Citation : 2009 Latest Caselaw 1608 Del
Judgement Date : 23 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: March 31, 2009
Date of Order: April 23, 2009
+ OMP 286/2005
% 23.04.2009
MTNL ...Petitioner
Through : Mr. Ravi Sikri and Mr. Dipesh Sharma, Advocates
Versus
Vindhya Telelinks Ltd. & Ors. ...Respondent
Through: Ms. Amrita Sanghi with Mr. D. Singh, Advocates
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. The petitioner has filed this petition under Section 34 of the Arbitration
& Conciliation Act, 1996 (for short, "the Act") for setting aside the award
dated 24th February 2005 passed by the Arbitrator (respondent No.2)
directing petitioner to pay to the claimant a sum of Rs.7,86,261/- along with
pendent lite and future interest @ 8% per annum on the principal amount
from 1st April 2002 till the date of payment.
2. The grounds raised in the objections are that the learned Arbitrator
failed to appreciate that the dispute with respect to the liquidated damages
was outside the purview of the arbitration agreement and the award passed
by the learned Arbitrator was quorum non judice and liable to be set aside.
OMP 286.05 MTNL v.Vindhya Telelinks Ltd. & Ors Page 1 Of 6
3. The respondent in reply to the objections has stated that the objections
were barred by limitation. On merits, it is submitted that the objections raised
by the petitioner are not tenable.
4. Brief facts relevant for the purpose of deciding this petition are that the
petitioner had placed a purchase order dated 12th October 1994 for supply of
polythene insulated jelly tin telecom cables of different specifications on the
respondent. A delivery schedule of the supply of cables was given in the
Annexure-B to the order. The delivery schedule provided for supply of entire
quantity of cables up to 15th February 2000. The claimant (respondent herein)
vide letter dated 12th January 2000 requested for re-fixing the delivery
schedule so as to enable it to supply the entire quantity of cables till 31st
March 2000. Vide letter dated 28th February 2000, the petitioner extended the
delivery period for 10 weeks from the date of issue of order, for supply of
balance quantities, but only in respect of 7 sizes of cables out of 13 sizes. The
petitioner's letter gave a tabular statement indicating the new/ extended
delivery period of 7 sizes of cables ranging from 25 th March 2000 to 15th April
2000. The delivery schedule in respect of rest of the sizes of cables was not
provided. In fact, the petitioner had by a prior fax message told respondent/
claimant not to supply outstanding quantities in respect of 3 sizes cables
namely 400/0.5A, 400/0.5UA, 1200/0.5UA. The respondent vide letter dated
13th March 2000 reminded the petitioner that it had not given extension in
respect of remaining 6 sizes of cable and told that the quantities of cables of
those 6 sizes were also lying ready with it awaiting delivery and if extension
was given, the cables would be offered for inspection and delivery. No
response was received. The claimant /respondent sent a reminder dated 26th
April 2000 asking for re-fixing the schedule for rest of the 6 sizes of cables.
OMP 286.05 MTNL v.Vindhya Telelinks Ltd. & Ors Page 2 Of 6 The petitioner vide their letter dated 16th May 2000 extended the delivery
period in respect of 4 sizes of cables up to 31st May 2000 and did not extend
the delivery schedule of 2 sizes of cables namely 2000/0.4(A)/2000/04(UA).
The delivery schedule in respect of these two sizes was not extended despite
reminders. On 26th June 2001, the petitioner sent a communication to the
respondent short-closing the purchase order/ contract in respect of
outstanding quantities and also informed that the liquidated damages of the
amount of Rs.7,43,907/- had been imposed in respect of the quantities not
supplied. The Claimant/respondent was asked to deposit this amount. Since
this amount was not deposited by the respondent/claimant, the petitioner
invoked the bank guarantee to the extent of Rs.7,43,907/- and called upon
the bank to remit this amount. The Claimant learnt about the intended
invocation of bank guarantee and moved an application under Section 9
before this Court. Vide order dated 12th October 2001, this Court directed the
bank to withhold the payment against the bank guarantee. However it
subsequently transpired that by the time this Court order was served on the
bank, the bank had already remitted the amount to the petitioner. However,
while finally deciding the application under Section 9 of the Act, this Court
held that invocation of the bank guarantee was not in accordance with the
terms of the bank guarantee and was bad in law.
