Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. India Furnishers vs Punjab National Bank
2009 Latest Caselaw 1579 Del

Citation : 2009 Latest Caselaw 1579 Del
Judgement Date : 22 April, 2009

Delhi High Court
M/S. India Furnishers vs Punjab National Bank on 22 April, 2009
Author: Mukul Mudgal
R-11
*    IN THE HIGH COURT OF DELHI AT NEW DELHI

                                        Date of decision : April 22, 2009

+                   FAO(OS) 261/2001


        M/S. INDIA FURNISHERS                           ... Appellant
                       Through Mr. B.K.Dewan with Mr. Bhavesh Kr.
                       Sharma, Advs.

                    versus

        PUNJAB NATIONAL BANK                          .. Respondent
                     Through : Mr. Jagdeep Kishore, Adv.

        CORAM:
        HON'BLE MR. JUSTICE MUKUL MUDGAL
        HON'BLE MR. JUSTICE VALMIKI J. MEHTA

     1. Whether the Reporters of local papers may be allowed to see
        the judgment?                                           Yes

     2. To be referred to the Reporter or not?                  Yes


     3. Whether the judgment should be reported in the Digest? Yes



 %                           JUDGMENT (ORAL)

MUKUL MUDGAL, J.

1. The appellant challenges the judgment of the learned Single Judge dated

15th March, 2001 by which the objections of the respondent against the award

dated 24th December, 1993 were allowed and the award set aside on the ground

that the Umpire had not given reasons for awarding of the estimated amount in

FAO (OS) 261/2001 Page 1 respect of claims No.7,11 and 12.

2. The learned Single Judge instead of remanding the matter thought it fit to

appoint a learned senior counsel of this court as an arbitrator. This direction for

the appointment of the arbitrator by the learned Single Judge was stayed by the

Division Bench of this court while admitting the appeal. The learned Single

Judge has further held that for awarding the amount payable to the appellant

only conclusions have been given by the arbitrator which are not supported by

any reasons, even though the award is a reasoned award.

3. The counsel for the appellant flawed the judgment of the learned Single

Judge on the ground that the contract between the parties did not require reasons

to be given. We have perused the contract and it is apparent that no reasons are

required to be given as is evident from the perusal of clause 13 which is set out

hereunder :

"13. ARBITRATION In case any dispute or difference arises between the Contractor on any matter within the scope of this contract, except as the matter left entirely to the discretion of the Interior Designers under the provisions of this Agreement, then either party shall forthwith give to the other written notice of such dispute or difference and such dispute or difference shall be referred to arbitration of an Arbitrator or Arbitrators, one to be nominated by the Employer and the other by the Contractor, or failing agreement between the said arbitrators, by an Umpire appointed by them and such award shall be binding on both the parties. The procedure laid down the Indian Arbitration Act 1940 shall apply in the matter of this reference."

4. The reasoning of the learned Single Judge thus does not appear to be

justified as clause 13 of the Arbitration Agreement does not require any reasons

FAO (OS) 261/2001 Page 2 to be given by the arbitrator. If the reasons given are inadequate then at best the

award becomes a non-speaking award, but after all if the Arbitrator or Umpire

can pass a non-speaking award, then, no fault can be found with an award on

the ground that the reasoning is absent or lacking or inadequate.

5. Furthermore, upon a perusal of the award itself we find that in fact

reasons were given. For this purpose we deem it necessary to extract the

relevant portions of the award by the arbitrator in respect of claims No.7,11 and

12.

"Claim No.7 : Claimants are entitled for the damages to the tune of Rs.1,66,046/- on account of prolongation of the contract and execution of the contract beyond the stipulated date of completion. The stipulated date under the contract was 31.1.1988. The period of work was extended by respondent. The work was to be done under schedule on the basis of samples. Only 13 samples were given upto 31.1.1988 as against 100 samples. There is no doubt that the work was done by claimant during months after the stipulated date. The claimant informed the Consultant that the expenses would be more and wanted escalation charges. This claim for escalation was to be considered as promised by Consultants after the completion of work. I hold that the claimant is entitled to escalation. The manufacturing of most of the furniture was completed by September, 1988. I have already found that the delay is attributable to Respondent. The respondent is the defaulting party.

