Citation : 2009 Latest Caselaw 1765 Del
Judgement Date : 30 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) 2669A/1998
% Date of Decision: 30th April, 2009
M/S ANANT RAJ AGENCIES ..... Plaintiffs
Through: Mr. Harish Malhotra, Senior
Advocate with Mr. Priyank Sharma,
Advocate
versus
DELHI DEVELOPMENT AUTHORITY & ANR. ..... Defendants
Through: Mr. D.S. Mahendru, Advocate
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may No
be allowed to see the judgment?
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
VIPIN SANGHI, J. (Oral)
I.A. NO.4191/1999
1. The respondent DDA has filed these objections under
Sections 30 and 33 of the Indian Arbitration Act, 1940, against the
award dated 02.11.1998 made by the sole arbitrator, Mr. L.R. Pahwa.
He was appointed as the sole arbitrator to adjudicate the claims of the
petitioner against the respondent arising out of a contract for
construction of 704 EWS houses in Block-F, Pocket-8 to 13 vide
agreement No.5/EE/RPD-5/DDA/85-86.
2. Learned counsel for the objector DDA, at the time of hearing
has made his submissions only in respect of a few items awarded by
the learned arbitrator and has not questioned the remaining award.
Accordingly, I now proceed to deal with each of the objections actually
raised by the objector and argued by the parties.
3. Claim No.1 was made for recovery of Rs.1,95,06,866/- plus
interest on account of non-payment of the final bill prepared and
submitted by the claimant/ petitioner. While dealing with this claim,
the learned arbitrator has dealt with various recoveries made by the
respondent-objector, which were put to challenge in arbitration.
Learned counsel for the respondent has sought to challenge the award
made in respect of the recovery of Rs.55,322.10 on account of
recovery of stipulated material at penal rates.
4. The respondent had sought to make a recovery at penal rates
of the aforesaid amount, since there was a difference in the theoretical
consumption and cement was provided by the respondent from its
stores. The learned arbitrator while allowing the said claim for refund
of an amount of Rs.55,322/- has taken into account the following
considerations:
(a) The respondent was not in a position to contend that there was
any misuse or pilferage or that the material was not consumed in
the work nor the respondent has been able to give any evidence
for loss being suffered, particularly when the recovery on the
single rate basis i.e. as per agreement rate has already been
made by the respondent.
(b) No notice had been issued by the respondent for any wastage or
any material rendered surplus.
(c) There was bound to be variation in the theoretical calculations
and actual calculations as sometime the cement is utilized for
redoing in any particular item and sometime the cement was less
in the bags issued.
(d) Similarly, in respect of SCI pipe and CI pipe, measurements are
not taken for the pipes spigot portion which are going into
socket. This also makes a difference in measurements.
(e) The respondent also failed to give the details of the recovery
and is vague in its submission.
(f) No proof of loss suffered by the respondent was produced before
the arbitrator.
5. Submission of learned counsel for the DDA is that in the
contract there was no stipulation requiring the respondent to issue a
notice with regard to material becoming surplus and on that account
recovery being made. This position is not disputed by learned counsel
for the petitioner. The contractual terms do not even make the penal
rate recovery subject to misuse or pilferage. This position is also
conceded by learned counsel for the petitioner. Since the recovery is
in accordance with terms of the contract and is in the nature of
liquidated damages, there was no requirement for the evidence of loss
suffered being led before the arbitrator. The fact that single rate
recovery is not disputed by the contractor itself establishes that there
was surplus material, which was not returned by the petitioner
contractor to the respondent. Pertinently, there was no challenge to
the single rate recovery by the petitioner. The arbitrator could not
have acted contrary to the agreement by introducing factors such as
variation in theoretical calculations and actual calculations for certain
assumed reasons such as the cement being utilized for redoing in
particular item and it being less in the bags issued. Similarly, he could
not have introduced factors such as the measurements not being
taken for pipe spigot portion which are going into socket. It is not
disputed by learned counsel for the petitioner that the theoretical
calculations are worked out by providing for margins for all such
factors as had been noted by the arbitrator. The purpose of penal rate
recovery appears to be to check pilferage of materials supplied by
respondent from its stores and also to prevent wastage on account of
mismanagement and tardy work by the contractor. The said recovery
being contractual, it cannot be disputed in the absence of any cogent
and material evidence. From the award of the learned arbitrator, it is
evident that he has acted merely on the basis of assumed shortage of
supply in the cement bags and assumed consumed in redoing any
particular item of work. Similarly, he has assumed that portions of
pipe which goes into the socket have not been measured. In my view,
the award in this respect cannot be sustained, as it is contrary to the
contractual term and is also founded upon factors which are beyond
the terms of the contract and have no factual basis. By acting contrary
to the contractual terms the learned Arbitrator has committed
misconduct of the proceedings. Accordingly, the objection of the
respondent in respect of the award of Rs.55,322.10 for refund of
recovery of stipulated material at penal rates is sustainable.
