Citation : 2009 Latest Caselaw 1630 Del
Judgement Date : 24 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: 15.4.2009
Date of Order: April 24, 2009
OMP No. 670/2007
% 24.4.2009
Union of India
(Sr. Divisional Engineer-V, DRM Office) ... Petitioner
Through: Mr. S.R.Narayan, Advocate
Versus
M/s N.K.Sharma & Company ... Respondent
Through: Mr. Chetan Sharma, Sr. Advocate with
Mr. M.S.Ahluwalia, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
By this petition under Section 34 of the Arbitration & Conciliation Act,
1996, the petitioner has filed objections against the award dated 20.8.2007 given by
the Arbitral Tribunal in respect of the dispute between the parties.
2. Brief facts relevant for the purpose of deciding this petition are that the
respondent was awarded a contract of replacement of worn out pipes along with
laying of new PVC pipeline for water supply between Ram Nagar Complex and
Qutub Road Complex on 16.10.2002 at an overall cost of Rs.34,47,399/- The work
was to be completed by 15.2.2003. The respondent started work and the first
running bill of the respondent was released for a sum of Rs.10,43,025/- after
deduction of rebate, income tax and surcharge etc. with the certificate that the work
was carried out to the satisfaction of the petitioner. The bill included cost of supply
of PVC pipe measuring 4833.95 m. The petitioner granted an extension upto
15.7.2003 for completion of work, without penalty, and a corrigendum was issued to
the contract. The total value of contract was also enhanced to Rs.41,17,951.28 due
to increase in scope of work in connection with water supply. There was another
corrigendum to the contract and the value of the works was enhanced to Rs.42,
79,191.57. The second running bill of the contractor was prepared by the petitioner
for Rs.16,35,077.33, which included cost of supply of PVC pipe measuring 5393.75
m. The second running bill of the respondent was approved but the amount of
second bill was not released. The contention of the respondent/claimant had been
that even in respect of second bill, a certificate was given that the work had been
executed as per specifications. However, the second bill was put in cold storage
since competitors of the claimant made some complaints against him. The
respondent however was not asked to stop the work and continued to do the
balance work at site. The respondent pleaded that he completed the work as per
contract in spite of his second bill having not been released. The petitioner later
raised an objection about the quality of PVC pipes and alleged that PVC pipes were
not of the specified quality.
3. The petitioner's case had been that two samples of PVC pipe were
collected and sent to Shri Ram Institute for Industrial Research, Delhi for testing.
The test conducted on these samples viz. PN-1 & PN-2 showed that the samples
were not of the required quality as the samples, when put on internal hydrostatic
pressure test at 27decree C for one hour, got burst during the test. It is submitted
that after the test report dated 31.10.2003 was released; a letter was received from
General Manager (Vigilance) by the petitioner directing the petitioner to recover an
amount of 7.78 lac from the respondent/contractor for supply of substandard PVC
pipe, from the due payment of CC-II on account of bill and amount available with the
petitioner. Thus, this recovery was made from the other due payments payable to
the contractor.
4. The learned Arbitral Tribunal considered the grounds of non-payment
of the bill by the petitioner viz. failing of the pipe during testing and came to the
conclusion that test results of Shri Ram Institute for Industrial Research, Delhi were
not applicable to the claimants. It was observed that the PVC pipe which the
claimant was supposed to use was to have outside diameter of 110 mm and wall
thickness of 1.1 mm as per item no. 2145(j) of Northern Railway Standard Schedule
of Rates SOR-1996. The test report was silent about the outside diameter and wall
thickness required for withstanding internal hydrostatic pressure. The learned
Arbitral Tribunal concluded that the samples were sent with incomplete
specifications for tests which were required to be conducted on them. The test
reports were also incomplete. They elaborated that when the petitioner sent
samples PN-1 & PN-2 to the laboratory for "physical test" there was no mention of
basic essential parameters like wall thickness, test pressure, class of pipe and
whether the pipes were to be used for "internal work" or "external work". These
details were required to be mentioned to the testing laboratory. It also observed that
the two test reports in respect of the two samples did not specify the required details
like at what pressure the pipe, of what wall thickness, burst during the test, what was
the wall thickness of the samples to which class of pipe they belonged. There was
no mention in the test reports as how much internal hydrostatic pressure was applied
at 27 degree C for one hour because it was different for pipes of different
specifications and it was different for pipes used in "internal works" and "external
works". The learned Arbitral Tribunal gave detailed reasons as to why the test
results were not applicable in this case. I find no reasons to disagree with the
Arbitral Tribunal on this count.
