Citation : 2009 Latest Caselaw 1562 Del
Judgement Date : 21 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS)349/2003
April 21, 2009
M/s Chander Kant & Co. ..... Appellant
Through : Mr. R.Rajappan, Advocate
versus
Delhi Development Authority ..... Respondent
Through : Ms. Sangeeta Chandra, Advocate
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE VALMIKI J. MEHTA
1. Whether the Reporters of local papers may be allowed
to see the judgment? No.
2. To be referred to the Reporter or not? No.
3. Whether the judgment should be reported in the Digest? No.
J U D G M E N T(ORAL)
%
MUKUL MUDGAL, J.
1. This appeal challenges the judgment of learned Single Judge in
respect of two claims i.e., claim No.1 and claim No.24.
2. We take the issue of claim No.24 first. In so far as claim No.24 is
FAO(OS)349/2003 Page 1 concerned, it is not disputed that Clause No.10C requires not only increase
of statutory wages but also proof of payments thereof. In the present case,
the proof of payments to the workmen concerned had not been produced by
the appellant/claimant, and, accordingly, there is no documentary proof in so
far as claim no.24. Therefore, finding on claim No.24 was rightly set aside
by the learned Single Judge.
3. In so far as claim No.1 is concerned, the finding of arbitrator is as
under:
"The details of claim are as follows:
-Bricks - 199000 No. Rs. 400 per thousand 79600
-M.S. sq. bars-12 MT Rs. 5000 per mt. 60000
-Brick tiles- 90000 Rs. 400 per thous. 36000 175600 Respondents have submitted photo copies of departmental registers for issue of materials.
Curiously in many places contractors signatures are not there even though required. There are no records produced by respondent of receipt of materials by claimant. Whenever any material is issued by respondent to claimant an unstamped Receipt is to be invariably taken (USR). Such USRs are not there. If USRs were not signed any prudent person will not issue further materials. No cogent
FAO(OS)349/2003 Page 2 reason has been put forward by respondent for continued issue of material without USR. The only record produced is MAS account which is respondents departmental record and there also there is no receipt on these items from claimant, even though for some other items such receipt is there. Therefore, I do not consider as valid that materials were continued to be issued even though claimants had not signed USR. The acceptance signature on a bill is to get payment and I do not consider that as a valid receipt for the materials as contended by respondent".
4. Significantly, the arbitrator is an expert in the field being a retired
Director General of Works, CPWD. Learned Single Judge has set aside the
above finding on claim No.1 by relying on running bill R-27. In our view,
the learned Single Judge has upset a finding of the fact recorded by an
Arbitrator which fell in his province as it is the Arbitrator who is the fact
finding authority. The arbitrator records that for the materials for which
adjustment sought by the DDA, there were no receipts (USRs) available as
signed by the appellant/contractor. Learned Single Judge had not dealt with
this finding of the arbitrator. There was no receipt available in the file and
FAO(OS)349/2003 Page 3 nor was the Registers for issue of the materials by the DDA signed at many
places by the contractor and in spite of these factors, the learned Single
Judge has merely placed only reliance on R-27 which shows that certain
deductions had been made by DDA. In our view a finding of fact recorded
by the arbitrator ought not to have been reversed by the learned Single Judge
as the arbitrator is entitled to arrive at a finding of fact and unless it is
wholly perverse in that such a finding of fact could never have been arrived
at a court hearing objections against an award ought not to set aside such a
finding of fact when two views were possible and an arbitrator had taken one
plausible view.
5. We partly allow the appeal and sustain claim no.1 preferred by the
appellant and dismiss the appellant's plea in respect of disallowance of claim
no.24. We feel that the interest of justice will be met if this claim is allowed
without grant of any interest.
6. We however hold that the appellant is entitled to interest at the rate of
9% per annum instead of 12% stated in the award in terms of the recent
trend of judicial opinion in Rajendra Construction Co. Vs. Maharashtra
Housing & Area Development Authority and others, 2005 (6) SCC 678,
McDermott International Inc.Vs. Burn Standard Co. Ltd. and others, 2006
FAO(OS)349/2003 Page 4 (11) SCC 181 & Rajasthan State Road Transport Corporation v. Indag
Rubber Ltd., (2006) 7 SCC 700 & Krishna Bhagya Jala Nigam Ltd. Vs.
G.Harischandra, 2007 (2) SCC 720.
The appeal stands disposed of accordingly.
MUKUL MUDGAL,J
VALMIKI J. MEHTA, J
APRIL 21, 2009
ib
FAO(OS)349/2003 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!