6. Learned counsel for the respondent has next sought to
impugn the award allowing refund of the recovery of Rs.33,943/- on
account of difference in costs of fitting at market rate and agreement
rates. The learned arbitrator has accepted the claim of the petitioner
on the ground that there was no liability of the claimant to pay the
difference of the cost of the fittings, as all the fittings were provided at
the time of completion of work and the work was declared completed
by the respondent on 15.11.1991 and at the time of recording the
completion certificate, it was not pointed out that any fittings were
missing or were not provided for by the claimant. The learned
arbitrator also found that the respondent had not placed on record any
notice given to the claimant during the maintenance period or
thereafter to the effect that the fittings had not been provided by the
petitioner or that the respondent was itself providing the fittings at the
risk and cost of the claimant. Learned counsel for the objector has not
been able to point out any material placed before the arbitrator to
show that this recovery was made after putting the respondent to
notice that the fittings were being provided by the respondent at the
risk and cost of the petitioner claimant. Accordingly, I see no merit in
this objection of the respondent and the same is rejected.
7. Learned counsel for the objector then impugns the award
made on the claim pertaining to item Nos. 3.5(a) & 3.5(c) of the
contract. The submission of the petitioner was that the respondent
had paid for the centering and shuttering of beams, which support the
suspended floors under agreement items for centering and shuttering
of lintels and beams i.e. agreement item No.3.5(c) instead of paying
the same under item No. 3.5(a). The claimant had relied para
5.2.9.1(c) of the CPWD specification 1977 Vol. I, which provided that
suspended floors landings and their support are to be measured under
one head. The roof beams are support to the roof slab. The
submission of the claimant was that since the centering and shuttering
of beams forming part of the suspended floors has to be removed after
the removal of the shuttering for suspended floor, there was no reason
for it not being paid under the agreement item No.3.5(a) relating to
centering and shuttering for suspended floor i.e. agreement item
No.3.5(a).
8. The learned arbitrator gave the following reason in his award
for allowing this claim for Rs.52,129/-:
"I have heard both the parties in details and have considered their respective submissions. I have also examined the agreement item no. 3.5 (a) and 3.5 (c) and the CPWD specification. The contentions of the claimant is correct and justified. The beams which form part of the suspended floors are in fact supports to the suspended floors and are not independent beams and form part of the suspended shuttering. These cannot be removed before the removal of centring and shuttering of the suspended floors. The centring and shuttering for the beams which forms part of the suspended floors has to be paid under the agreement item relating to suspended floor. In the CPWD specifications the word „support‟ has also been mentioned. The supports are nothing but the beams which give support to the suspended floor."
9. Learned counsel for the objector DDA has raised only a
general objection to the aforesaid award and is not able to point out as
to what is the error in the reasoning of the learned arbitrator, as
extracted above. The award has been made on the basis of the
undisputed figures and the award also indicates the manner of
calculation of the amount. Accordingly, I find no justification in this
objection of the objector. The same is accordingly, rejected.
