Citation : 2009 Latest Caselaw 1607 Del
Judgement Date : 23 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.S.(OS) 2145A/1999
Date of Decision: 23st April, 2009
GOEL ASSOCIATES ... Petitioner
Through: Mr. D.R. Bhatia, Advocate.
versus
ECIL COOP. GROUP HOUSING SOCIETY ..... Respondent
Through: Mr. S.C. Singhal, Advocate.
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may No
be allowed to see the judgment?
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
% JUDGMENT (Oral)
VIPIN SANGHI, J.
1. This petition under Section 34 of the Arbitration & Conciliation
Act 1996 (The Act) has been filed to challenge the award dated
27.08.1999 in Arbitration Case No. 97/1998 passed by Mr. Justice P.K.
Bahri (retd.) on the claims preferred by the petitioner/consultant and
counter-claims preferred by the respondent society.
2. The parties entered into an agreement dated 09.04.1996
whereunder the petitioner was appointed as the consultant architect
for the construction of Group Housing Society Flats for the members of
the respondent society. Clause 12 of the agreement entitled the
society to terminate the contract at any stage, if they found the
services of the architect are not satisfactory. The services of the
petitioner/claimant were terminated on 05.04.1997. The same gave
rise to disputes between the parties which were sought to be referred
to arbitration.
3. Before the learned Arbitrator the defence of the respondent
society, to justify the termination of the contract was that the
petitioner/architect was insisting on the appointment of a contractor of
his own choice and was threatening the respondent society that in the
event of named contractor not being appointed, the respondent
society would suffer adverse consequences. The learned Arbitrator
accepted the aforesaid ground on a perusal of the materials placed on
record including the resolutions passed by the Managing Committee
prior to the termination of the agreement dated 09.04.1996.
4. The learned Arbitrator found that the petitioner had been
paid an amount of Rs. 1,26,000/- till the time of termination. He
rejected the claim for balance fee payable under the agreement which
would have been paid to the petitioner, had it not been terminated
earlier. He also rejected the claim for damages on account of loss of
reputation and business due to termination of the contract on the
ground that no evidence was led and no submission was made in that
regard. The counter-claims of the respondent society were also
rejected as being an afterthought and a counter blast to the claims of
the claimant. Consequently, the learned Arbitrator made a `NIL'
award.
5. The first submission of Mr. D.R. Bhatia, counsel for the
petitioner/objector is that initially the learned Arbitrator had fixed his
fee at Rs. 5,000/- per hearing to be shared equally by both the parties.
However, after the filing of the counter-claims by the respondent in
excess of Rs. 1 crore, the fees was upwardly revised to Rs. 10,000/- per
hearing to be shared equally by the parties. He submits that the
upward revision disabled the petitioner/claimant from pursuing the
arbitration proceedings effectively. He submits that on this ground the
award should be set aside.
6. I find no merit in the submission of Mr. Bhatia. Admittedly,
no such grievance was raised by the petitioner before the learned
Arbitrator or before the court during the stage of arbitration. The
petitioner willingly participated in the proceedings without raising any
such objection. Even in the present objection petition, I find that
paragraph 8, apart from reciting the aforesaid development does not
state that the petitioner was unable to pay the fee and that he has
suffered on that account. I, therefore, reject this submission.
7. The next submission of learned counsel for the
petitioner/objector is that the petitioner during the course of the
arbitration proceedings had moved an application dated 07.02.1999
before the learned Arbitrator requiring the respondent society to
produce the following record in their power and possession:
"Minute books of the Managing Committee and Annual General Body Meetings along with
secretary as report if any held after 09.04.1996".
8. The submission of Mr. Bhatia is that the learned Arbitrator,
however, did not pass any orders on this application. Instead he
proceeded to hear the matter and passed the impugned award
wherein it was held by him that the justification offered by the
respondent society for termination of the contract was made out.
9. The relevant part of the award dealing with the aforesaid issue
reads as follows:
"40. Coming back to the real issue I am only left with the copies of resolutions of the Managing Committee of the respondent on this subject (Annexure R 5). Minutes of meeting of 15.3.1997 show that tenders of seven contractors were received and at the time of opening of tenders, five contractors were present who deposited the earnest money with the tenders. Minutes of the meeting dated 19.3.1997 show that the Secretary informed the committee that the claimant had been sending threatening messages that if the contractor of his choice and liking was not appointed, he would do his best to damage the working of the society and had threatened to make a report to the Registrar against appointment of any contractor of the choice of the Committee. He also informed that soon after his confrontation with the General Body on 26.7.1996, he canvassed for appointment of contractor, preferably M/S Chinar or M/s..... The name of the said proposed contractor is not recorded. The minutes proceed to record that the Managing Committee had been resisting the pressure of the claimant for appointment of contractor of his choice and had advertised in newspapers for getting tenders. It is further
recorded that the claimant for long had been insisting on giving contract on square foot basis rather than on item rates and on that score the tender work was delayed, as the committee did not yield to his demand. It is further mentioned that the claimant wanted to short-list the contractors to be selected and approved by him. The Secretary informed that after the letters had been issued to the contractors, the claimant told the Secretary that only that contractor would work in the society, which would be approved by him. The Secretary told the claimant that it was the sole discretion of the Managing Committee to appoint a contractor and the claimant would have no say in the matter.