I have considered over the amount of claim for prolongation of the contract and I estimate that a sum of Rs.1,00,000/- is awardable to claimant."

"The claim No.10 is disallowed.

Claim No.11 : Claim for Rs.2.48,352.54P for running hired workshop for manufacture of the at C-166 Okhla Industrial Area, Phase I. Claim No.12 : Claim for Rs.2,56,184.14 for hiring of godown for storage of furniture.

I am taking up the items together treating the claims for compensation for default of Respondent in not providing the claimant with space for storage and space for temporary workshop at the site under the agreement of contract. There is no doubt that the Respondent was bound to give space for storage and space for workshop at the site and the Respondent failed to provide the space for storage and workshop at the site. The Respondent however permitted the storage of

FAO (OS) 261/2001 Page 3 furniture in the currency chest. But the space was insufficient and the major part of furniture had to be stored in a godown. The Respondent were at fault in not providing any space for workshop and storage. As said by learned counsel for claimant that it was a breach of contract. I think the claimant is entitled for compensation. I have heard arguments of the counsel for the parties. It was urged by the counsel of respondent that as the lessors were relation of Dayal Motwane the leases produced were bogus and no payment was made. The witness produced by the respondent and by a representative of Consultants did admit of the hired workshop at Okhla and the hired godown.

I am not impressed by the above argument. As I am estimating the compensation I need not concern myself with the actual payment as pleaded by Claimant. On a consideration of the circumstances I estimate the compensation at Rs. 2,50,000/-.

I award Rs. 2,50,000/- as compensation."

6. We thus find that the learned Single Judge may not be right even on this

ground as certain reasons in support of the conclusions have been given in the

award though the same may not be as elaborate. The judgments in Bank of

Baroda v. B.J.Bhambani and another, 1988 (Supp.) SCC 785 and Gujarat

Water Supply and Sewerage Board v. Unique Erectors (Gujarat) (P) Ltd.

and another, 1989 Vol.1 SCC 532 may be usefully referred to that even if the

Award has to be a reasoned Award even then the reasons may not be very

elaborate and all that is required is that the reasons disclosed the mind of the

Arbitrator. Even if it is to be assumed that the reasons were to be given, though

not so required by the Contractual Clause, it is amply clear that since some

reasons are given we do not feel that the Award warrants interference. Besides

that we cannot lose sight of the fact that the Arbitrator is a technical person and

is sufficiently experienced to estimate the amount in a fair manner.

7. Accordingly, we set aside the judgment of the learned Single Judge. Mr.

FAO (OS) 261/2001 Page 4 Kishore, the learned counsel for the respondent further pleaded that the interest

of 15% per annum on the award amount works against the respondent in view

of the fact that the award was passed long back on 24th December, 1993. There

is substance in the plea of counsel for the respondents and after taking into

account the period of time elapsed from the date of the award and the current

rate of interest, and in accordance with the recent judgments of the SC in

Rajendra Construction Co. v. Maharashtra Housing & Area Development

Authority and others, 2005 (6) SCC 678, McDermott International Inc. v.

Burn Standard Co. Ltd. and others, 2006 (11) SCC 181, Rajasthan State Road

Transport Corporation v. Indag Rubber Ltd., (2006) 7 SCC 700 & Krishna

Bhagya Jala Nigam Ltd. v. G.Harischandra, 2007 (2) SCC 720, the interest of

justice would be sufficiently met if the award is sustained, but, interest granted

by the Award is reduced to 12% per annum and further in case the respondents

makes the payment within four weeks from today then the interest would be at

stand reduced to 9% per annum .

Dasti.


                                                    MUKUL MUDGAL,J



                                                    VALMIKI J. MEHTA, J
APRIL 22, 2009
mm




FAO (OS) 261/2001                                                           Page 5
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter