Citation : 2009 Latest Caselaw 1740 Del
Judgement Date : 29 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: April 23, 2009
Date of Order: April 29, 2009
+ CS(OS) No.2578A/1996
% 29.04.2009
DURGA LAXMI BUILDERS ... Plaintiff/Petitioner
Through: Mr.Sandeep Sharma, Adv.
Versus
VICE CHANCELLOR UNIVERSITY OF DELHI
...Defendant/Respondent
Through: Mr. Mohinder J.S. Rupal with
Mr. Jatinder Khanna, Advs.
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment? Yes.
2. To be referred to the reporter or not? Yes.
3. Whether judgment should be reported in Digest? Yes.
JUDGMENT
1. Mr. P.R. Thakur was appointed as an Arbitrator to
adjudicate the dispute between the parties. He after passing an
award on 9th October, 1996 filed the award in the Court. Notice of
the award was sent to the parties and respondent filed objections
under Section 30/33 of the Arbitration and Conciliation Act, 1996
before the Court alleging therein that the Arbitrator had no
jurisdiction to decide the matter being beyond the contract and
there was no written agreement between the claimant and the
respondent as to invoke the jurisdiction of the Arbitrator. The
Arbitrator awarded a sum of Rs.2,42,288/- without any basis
invoking Clause 10 CC of CPWD Schedule. Clause 10 CC of the
CPWD Schedule was not applicable as it was nowhere provided in
the contract that any part of the guidelines of CPWD shall be
applicable in this case. The Arbitrator mis-conducted himself by not
going into the facts of the case properly. The initial contract
between the parties was for a civil construction work to the tune of
Rs.14.75 lakh. However, the contractor was given additional work
apart from the initial contract and this additional work was not to be
considered as part of the contract. Moreover, the time consumed in
the additional work has been wrongly considered by the Arbitrator
as delay in the initial contract on the part of the objector. All the
bills of additional work were submitted by the contractor as per
agreed terms and conditions and same were paid and accepted by
the contractor. The contractor had not raised issue of delay nor
made a complaint regarding delay at any point of time. It is also
stated that in the final calculation there was a calculation mistake of
around Rs.11,000/- made by the Arbitrator. The Objector submitted
that the claimant was not entitled to claims no. 1 and 3 and the
conclusion arrived at by the Arbitrator that there was delay of 14
months was contrary to the contract and the facts. It is also stated
that Arbitrator allowed claims without any rationale or basis and
mis-conducted himself in passing the impugned award.
2. The averments made by the objector/respondent were
denied by the contractor. Following issues were framed by the
Court:
"1. Whether the award dated 9.10.96 made and
published by the sole Arbitrator Shri.P.R. Thakur, is
liable to be set aside on the grounds stated in the
objection petition?
2. Relief."
3. An agreement for construction of housing complex at
South Delhi Campus, University of Delhi was executed between the
University of Delhi and the contractor in August, 1986. Prior to this
agreement a public notice of calling of tender was issued by the
petitioner. In his tender the contractor had put following 4
conditions:
1. 1% rebate for the final bill within 8 months of
completion of work and release of security deposit
within a week of expiry of maintenance period.
2. We wish our quoted charges beyond deviation
limit.
3. Rates are valid for 2 months from date of opening
of tender.
4. Any increase in price of Steel, GI and CI pipes and
their fittings (GI and CI) by Government of India will
be charged extra.
4. Initially, the price quoted by the contractor was
Rs.16,75,795/-. However, the record of arbitration shows that there
were certain modifications made in the tender and ultimate price
quoted was Rs.14,75,268.30. This tender of the petitioner was
accepted vide letter dated 28th May, 1986 wherein University
informed the contractor as under:
"Dear Sir,
Your lowest tender amounting to Rs.14,75,268.30 which is 66.47% above the estimated cost of Rs.8,86,200.00 put to tender for the work mentioned above has been accepted by the University authorities. Your letter No.Nil dated 28.2.86 in which you have withdrawn your conditions from Sl.No.1 to 4 of your above tender and confirmed the rate for item No.21 as Rs.125/- for 100 sq.meter instead of per se meter and your another letter No.Nil dated 7.5.86 in which you have extended the validity of the above tender upto 30.5.1986 shall form part of the agreement.
You are, therefore, requested kindly to call on this office along with non-judicial stamp paper of Rs.2/- in
order to complete the contractual formalities on CPWD Form No.8.
You may kindly note that the date of start of this work be reckoned from the 10th day after date of issue of this letter." (Emphasis added)
5. In pursuance of above letter, the contract between the
parties for construction of this complex was signed. The contract
between the parties did not refer to Clause 10CC of CPWD
Schedules. The contractor who had initially made a specific
condition of price increase in the tender had withdrawn this
condition before entering into agreement. The agreement provided
Clause 10C in respect of increase in price. Clause 10C provided that
if during the progress of works, the price of any material
incorporated in the works and/or wages of labour increase as a
direct result of the coming into force of any fresh law, or statutory
rule or order and such increase exceeds 10% of the price and/or
wages prevailing at the time of acceptance of the tender for the
work and if the contractor thereupon necessarily and properly pays
such increased price in respect of such materials/labour
incorporated in the execution of work, then such increase in the
material and wages if exceeds 10%, he would be entitled to
reimbursement to the extent of excess over 10%. This clause also
provided for benefit to the employer if the prices decreased.
