Citation : 2009 Latest Caselaw 1428 Del
Judgement Date : 16 April, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.S.(OS) 859A/1998 with OMP No. 84/1998
Date of Decision: 16st April, 2009
METALLURIGICAL ENGINEERING CONSULTANTS ... Petitioner
Through: Mr. Deba Prasad Mukherjee with
Mrs. Nandini Mukherjee Sen,
Advocate.
versus
SCIL ..... Respondent
Through: NEMO.
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may No
be allowed to see the judgment?
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
% JUDGMENT (Oral)
VIPIN SANGHI, J.
1. The petitioner M/s. Metallurgical & Engineering Consultants
(India) Ltd. (MECON) has filed the aforesaid petition under Section 30
of the Arbitration Act 1940 to impugn the majority award dated
19.11.1996 and the order dated 09.12.1997 modifying the said award
made by the Arbitrators.
2. The petitioner was awarded the contract to install 7 Meter Tall
Coke Oven Batteries Nos.1, 2 & 3 and associated Coke Dry Cooling
Plants Nos.1, 2 & 3 by Rashtriya Ispat Nigam Limited at their
Vishakapatnam Steel Project at Visakhapatnam. The petitioner, in
turn, appointed the respondent M/s. SCIL India Ltd. as the sub
contractor and placed an order on them for execution of the work of
erection, testing start up, commissioning and post-commissioning
services of the 7 Meter Tall Coke Oven Batteries No.1 & 2 and
associated Coke Dry Cooling Plants 1 & 2 of the Visakhapatnam Steel
Project for a total estimated price of Rs. 8,03,76,680/- by a letter of
Intent No. 11.83.0526 dated 6.10.1982. This was followed by a formal
agreement being executed between the parties on 10.11.1983
containing the detailed terms and conditions for execution of the
aforesaid works. Disputes arose between the parties on account of
delay in the execution of the works. Since there was an arbitration
agreement contained in the agreement dated 10.11.1983, disputes
between the parties herein were referred to arbitration in accordance
with the rules of the Indian Council of Arbitration. The arbitration panel
consisted of Mr. Justice R.S. Pathak (retd. Chief Justice of India), who
acted as the Chairman, Mr. Justice H.L. Anand (retd. Judge, Delhi High
Court) and Mr. Justice S.N. Sapra (retd. Judge Delhi High Court). The
petitioner was the claimant before the arbitrators. Petitioner made a
claim of Rs.9,52,61,788/- against the respondent. The respondent SCIL
repudiated the petitioners claim and made a counter claim of Rs.
68,22,43,745.67/-. Mr. Justice H.L. Anand (Retd.) made a detailed
reasoned award dated 04.10.1996. On the other hand, Mr. Justice S.N.
Sapra (Retd.) made his award dated 30.09.1996 after having the
benefit of perusing the award made by Mr. Justice H.L. Anand (Retd.).
While substantially agreeing with the award made by Mr. Justice Anand
(Retd.) on his findings on issue nos.1 to 10, 12 to 15, 17 to 23, 24 to 34
and 36 to 41 subject to his findings, he expressed his disagreement
with the award made by Mr. Justice Anand (Retd.) on a few issues. The
Chairman Mr. Justice R.S. Pathak (Retd.) after perusing the two awards
made by Mr. Justice H.L. Anand (Retd.) and Mr. Justice S.N. Sapra
(Retd.) and after giving his due consideration concurred with the award
made by Mr. Justice H.L. Anand (Retd.). Consequently, the majority
award as made by Mr. Justice H.L. Anand (Retd.) and concurred by Mr.
Justice R.S. Pathak (Retd.) holds the field. On the applications of both
the parties for modification of the majority award, the same was
corrected on 09.12.1997. Mr. Justice S.N. Sapra (Retd.) agreed with
these corrections.
3. The learned arbitrators by the majority award, as corrected,
held the respondent SCIL accountable for the excess amount of
Rs.9.13 lacs paid to them, since it was held that they had directly or
indirectly received a total sum of Rs.1194.78 lacs as against the total
value of work of phase I of Rs.1185.65 lacs. The majority award also
granted damages to the claimant to the tune of Rs.1,59,27,000/-
thereby rendering the respondent liable to the petitioner claimant in
the sum of Rs.1,68,40,000/-. The respondent‟s counter claims were
allowed to the tune of Rs.56,96,231/- under item nos.1 and 2; to the
extent of Rs.8,27,600/- under item nos.11 and 12 and to the extent of
Rs.52,16,604.94 in respect of items under item „B‟ relating to
miscellaneous claims. The total amount of counter claims allowed by
the majority award, therefore, comes to Rs.1,17,40,435.94. The
liability of the respondent to the claim, therefore, stood reduced to
Rs.50,99,564.06 to which the claimant was held entitled. As against
this, the claimant had received a sum of Rs.2,53,97,261/- by
encashment of bank guarantee. Consequently, the majority award, as
corrected, directed refund of the excess amount received by the
petitioner of Rs.2,02,97,696.94. It was directed that if the amount is
refunded within one month no interest would be payable. However, in
case the same is not so paid, the respondent was entitled to interest
on the outstanding amount @ 18% p.a. from the date of expiry of one
month from the date of the award i.e. 09.12.1997 until payment.