10. Learned counsel for the objector next objects to the award on
the claim founded upon Items 3.7(a) and 3.7(b). This claim was made
by the claimant on account of quantity of steel less paid due to issue of
overweight steel by the respondent. It was contended by the claimant
petitioner that though the steel was issued by weightment, the
measurement were recorded by the respondent on the basis of length
multiplied by the standard weight of steel per meter length. The
arbitrator takes note of the notices issued by the claimant in Exhibits
C-2 to C-6, raising its said claim before the respondent. The
respondent had refuted the liability towards payment for overweight of
steel and contended that the payment had been made as per
conditions of the agreement and that the claimant could not claim any
extra payment. The respondent also contended that if and when
overweight steel was received by the claimant, it was for the claimant
to have informed the respondent. The learned arbitrator allowed this
claim by recording his reason as follows:
"I have heard both the parties in detail and have considered their respective submissions made in this regard. It is an admitted fact that as per the practice in DDA the steel is issued by the weight and the payment is made by applying the standard weights and the lengths
measured. The respondents admitted that the weight of steel paid has been calculated on the basis of standard steel weights. The respondent has also not denied the total quantity of steel issued to the claimant. There is no dispute about the quantity of tor steel being issued as 272718 kg and mild steel issued as 5510 kg. There is also no dispute that respondent has paid only 265206.20 kg of tor steel and 5160.13 of mild steel against agreement item no. 3.7(a) and 3.7 (b) respectively. There is no allegation on the part of the respondent that there was any wastage of steel at site. The difference in quantity issued and quantity paid has come because of different method adopted by the respondent in issuing and measuring the steel. The steel issued was overweight as is clear from the quantity issued and paid. Thus, the claimant is entitled for payment of difference of quantities due to overweight of mild steel and tor steel issued by the respondent.
11. Since the learned arbitrator has referred to Exhibits C-2 to C-
6 in the award, the same have been perused by me. Exhibits C-2 & C-
3 are communications dated 19.10.1985 and 22.10.1985 issued by the
petitioner making reference to a circular issued by CPWD dated
15.07.1982 and stating that "steel which is issued by the department
is mostly overweight". The letter dated 19.10.1985 further records
that as per para 1 of the CPWD circular M.S. Rounds or Tor Steel bars
upto and including 10 mm dia which are billed by the suppliers on
actual weight basis, will be verified and accounted for in the stock
account on actual weight basis and will also be issued on actual weight
basis. As per para II of the circular M.S. Rounds or Tor Steel bars
above 10 mm will on receipt, be verified and accounted for in stock
accounts on standard section weight basis. These will also be issued
on standard sectional weight basis. The claimant requested the
respondent that M.S. Rounds and Tor Steels above 10 mm diameter on
receipts from the departmental store on actual weight basis may be
converted on standard section weight basis and issued on standard
sectional weight basis by debiting or crediting the difference to the
work. The communication dated 22.10.1985 reiterated the aforesaid
position. Exhibit C-4 is another communication issued by the claimant
dated 29.10.1985. This communication makes a reference to the
respondent‟s letter dated 26.10.1985, which does not appear to have
been placed before the arbitrator. However, the communication
Exhibit C-4 indicates not only the stand of the respondent, but also
clearly brings out the fact that there was actually no basis for the
claimant petitioner to claim that the steel issued to it was overweight.
It appears that the petitioner took a blind shot in the dark by claiming
that the MS Rounds and Tor Steel bars issued to it were overweight,
while that position was denied by the respondent. The letter dated
29.10.1985, insofar as it is relevant, reads as follows:
"In your above cited letter, you have written that you have instructed our site representative and Asstt Engineer-I in charge of the work to follow the circular, but so far no over weight steel has been received.
We think that it is not possible to find out whether a steel is over weight or not by naked eye. The overweight can only be determined by periodical checking of the weight of the steel received from the departmental store by cutting samples and weighing etc."
12. From the correspondence Exhibits C-2 to C-6, it appears that
the grievance of the petitioner was that M.S. Rounds and Tor Steel bars
above 10 mm diameter was being supplied on actual weight basis and
not on standard section weight basis. However, that itself does not
lead to the conclusion that the steel i.e. M.S. Rounds and Tor Steel
above 10 mm diameter actually supplied by the respondent to the
petitioner was overweight. As stated by the petitioner itself in Exhibit
C -4, it is not possible to find out whether the steel is overweight or not
by a naked eye. The overweight can only be determined by periodical
checking of the weight of the steel received from the departmental
store by cutting samples and weighing etc. It was not the petitioner‟s
claim that this exercise had been done in respect of the MS Rounds
and Tor Steel bar of above 10 mm diameter. It is clear that there was
no evidence led before the arbitrator, for him to conclude that the M.S.
Rounds and Tor Steel bars of 10 mm diameter or above supplied to the
petitioner by the respondents was actually overweight. The learned
arbitrator has observed that the steel issued was overweight "as is
clear from the quantity issued and paid". I am not able to appreciate
this reasoning of the learned arbitrator. Mr. Malhotra, learned senior
counsel for the petitioner, has argued that it is for the arbitrator to
appreciate and evaluate the facts and the Court cannot go into the
same. It is not for the Court to examine the sufficiency and
insufficiency of evidence so long as there is some evidence placed
before the arbitrator.