6. It is settled law that Arbitrator is prisoner of the
contract. He cannot travel beyond the contract while considering
the dispute between the parties. In the present case, the learned
Arbitrator had awarded a sum of Rs.2,22,043/- under Clause 10CC of
CPWD guidelines relating to escalation in the prices of materials
observing that this amount was approximately 7 and a half per cent
of the cost of the work and the escalation appears to be just,
equitable and reasonable. The learned counsel for the contractor
has sought to justify awarding of this amount in view of judgment of
Narain Das R.Israni vs. DDA 1996(1) Arbitrator law Reporter 602
and K.N.Sathyapalan (dead) by LRs vs. State of Kerala and
Anr. and another decision in suit No.1832/98 between the same
parties decided by this Court on 18th January, 2002 and a decision in
suit No.1833A/98 between the same parties.
7. It is settled law that judgment in each case decides and
adjudicates the lis in that particular case and unless and until a
general law is laid down by the judgment under Article 141 of
Constitution of India, the judgment cannot be read laying down a
law. None of the judgments cited by the petitioner is relevant in this
case in view of the peculiar facts that the contractor in this case
made escalation as a pre-condition of contract in his tender
document, but later on he withdrew this condition of tender and
signed an agreement containing different escalation clause. It is
settled law that the parties are bound by the contract between them
and the Arbitrator who has to adjudicate the dispute between the
parties is also prisoner of the contract. He cannot invoke principles
of equity, fair play etc. to justify travelling beyond the contract. The
Arbitrator cannot ignore the specific terms of the contract entered
into between the parties and if he ignores he does misconduct. In
Food Corporation of India vs. Chandu Construction and Anr.
2007 (4) SCC 697, the Supreme Court observed that Arbitrator being
a creature of the agreement between the parties, has to operate
within the four corners of the agreement and if he ignores the
specific terms of the contract, it would be a question of jurisdictional
error on the face of the award, falling within the ambit of the legal
misconduct which could be corrected by the Court.
8. The Arbitrator in this case could not been relied upon
Clause 10 CC of CPWD general conditions since the contract
between the parties was very specific about price escalation and the
contractor had specifically given up his pre-condition of price
escalation before signing the contract. I therefore hold that the
award allowed by the learned Arbitrator on the basis of Clause 10CC
of the CPWD, general conditions was beyond jurisdiction. CPWD
general conditions did not form part of contract.
9. Claim no. 3 of the contract was for a sum of
Rs.3,29,400/- on account of infructuous expenditure incurred due to
prolongation of the contract. The learned Arbitrator considered that
the work got completed in 20 months instead of stipulated period of
6 months. The claimant had to maintain his establishment and
incur overhead expenditure at site for 14 additional months beyond
the contemplated period of 6 months. He therefore allowed a sum
of Rs.2,50,000/- as infructuous expenditure.
10. It is an undisputed fact that the contract for construction
awarded to the contractor was for a sum of Rs.14,75,268/-.
However the actual work carried out by the contractor was of over
Rs.30 lakh, i.e., more than double the amount of contract. As is
revealed from the documents, when the contract for the
construction of housing complex was going on, Delhi University had
other civil construction works. In normal course of business, the
University should have called fresh tenders since the other works
were of more than Rs.15 lakh but it seems that the present
contractor was a favourite of Delhi University and Delhi University
instead of issuing fresh tenders asked the contractor to do
additional civil works under the same contract. So, all subsequent
works at different places in the South Delhi Campus were allowed to
be done by the present contractor at the same rates which he
quoted for the housing complex and it is in this way that a contract
for Rs.14.75 lakh got swelled into a contract of over Rs.30 lakh.
Since the contractor had willingly undertaken to do works other than
contracted work at the rate, terms and conditions, this does not
mean that the completion period of entire work including the
additional work undertaken by the contractor had to be 6 months as
has been considered by the Arbitrator. The Arbitrator lost sight of
the material evidence that the actual contract was for Rs.14.75 lakh.
This amount had been received by the contractor long back. The
contracted work would have been completed long back and only the
bills for subsequent additional works were being given by the
contractor to Delhi University. When additional work was
undertaken by the contractor at different sites obviously additional
time in completion of work would be required. The Arbitrator could
not have considered that the additional work undertaken by the
contractor was part of the same work, neither was it the case of the
contractor or of the University that the original work swelled into the
double the amount. Rather it is the case of the contractor himself in
his claim that he had to carry his machinery at different places in
South Campus and that is why he had to spend infructuous
expenditure. The claim reads as under:
"work related to housing complex but work was got
carried out at several places in the whole of campus
which resulted in infructuous expenditure on
construction of water tanks, and brick plate forms for
mixing cement concrete and mortar at various
places. Lot of wastage of materials was there in
working at various places and there were wastage of
labour also in executing the work in various places.