41. The Society informed that the claimant had conveyed through Associate Architect that he would create a scene in the General Body and put the committee in difficult situation by telling that he had a tender of the a contractor at very low rates. The Managing Committee then recorded that the claimant would not be allowed to have any say and after negotiating with tenderers, selected M/S Viz Contractors (P) Ltd., as contractor.
42. The minutes of meeting dated 5.4.1997 show that the claimant continued to maintain high pressure tactics for appointment of his own contractor and threatened to blackmail the office bearers on Bhoomi Puja day on 12.9.1997. The Managing Committee thus took decision to terminate his contract. Soon after the termination letter was received, the claimant lodged a complaint with the Registrar against the Managing Committee in which he alleged that against his advice, the committee has awarded the contract at Rs. 660 lakhs while the rate comes to Rs. 540/- per sq. ft., when it should have been Rs. 440/- per sq. ft. He gave the total area as 1,12,500 sq. ft. It is
significant to note that the claimant in his bills for getting his fee himself has quoted the rate of Rs. 600/- per sq. ft. and estimated total cost of Rs. 631 lakhs and got Rs. 1,28,200/-, the ten per cent fee on that basis. This immediate reaction of the claimant shows that he was not happy with the Managing Committee for not toeing his line in selection of the contractor. There were eight members of the Managing Committee. They had no ill will towards the claimant. There is no reason to doubt the correctness of facts recorded in the minutes of the meetings of the Managing Committee.
43. It is evident that the claimant was putting pressure on the Committee to appoint contractor in consultation with him and as the Committee did not relent, he threatened to put the office bearers in bad light before other members of the society.
44. The learned counsel for the claimant has vehemently contended that a clumsy attempt has been made to have some ground for terminating the contract. He has pointed out that the names of contractors whom the claimant favoured for appointment are not even disclosed. In the minutes name of one contractor is mentioned but the same is quite incomplete and there is blank space kept wherein name of second contractor was supposed to be indicated. Nothing in my view turns on this. In case the respondent intended to incorporate any wrong names, the respondent had enough opportunity to do so. Keeping the record as it is, the respondent has acted fairly. Whatever information the Secretary made available, was incorporated in the minutes.
45. The facts appearing in the minutes of the two meetings of the Managing Committee leave no room for doubt that the claimant was exceeding his duties and obligations
enumerated in the contract. He had no business to try to impose his choice on the Committee. The threats being held out by him to the members of the Managing Committee were in bad taste. From such facts any prudent person could conclude that the work of the claimant as an Architect is not satisfactory. Thus I reach the finding that the respondent was within its rights to terminate the contract in consonance with letter and spirit of the clause 12 of the contract."
10. I find no merit in the submission of Mr. Bhatia for various
reasons. Firstly, the learned Arbitrator has returned a finding of fact
with regard to the petitioner exerting undue pressure on the
respondent society. The arbitrator is the final judge of facts. In these
proceedings, it is not for the Court to re-appreciate the material and
evidence placed before the Arbitrator and arrive at its own findings on
issues of fact. It cannot be said that the finding of the learned
Arbitrator on the said issue is based on no evidence or material
whatsoever. So long as there was some material before him, he could
base his findings on the same. It is not for this Court to judge the
sufficiency or insufficiency of the evidence. A perusal of the award
would show that the learned Arbitrator upheld the defence of the
respondent society that the petitioner was exerting undue pressure on
the society for appointment of a particular contractor of his own
choice, inter alia, on the basis of the minutes of the meeting dated
19.03.1997.
11. The learned Arbitrator was not concerned and did not look into
all the minutes of the Managing Committee Meeting and Annual
General Meeting held after 09.04.1996 (which was the date of
appointment of the petitioner as the architect) as sought for by the
petitioner claimant in his application. This is for the reason that there
was no dispute or issue raised with regard to the initial appointment or
working of the petitioner. The agreement executed between the
parties was an admitted document and no controversy with regard to
the same was ever raised. There was no reason for the learned
Arbitrator to, therefore, summon the record for the period after
09.04.1996.
12. Mr. Bhatia has submitted that the date 09.04.1996 was
mistakenly typed in the application dated 07.02.1999 moved before
the learned Arbitrator. The same ought to be read as 09.04.1997. In
my view, even if the aforesaid was a typographical error before the
learned Arbitrator, the same cannot be corrected at this stage before
me. The fact of the matter is that the learned Arbitrator proceeded on
the basis of the record before him. He had no reason to believe that
the petitioner was desirous of calling for the record pertaining to the
meetings held on 19.03.1997 and/or 05.04.1997. At this stage, Mr.