13. There can be no quarrel with the legal proposition advanced
by Mr. Malhotra. However, the present appears to be a case where
there was no evidence at all before the arbitrator to conclude that the
steel issued by the respondent, namely, M.S. Rounds and Tor Steel
bars of above 10 mm diameter was overweight. Pertinently, this
position has been denied by the respondent not only in the
correspondence, as is evident from Exhibit C-4, but also before the
arbitrator, as is evident from award itself. The award on Item Nos.
3.7(a) and 3.7(b) appears to have been made without any evidence
whatsoever. This constitutes misconduct on the part of the Arbitrator.
For the aforesaid reasons, the award made by the arbitrator in respect
of item Nos. 3.7(a) and 3.7(b) for Rs.79,712.26 cannot be sustained
and is, therefore, set aside.
14. The next objection raised by Mr. Mahendru is in respect of the
award made by the arbitrator on the claim founded upon item 6.1 of
the contract. This item pertains to providing and fixing T. iron for
doors and windows. The case of the claimant before the arbitrator was
that the respondent had not measured the weight of the M.S. Lugs,
M.S. Flat welded at the back of the frame for fixing hinges, and the
base tie welded to the door frame at the bottom. The claimant had
claimed that as per the item, the entire weight of door/window frames
including lugs, M.S. flats and base tie are to be measured for payment.
15. The respondent had contested this claim by stating that the
claimant had provided M.S. base tie, M.S. Lugs and M.S. flats welded at
the back of the frame as per the agreement item. The payment had
been made on the basis of T. iron section only. The items, namely,
M.S. lugs, M.S. flats and tie bar are included in the rate and hence, not
payable.
16. The learned arbitrator notes that the respondent had not
denied the fixing of M.S. flats at the back of the frame for fixing butt
hinges and M.S. lugs and M.S. base tie being welded at the bottom of
the door frames. The learned arbitrator rejected the defence of the
respondent founded upon the interpretation of CPWD specification and
para 4 of the additional specification. He notes that the specification
does not provide that the M.S. lugs, M.S. flats and base tie are not to
be measured for the purpose of calculating the total weight of the
frames for payment. I see no force in the objection raised by the
respondent to the award made by the arbitrator on the said claim. It is
not the case of either of the parties that the contractor was not obliged
to provide the M.S. lugs, M.S. flats welded at the back of the frame for
fixing hinges and the base tie welded to the door frame at the bottom
under the contract item. The claim of the claimant was not that he
was required to do any additional item of work by providing the M.S.
lugs, M.S. flat and base tie. The claimant‟s claim is only that the
weight of M.S. lugs, M.S. flat as welded at the back of the frame for
fixing hinges and the base tie welded at the door frame at the bottom
should be included while computing the work done by the claimant.
The learned arbitrator has observed that the specification relied upon
by the respondent does not provide that the M.S. lugs, M.S. flat and
base tie are not measured for the purpose of calculating the total
weight for payment to the contractor. In my view, this finding of the
learned arbitrator is unexceptionable. Accordingly, this objection of
the respondent is rejected.
17. The next objection raised by Mr. Mahendru is in respect of
item No.9.9(a). The claimant had made a claim for applying primer
coat on new wood work. The same was awarded by the learned
arbitrator for Rs.42,083/-. The defence of the respondent to the said
claim was that the wooden door and window shutters which were
supplied to the claimant for fixing were already finished with the
primer coat and as such no primer coat was required to be applied on
shutters. On the other hand, the stand of the petitioner was that the
petitioner had applied a primer coat on the wooden doors and windows
supplied to them for fixing.
18. The learned arbitrator allowed the said claim on the
reasoning that the item for applying primer coat on the wood work is
provided in the agreement. On that basis he has proceeded to make
his award.
19. The submission of Mr. Mahendru, counsel for the DDA is that
this claim of the petitioner was allowed though totally devoid of any
evidence. The petitioner had not produced any material to show that it
had procured and applied primer on wooden doors and windows
shutters.