The infructuous expenditure was incurred in
transportation of cement and various building
construction materials to different sites inside the
campus."
11. The contractor claimed under infructuous expenditure
the wages for engineers at the rate of Rs.3,000/- per month for 14
months, wages for work Mistri at the rate of Rs.2150/- per month for
14 months, 2 supervisors at the rate of Rs.2450/- for 14 months,
Pump and mixer operator and expenses on various other
miscellaneous matters. The claim on the face of it was frivolous and
ridiculous. If the contractor had undertaken additional work apart
from the initial housing complex at different places in the campus at
the same rate, it cannot be expected that the contractor would have
done this work without employing engineers, work mistris,
supervisors, drivers and mixers. The items rates quoted by the
contractor take care not only of the salaries of different staffs which
are employed by the contractor but also take care of his profits,
administrative expenses and overhead charges. When the
contractor accepted additional work of more than 15 lakh at
different sites in the campus he was very well aware that he would
have to get this work executed through engineers, supervisors,
mistris, etc. Claiming charges for employing engineers, work
mistris, supervisors, etc. for the work which he carried out apart
from the original work during the extended period was a surprising
claim and it is surprising that the Arbitrator entertained such a
claim. Even if original work had some additional items of work, the
claimant specifically provided under Clause 12 that in case there
were alterations, additions or substitutions in the original
specifications, drawings, designs and instructions such additions
shall not invalidate the contract and the time for completion of work
shall stand extended in the same proportion as the altered,
additional or substituted work bears to the original work. Over and
above this a further period to the extent of 25% of the time shall be
allowed to the contractor.
12. It is clear that even in case of additions and alterations
in the original contract work, the time was liable to be extended in
proportion to the additions and alterations. This case is not of the
additions to the original specifications and drawings. The original
work consisted of construction of a housing complex at one site but
the University and the contractor together agreed for more civil
works not related to housing complex, done at different places in
South Campus. The time consumed in these subsequent works
cannot be considered as delay in original work nor can be
considered that the subsequent works are part and parcels of the
original work or original contract. The subsequent works could have
been treated as part and parcel of the original contract only if the
additions or alterations were by way of change in specifications,
designs, drawings as provided in Clause 12. Even if we believe that
the additional work was to be part of the original contract, looking
into the facts that additional work was more than the original
contract, the time for the original contract was to be proportionately
increased and plus additional 25% time was to be given in terms of
Clause 12. The proportionate increase in time for the additional
work will be 7 months and if we take 25% more increase in the total
time, the work would have been required to be completed in
approximately 17 months. The work was completed in 20 months.
By no stretch of imagination, it can be said that there was 14
months delay in completion of work.
13. Moreover, there is no document to show that there was
any delay on the part of University of Delhi. A contractor, by
delaying the contract, cannot claim compensation in respect of
delay and enrich himself. Delaying the contract cannot have
premium. There is no evidence on record to show that during
currency of contract, respondent wrote any letter to university
about any hindrance being created by University in execution of
work by contractor.
14. I consider that in the present case, the Arbitrator grossly
mis-conducted himself in law by transgressing the express
provisions of the contract as stated in Clause 12 and not taking into
consideration that it was not a case of one contract but several
contracts which the contractor undertook after the present contract,
without any written agreement. I therefore consider that award of
the Arbitrator of claim no. 3 was without jurisdiction and liable to be
set aside.
15. Under claim no. 4, the Arbitrator has allowed a sum of
Rs.15,000/- to the contractor for purpose of Chowkidars and watch
and ward staff observing that though the petitioner had not
produced any Chowkidar as a witness nor had produced watch and
ward staff as a witness to show that he had employed them but
since the construction work did require watch and ward and for that
purpose Chowkidars had to be employed by the contractor he
allowed to them Rs.15,000/-. For the reasons stated in para 14
above for which I have disallowed the claim on infructuous
expenditure on account of delay of 14 months, this claim is also not
tenable. Every contractor is to employ watch and ward staff at the
construction site during the period he continues the construction.
He is not to be paid separately for watch and ward staff. It is part of
his work and job.
16. Claim no. 5 is in respect of the interest. The Arbitrator
has allowed 12% interest on different claims. I consider that 12%
interest allowed by the Arbitrator is on higher side I consider that
6% simple interest would meet the ends of justice. The award in
respect of claim no. 1(b), claim no. 3 and claim no. 4 is hereby set
aside. The award in respect of claim no. 1, claim no. 2 is upheld.
The claimant/contractor would be entitled to 6% p.a. simple interest
on these claims from the date amount became due till the payment.
The petition is disposed of in above terms.
April 29, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!