Bhatia submits that the petitioner had asked for the minutes of the
Managing Committee and Annual General Body and the report of the
secretary after the appointment of the architect on 09.04.1996.
Consequently, the same included the entire record up to the date of
termination and not just the record immediately after the appointment
of the petitioner as the architect.
13. Since the learned Arbitrator found in favour of the petitioner that
the work of the petitioner, till the date of termination of the contract
was satisfactory, in my view, there was no occasion for the learned
Arbitrator to have summoned the entire record as required by the
petitioner and the failure of the Arbitrator, in any event, cannot be said
to have vitiated the award.
14. In any event, to satisfy the conscience of the court as to whether
the production of the original minutes/proceedings register before the
learned Arbitrator could have had any material bearing on the
determination of the Arbitrator, the respondent was directed to
produce the original record containing the minutes of Managing
Committee Meetings held at the relevant time. The same has been
produced before the court and has been perused by me. The
proceedings register shows that a Managing Committee meeting was
held on 15.03.1997 (which begins at page 24 and ends at page 29 of
the proceedings register). In this meeting resolution nos. 44, 45 and
46 were passed. The next meeting of the Managing Committee of
which the minutes are recorded is of 19.03.1997. As recorded by the
learned Arbitrator, the minutes of Managing Committee meeting of
19.03.1997 (which begin on page 30 and end on page 33 of the
proceeding register) clearly bring out the stand of the respondent that
the architect had been sending threatening messages that if the
contractor of his own choice and liking was not appointed by the
Managing Committee, he would do his best to damage the work of the
society and its standing. He even threatened to report with the
Registrar Cooperative Societies against the appointment of contractor
of the choice of the Managing Committee. These minutes also record
that immediately after his confirmation by the General Body on
28.07.1996, the architect had started canvassing for appointment of
the contractor, preferably M/s. Chinar and one other contractor whose
name is not recorded in the minutes. The resolution no. 47 passed on
the said date also records that the Managing Committee seriously
reviewed the situation and decided that the independence of the
Managing Committee would be maintained and that the architect
would not be allowed to have its contractor thrust on the society. This
was followed by the next meeting of the Managing Committee of
23.03.1997. The resolution passed in this meeting bears resolution
no. 47-A. It is, therefore, seen that the proceedings register as
maintained by the respondent society appears to be genuine and a
properly and routinely maintained document. The minutes of the
Managing Committee Meeting dated 19.03.1997 appear to be
contemporaneously recorded since they are preceded by minutes of
15.03.1997 (wherein resolution Nos. 44, 45 and 46 were passed) and
succeeded by the Managing Committee Meeting minutes of
23.03.1997 (when resolution no.47A was passed).
15. Mr. Bhatia, learned counsel for the objector submits that a
perusal of the register shows that the minutes of the Managing
Committee Meeting held on 05.04.1997, wherein it was resolved that
the contract with the petitioner be terminated vide resolution no. 48,
have been separately written out and pasted in the minute book.
16. In my view, that by itself cannot lead to an unimpeachable
conclusion that the Minutes of the meetings dated 19.03.1997 and
05.04.1997 are false and fabricated as contended by the petitioner and
raise a doubt so far as the genuineness of the said minutes are
concerned. As aforesaid, these are issues of fact on which the learned
Arbitrator and not the Court is the final judge. Undoubtedly, two views
were possible. The Arbitrator has accepted the view that the Minutes
dated 05.04.1997 were genuine as he has relied on the same.
Pertinently, by the same resolution no.48 passed on 05.04.1997, by
which the petitioner was removed the new architect M/s. Vidhyanath
Associates was recommended for appointment. The minutes dated
19.3.1997 were not put to challenge by the petitioner on any ground.
17. Moreover, the issue before the Arbitrator was whether the
respondent society had a justifiable ground available to it to terminate
the contract with the petitioner. The fact that such ground was
available is evident from the contemporaneously recorded minutes of
19.03.1997.
18. My attention has also been drawn to para 15 of the award. It
appears that the parties had agreed that no oral evidence would be led
and no cross-examination of witness would be done and only final
arguments shall be advanced. The respondent society had filed its
affidavit by way of evidence and placed the resolutions dated
15.03.1997, 19.03.1997 and 05.04.1997 on record and relied upon the
same. These were relied upon by the learned Arbitrator in view of the
aforesaid understanding between the parties.
19. For the aforesaid reasons I see no merit in the objection of
the petitioner with regard to the non consideration of the petitioner's
application dated 07.02.1999. I find no merit in the petition. The
same is accordingly dismissed. The parties shall bear their respective
costs.
VIPIN SANGHI, J.
April 23, 2009 dp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!