds Ltd. Vs Church of South India Trust
Association (1992)75 Company Cases 440 and Deputy
Commercial Tax Officer v. Corromandal Pharmaceuticals,
(1997) 89 Company Cases 1 held that Section 22 of SICA would not
operate as a bar to the payment of dues of workmen, employees
following the adjudication of industrial disputes or determination of
dues under the provisions of Industrial Disputes Act.
14. As would be obvious, said observations were in view of the
provisions of the Industrial Disputes Act. The counsel for the decree
holder admits that the decree holder was not a workman and was/is
not covered by the provisions of the Industrial Disputes Act. He has
however contended that the principle would apply. However, I am
unable to accept the said contention. The courts have in various
context treated the workman to be different from managerial or
other employee. The law relating to a workman can thus not be made
applicable to non-workman employees. Thus, the contention of the
decree holder that Section 22(1) of SICA does not apply to the
present execution does not find favour with me and is rejected.
15. As far as the request of the decree holder for adjournment of
the present execution awaiting the permission from BIFR/AAIFIR is
concerned, I find that the execution under Section 22(1) does not
"lie". The execution as on the date of institution before this court
thus did not lie and ought not to remain on the docket of this court.
Even though the arbitral award of which execution is sought is dated
30th November, 1999, no prejudice shall be suffered by the decree
holder inasmuch as the time during which the decree holder was
prohibited from executing the same owing to the provisions of
Section 22 of SICA would be excluded in computing the limitation for
applying for execution. It is often found that parties, to serve their
own purpose, want to keep proceedings, which otherwise are not
maintainable, pending before this court. This court cannot allow its
process to be abused in this fashion and if found that the
proceedings do not lie before this court, the same cannot be
adjourned day after day merely awaiting the situation in which the
proceedings would be maintainable. Nothing substantial has
happened in these proceedings, the benefit whereof would be lost to
the decree holder in the event of applying afresh. Though issue was
framed when proceedings were pending before District Court but the
same appears to be misconceived in an much as in execution the
question whether arbitral award under the Arbitration Act, 1996 can
be set aside or not cannot be gone into. The execution petition is
thus dismissed. However, in the circumstances the parties are left to
bear their own costs.
RAJIV SAHAI ENDLAW (JUDGE) 18th August, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!