5. After concluding that test results were not applicable the learned
Arbitral Tribunal regarding claim no.1 observed that the amount of second running
bill and the amount of total work done by the claimant came to Rs.30,09,800.53
however, since the claimant had claimed only Rs.21,00,000/-, the Arbitral Tribunal
awarded maximum of Rs.21,00,000/-. The petitioner has assailed this award on the
ground that sample of PVC pipe used by the claimant failed in laboratory, so the
quality of work was not in accordance with the contract and petitioner was not liable
to pay for spurious quality. Against claim no.2, of Rs.7,00,000/-, the Arbitral Tribunal
awarded a sum of Rs. 4,20,000/-. The petitioner has assailed the awarding of this
amount of Rs.4,20,000/- against cost of material on the ground that cost of material
was included in the running bill and no separate cost of material could be awarded
regarding substandard material lying on the site. The petitioner was not liable to pay
for material dumped at site and not used, rather petitioner made a counter claim of
Rs.10,00,000/- since this dumped material continued to occupy space in the Railway
Stores from July, 2003 to March, 2007.
6. A perusal of statement of claim filed by the claimant/respondent would
show that the respondent filed 08 claims. Claims no. 1, 2 & 3 were clubbed togher
by the respondent for Rs.31,00,000/-. The claimant explained these three claims in
its claim petition together by referring to the running bills raised by the claimant and
work done. The claimant concluded that the total amount payable to the claimant
under these three claims came to Rs. 29,91,532.07 which included work done till
end. Surprisingly, the learned Arbitral Tribunal went even beyond the claims. The
total amount receivable by the claimant was stated as Rs.29,91,532.07 against all
the three claims, the Arbitral Tribunal came to the conclusion that the amount
payable against claim no.1 alone was Rs. 30,09,800.53 but since the claimant had
restricted its claim to Rs.21,00,000/- they were allowing only Rs.21,00,000/-.
7. The claimant in its claim petition had not stated that he was entitled to
payment of Rs.7,00,000/- against material lying with the petitioner. The running bills
included cost of material and that was the reason that the claimant dealt with claims
no. 1, 2 & 3 together and the claimant only dealt with running bill, work done and the
amount payable to him. He had not separately claimed the price of PVC pipe. I
therefore, consider that the learned Arbitral Tribunal without any basis and without
any justification separately considered the amount of Rs.7,00,000/- towards PVC
pipe which was not even the case of the claimant and allowed Rs.4,20,000/-. He,
thus, mis-conducted himself. I therefore, disallow this part of the award.
8. There is no infirmity in the rest of the award made by the learned
Arbitral Tribunal. The learned Arbitral Tribunal has come to the conclusion that the
report of Shri Ram Institute for Industrial Research was not relevant and was not
applicable in this case. The samples neither were drawn properly nor were the
samples sent with proper specifications and instructions. I do not find any reason to
substitute my own opinion against the opinion of the learned Arbitral Tribunal. It is
settled law that this Court does not sit as a Court of appeal over the judgment of the
Arbitrator. The Arbitrator is the judge of facts and law both.
9. In view of my above discussion, the award passed by the learned
Arbitral Tribunal is modified to the extent that the claimant is entitled to
Rs.21,00,000/-, along with simple interest of 12% p.a. from the date of publishing of
the award till payment of the amount.
April 24, 2009 SHIV NARAYAN DHINGRA, J. vn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!