20. The reasoning given by the learned arbitrator, in my view, is
patently fallacious and cannot be sustained. Merely because in the
rate contract one of the items was pertaining to providing primer
coating on wooden doors and windows, it does not necessarily follow
that the said item of work was actually required to be performed by
the contractor or that it was actually done by the contractor. The rate
contract contains rates for varied specified items of work. As and
when the eventuality arises, the contractor is required to carry out the
works for which rates are fixed. There may be works required to be
carried out, which are even beyond the items specified in the rate
contract. For such items rates are to be fixed in accordance with the
contract. However, it does not follow that each and every item
contained in the rate contract has necessarily to be performed by the
contractor. The claim for application of primer could have been
sustained by the contractor by leading evidence to establish the
purchase and procurement of primer and its application on the wooden
doors and windows. The claimant contractor has, however, not led any
evidence to substantiate the claim. The learned arbitrator has
proceeded on the fallacious assumption that merely because the said
claim pertains to an item contained in the rate contract, the same
would have been performed by the contractor. Such an approach
clearly tantamount to misconduct on the part of the learned Arbitrator.
For the aforesaid reasons, I am of the view that the award on item
No.9.9(a) for Rs.42,083/- cannot be sustained and is, accordingly, set
aside.
21. The next objection of Mr. Mahendru is in respect of award
made pertaining to item No.19 for cutting holes 15cm X 15cm in RCC
work. The submission of Mr. Mahendru is that the cutting of holes in
RCC work for laying GI pipes and SCI pipes is to be done by the
contractor without charging any extra payment therefor under the
terms of the contract. He refers to condition No.5.1 of the agreement
which reads as follows:
"5.1 Cutting of holes in walls, floors, chajjas, R.C. C. slabs etc:
The tendered rate shall include the cost of cutting holes where ever required and making good the same and nothing extra shall be paid for this."
22. Mr. Mahendru submits that the learned Arbitrator has acted
in ignorance of this contractual term and awarded the claim contrary
to the said clause.
23. The submission of Mr. Malhotra in response to the aforesaid
clause pointed out by the respondent-objector is that the claimant
contractor was required to carry out extra work of cutting such of RCC
slab since the drawing were given belatedly. Had the drawings been
given on time, the occasion for cutting the RCC slab would not have
been arisen.
24. A perusal of condition No.5.1 shows that the same specifically
provides for cutting of holes, inter alia, in RCC slabs. It does not carve
out any exceptions. In my view, the award made by the learned
arbitrator on item No. 19 cannot be sustained since the same had been
made without even taking note of condition No.5.1. The arbitrator has
obviously not applied his mind to the said condition. Accordingly, the
award made in item No.19 for Rs.52,809.74 is set aside.
25. The next objection of Mr. Mahendru is in respect of the award
made on item Nos. 20(a) & 20 (b). This claim had been made for
providing SCI collars to SCI pipe 100mm dia and 75mm dia,
respectively. The claimant had stated that they were required to
provide the SCI collars and SCI pipe as the location of WC P-trap and
floor traps were such that the full length of pipes issued by the
respondent could not be laid. The provision of collars was necessary
as small length had to be joined while connecting these pipes to
vertical stacks of pipes. The pipes were issued by the department in
one length only. Had the respondent not wanted the collars to be
provided the claimant should have been issued the pipes of required
length. The arbitrator had awarded Rs.79,122/-. Mr. Mahendru has
referred to condition No.3.15 of the specifications and conditions at
page 57 which states "The contractor shall have to provide SCI collars
required for fixing of SCI pipes of the required size free of cost and
nothing extra shall be paid for the same."
26. The arbitrator, obviously, ignore the said clause and the
award made by him is contrary to the said clause. At the time of
arguments, Mr. Malhotra fairly concedes that the said award on item
Nos.20(a) and 20(b) cannot be sustained and fairly stated that the
same may be set aside. Accordingly, the award made on item
Nos.20(a) & 20(b) for Rs.79,122/- is set aside.
27. The next objection of Mr. Mahendru is that the award made
on item No.29 for straightening the bent up steel bars issued in coils
and bent up bundles, and for cutting bars to the lengths/sizes required
and hoisting the same for various levels cannot be sustained, in view of
the decision of this Court in Narain Das R. Israni v. Delhi
Development Authority 2005 VIII AD (Delhi) 556. The arbitrator has
awarded an amount of Rs. 2,78,228/- under this claim. It is agreed by
the petitioner as well that item 29 of the award is liable to be set aside
in view of the aforesaid decision. The same is, accordingly, set aside.
