Citation : 2009 Latest Caselaw 1448 Del
Judgement Date : 17 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.207/2001
Reserved on : April 15, 2009
Pronounced on: April 17, 2009
DELHI DEVELOPMENT AUTHORITY ... Appellant
Through : None.
.
versus
M/s ANANT RAJ AGENCIES ..... Respondent
Through : None
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE VALMIKI J. MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment? No
2. To be referred to the Reporter or not? No
3. Whether the judgment should be reported in the Digest? No
% JUDGMENT
VALMIKI J.MEHTA,J.
1. The appeal has been filed by the appellant/DDA under Section 39 of the
Arbitration Act, 1940 against the judgment dated 14.3.2001 of the learned Single Judge
whereby the learned Single Judge has made the award rule of the court and dismissed the
objections of the appellant except certain modifications, which are not material for the
purposes of the present appeal.
2. The appellant in the grounds of appeal has confined its challenge only to the
FAO (OS) No.207/2001 Page 1 claims No.2 and 10 which pertain respectively to damages on account of execution of
work beyond the stipulated date of completion and expenditure incurred in maintaining
the watch and ward staff.
3. None has appeared on behalf of the appellant to press the appeal.
4. We have, therefore, gone through the records and would dismiss the appeal for
the reasons stated below.
5. The claim No.2 which pertained to claim of damages on account of execution of
work beyond the stipulated date of completion has been considered by the learned Single
Judge by specifically mentioning the six factors on behalf of the DDA which led to the
delay in completion of the work. The contention of the appellant/objector before the
learned Single Judge was that with respect to two of the six factors which the arbitrator
has held being the reasons responsible for delay in completion of the work, were such
factors for which under the contract no compensation could have been ordered. The
learned Single Judge, in our opinion has rightly found that the other four facts were in
themselves enough to support the decision of the Arbitrator with respect to his finding as
regards the delay in completion of the contract.
6. The challenge to an award is limited, being under Section 30 of the Arbitration
Act, 1940, with regard to mis-conduct of the Arbitrator or mis-conduct of the
proceedings. Sitting in appeal over a judgment of the learned Single Judge affirming the
award, the jurisdiction will be even still further circumscribed in that the error in the
judgment under challenge must be such that the finding is wholly illegal or perverse
which calls for interference by this court in appeal. We do not so find and accordingly,
FAO (OS) No.207/2001 Page 2 the challenge of the appellant seeking to upset the finding of the learned Single Judge
with regard to claim No.2 thus cannot be sustained.
7. As regards the challenge to the finding of claim No.10 which pertains to
expenditure incurred by the contractor/respondent in maintaining the watch and ward
staff, the learned Single Judge has duly noted the finding of the arbitrator that though the
work was completed on 15.4.1985, the respondent was required to keep the watch and
ward staff even after the date of completion up to 15.10.1987. Surely it was not a duty of
the contractor to keep the watch and ward staff after the completion of work and thus the
contractor was therefore entitled to recompense. The learned Single Judge has in fact as
corrected the error pointed out by counsel for the parties and reduced the claim under this
head from Rs.2,45,500/- to Rs.2,23,500/-. The arbitrator is the master of facts and the
courts would not interfere in the finding so arrived at unless the finding is shown to be
wholly illegal/perverse or beyond the terms of the contract. As stated above, none has
appeared on behalf of the appellant and we do not find any fault in the reasoning adopted
by the learned Single Judge. It may be noted that the appellant has released the amount
to the respondent and as per the statement of the counsel recorded on 1.11.2001.
8. In view of the above the appeal is dismissed, but without any order as to costs.
VALMIKI J. MEHTA, J
MUKUL MUDGAL, J
April 17, 2009
ib
FAO (OS) No.207/2001 Page 3
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!