5. The Claimant/ respondent later on invoked the arbitration clause and
made a claim of Rs.1,49,76,134/- as damages on account of loss and a claim
for refund of Rs.7,43,907/- recovered by the respondent by invocation of
performance bank guarantee along with interest.
6. It is noted by the Arbitrator that during arguments, the claimant
OMP 286.05 MTNL v.Vindhya Telelinks Ltd. & Ors Page 3 Of 6 /respondent did not advance arguments in respect of claim of
Rs.1,49,76,134/- (claim No.1) and only made submissions for refund of
Rs.7,43,907/-. However, since the claim No.1 was not formally withdrawn, the
learned Arbitrator considered both the claims and found that claim for
damages /profits for an amount of Rs.1,49,76,134/- was not tenable and
allowed the claim for Rs.7,43,907/- along with 8% interest.
7. A perusal of award passed by learned Arbitrator would show that the
Arbitrator had considered the provisions contained in the contract regarding
levy of liquidated damages and rescission of contract and found that the
petitioner had not imposed any liquidated damages in respect of cables
where the quantity of cables were supplied with delay under rescheduled
delivery period. The liquidated damages had been imposed on those
quantities which had not been supplied. The Arbitrator observed that the
question of invocation of clause 16 regarding imposition of liquidated
damages does not arise in this case and the clause was not attracted in case
of the material being not supplied. It was only attracted in case where the
material was supplied beyond the time schedule and the petitioner had
liberty to impose the liquidated damages because of delayed supply. The
learned Arbitrator observed that in case no supply was made and the contract
was short-closed on account of non supply, the question of imposition of
liquidated damages would not arise. The Arbitrator also found that the
petitioner had not served any notice under Clause 18(1) of the contract for
termination of the contract and even termination of contract being in violation
of clause 18 was bad in law.
8. It is settled law that this Court does not sit in appeal over the judgment
OMP 286.05 MTNL v.Vindhya Telelinks Ltd. & Ors Page 4 Of 6 of the Arbitrator. If the Arbitrator has given plausible interpretation to the
different provisions of contract, the Court cannot reject the interpretation
because another interpretation was also feasible. There is no dispute to the
fact that this court had passed order finally disposing of the earlier
application under Section 9 of the Act holding inter alia that the invocation of
the bank guarantee by the petitioner was contrary to the terms and
conditions of the bank guarantee and was bad in law. This order was not
assailed and had become final. This Court while passing order under Section 9
had considered the provisions of the bank guarantee as well as the provisions
of the contract between the parties and after considering the provisions of
the contract and the language of the bank guarantee, this Court came to
conclusion that the performance bank guarantee was wrongly invoked by the
petitioner and the bank guarantee did not include the instance of failure to
make supply by the scheduled date to the petitioner. The invocation of bank
guarantee was bad in law.
9. The contention of the petitioner that the issue of liquidated damages
was beyond the purview of the Arbitrator is also not tenable. Whether the
liquidated damages could be levied in case of short supply of cables is an
issue which was required to be gone into on the basis of contract. It is not the
case where the liquidated damages had been imposed by the petitioner for
delayed supply. The petitioner though had in the extension letter written that
the extension was being given subject to condition of liquidated damages but
the petitioner did not impose liquidated damages in case of delayed supply
and imposed liquidated damages for short supply of the cables, despite the
fact that the respondent had been writing to the petitioner that the cables
were ready and it should take the delivery of cables. The learned Arbitrator
OMP 286.05 MTNL v.Vindhya Telelinks Ltd. & Ors Page 5 Of 6 had authority to decide the issue if in view of provisions of the Contract,
petitioner could impose liquidated damages for short supply of cables in case
of closure of contract. The learned Arbitrator did not exceed his jurisdiction.
10. In view of foregoing facts and discussion, I find no force in this petition.
The petition is hereby dismissed. No orders as to costs.
11. Since I have dismissed the objections raised by the petitioner on
merits, I consider that there was no necessity to deal with the issue of delay
in refilling the objections.
April 23, 2009 SHIV NARAYAN DHINGRA J. rd OMP 286.05 MTNL v.Vindhya Telelinks Ltd. & Ors Page 6 Of 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!