28. Mr. Mahendru has then raised an objection with regard to the
award made under item No.2 under the general heading "Other
Payments Due". This claim was made for reimbursement of loss
suffered due to infructuous expenditure on the hire charges of tools
and plants, materials for centering and shuttering rendered idle on
account of failure of department for delay in supplying the services,
plans for sewerage water supply route for electrical cables, non-supply
of doors and windows shutters and on account of timely decision not
being taken by the respondent.
29. The learned arbitrator has given detailed reasons to conclude
that the delay was entirely attributable to the respondent and that the
petitioner contractor was, therefore, entitled to be compensated on
account of such delay. He also took note of the fact that extension of
time was granted by the respondent without levy of liquidated
damages. The submission of the respondent that the petitioner was
not entitled to claim any further damages, apart from those provided
under clause 10CC was rejected by the learned arbitrator, by holding
that:
"The denial of the respondent for the liability of escalation on the ground that they have already paid escalation under clause 10 CC is devoid of any merits as the escalation which is paid under clause 10 CC does not take into its ambit the actual escalation coming to the work."
30. The reasoning adopted by the learned arbitrator appears to
be unsustainable in view of the decision of this Court in DDA v. U.
Kashyap 1998 VII AD (Delhi) 300. The ratio of this decision has been
further followed by this Court in Jagat Ram Trehan & Sons v. DDA
2002 (63) DRJ 119. Para 12 of the Jagat Ram Trehan (supra) reads
as follows:
"12. Now coming to the next objection of the counsel for the respondent with regard to the award of Rs.7,71,018/-, on account of escalation of cost of material and labour, in view of the fact that under clause 10 CC payment had already been made, the arbitrator was not justified in allowing the aforesaid amount as damages. Division Bench of this Court in Delhi Development Authority v. K.C. Goyal (supra) has held that once a particular formula is provided in the contract, applying some other formula and awarding the claim would amount to legal misconduct. Following the ratio of Delhi Development Authority v. K.C. Goyal (supra) I hold that arbitrator has committed legal misconduct in awarding a sum of Rs.7,71,018/- on account of escalation of cost of material and labour."
31. I, therefore, hold that the award on Item No. 2 under the
heading "Other Payment Due" for Rs. 32,02,641/- is unsustainable and
the same is set aside as the learned arbitrator has misconducted
himself.
32. Mr. Mahendru has also challenged the award made on item
No.3 towards reimbursement of expenses incurred on account of
infructuous expenditure in maintaining contingents or artisans, labour
and watch and ward staff after the date of completion recorded by the
department. The case of the claimant was that the claimant was
required to maintain its staff at the site on account of failure of the
respondent to take over possession. The arbitrator has awarded an
amount of Rs.1,23,000/- for the period 15.05.1992 till 14.08.1993, after
taking into account the defect liability period during which the
contractor was obliged to maintain its staff at the site from the date of
completion of the work. The submission of Mr. Mahendru is that the
respondent had issued various communications to the contractor which
are found on record dated 21.12.1995, 02.01.1996 and 30.01.1996,
whereby the respondent DDA had asked the claimant to handover the
possession of the flats to them.
33. In response, Mr. Malhotra points out that the period for which
the expenditure has been allowed is of the years 1992 and 1993,
whereas the respondent had asked for the possession only in the year
1995-96. In my view, no error can be found in the award made on item
No.3 since the DDA, it appears, was not in a position, and did not take
over the possession of the flats upto 14.08.1993. This objection is,
therefore, rejected.
34. It is lastly argued by Mr. Mahendru that the award made on
item Nos.2 & 3 towards pre suit interest, pendente lite and future
interest whereby the arbitrator has awarded interest @ 18% per
annum is unreasonable. Mr. Malhotra in response submitted that since
a large portion of the award has been set aside by the Court, the rate
of interest should not be reduced.
35. Taking into consideration the decision of this Court in Narain
Das R. Israni (supra) I am inclined to reduce the rate of interest for
the pre-suit and pendente lite period @ 12% per annum. Accordingly,
the award is made a rule of the Court and a decree is passed in terms
of thereof, except to the extent it has been set aside hereinabove. In
case the respondent makes payment of the decretal amount within
three months no further interest shall be payable. However, in case
the same is not so paid, the petitioner shall be entitled to further
interest from the date hereof till payment/realization @ 9% per annum.
Parties are left to bear their respective costs.
VIPIN SANGHI, J.
APRIL 28, 2009 rsk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!