4. Mr. Mukherjee, learned counsel for the petitioner has sought
to raise a challenge to the majority award on four counts only. His first
submission is that the award made by the learned arbitrators was not
made in a single and common sitting. He submits that the arbitrators
should have applied their minds at the same time in consultation with
each other and then made the award. He submits that it was
necessary and essential for the learned arbitrators to have made and
signed the award at the same time on the same day for it to be a valid
award. However, from a perusal of the award it is evident that Mr.
Justice H.L. Anand (Retd.) prepared his award which was sent to Mr.
Justice S.N. Sapra (Retd.). Mr. S.N. Sapra (Retd.) after perusing the
same made his own award dated 30.09.1996. It appears that
thereafter Mr. Justice H.L. Anand (Retd.) prepared the formal award
dated 04.10.1986 and both these awards were forwarded to the
Chairman Mr. Justice R.S. Pathak (Retd.) who thereafter made his
award expressing his agreement with the award made by Mr. Justice
H.L. Anand (Retd.).
5. The second submission of Mr. Mukherjee is that one of the
issues raised before the arbitral tribunal was with regard to the legality
of the invocation of bank guarantee nos. BG375 and BG417 dated
6.6.85 and 17.7.87 by the claimant. The respondent had disputed the
said invocation as being illegal and wrongful. Mr. Mukherjee submits
that this issue was not gone into by the tribunal as is evident from the
majority award. He submits that since the said issue was not gone into
by the learned arbitrators, the amount recovered under the said bank
guarantees could not be accounted for while making the award.
6. The third submission of Mr. Mukherjee is that the learned
arbitrators while deciding issue no. 23 had wrongly computed the
amount in para 173 of the majority award. As per para 173 of the
majority award, the arbitrators had computed the total value of work of
phase 1 at Rs. 1185.65 lacs and the amount received by the
respondent as Rs.1194.78 lacs. In the objections filed before this
court, the petitioner has computed the excess payment made at Rs.
2,07,4,398.00/-.
7. The last submission of Mr. Mukherjee is that the learned
arbitrators were not justified in denying the claim for interest made by
the claimant. He submits that the claim for interest has primarily been
declined by taking into account the fact that the respondent had been
declared as a sick industry and its case has been referred to the BIFR.
He submits that the sickness of the respondent was not a relevant
consideration that could have been considered by the arbitrators to
deny the claim of interest to the petitioner the transaction being a
purely commercial one. The claimant, according to Mr. Mukherjee, was
entitled to grant of interest on the amount due and payable by the
respondent. No other submission has been made by Mr. Mukherjee.
8. Having heard learned counsel for the petitioner and having
perused the record including the majority award as corrected, I find no
merit in the objections preferred by the petitioner and, in my view, the
same deserves to be dismissed.
9. So far as the objection of Mr. Mukherjee to the manner in
which the award has been made is concerned, I find no merit in the
same. A perusal of the award shows that the same has been signed by
the three arbitrators. The award is engrossed on stamp papers and
bears the date 19th November, 1996 which is the date of the award.
The award recites that after considering the pleadings and having
heard oral evidence and submissions of the parties at length, the
arbitrators give their award by majority of two to one with reasons
pronounced by each arbitrator in Annexure (A) by Mr. Justice R.S.
Pathak (Retd.) (B) by Mr. Justice H.L. Anand (Retd.) (C) by Mr. Justice
S.N. Sapra (Retd.).
10. When an arbitral tribunal consists of more than one arbitrator,
and each of the arbitrators decided to write their own opinions, it is but
natural that the respective opinions would be written individually and
once an opinion has been written by one of the arbitrators, it would be
circulated to the others. It is only after circulation of the respective
opinions that the final award emerges either as a unanimous award or
as a majority award. That is exactly what has transpired in the present
case. As noticed above, it is clear that Mr. Justice H.L. Anand (Retd.)
firstly prepared his opinion which was circulated to Mr. Justice S.N.
Sapra (Retd.). Mr. Justice S.N. Sapra (Retd.), on perusing the said
opinion preferred to write his own opinion partially disagreeing with the
findings of Mr. Justice H.L. Anand (Retd.). Mr. Justice S.N. Sapra (Retd.)
wrote his opinion on 30.11.1996 thereafter the opinions of Mr. Justice
H.L. Anand (Retd.) which was dated 04.10.1996, and the opinion of Mr.
Justice S.N. Sapra (Retd.) dated 30.09.1996 were circulated to Mr.
Justice R.S. Pathak (Retd.), the Chairman of the tribunal who concurred
with the award made by Mr. Justice H.L. Anand (Retd.). Thereafter the
learned arbitrators have made their formal award dated 19.11.1996
which has been duly signed by each one of them. The formal award by
majority accepts the view penned down by Mr. Justice H.L. Anand
(Retd.). It is evident that there was consultation and exchange of
views between the learned arbitrators. There is no infirmity in the
mechanism adopted by the learned arbitrators while making the
majority award and Mr. Mukherjee has not been able to point out as to
how the procedure adopted by the learned arbitrators is fallacious.
This objection is, therefore, rejected.
11. Before I deal with the next objection, I may note that it is well
settled that the arbitrators are the final arbiter of all factual disputes
between the parties. It is not for this court to re-appreciate the facts
and to re-compute for itself the amounts as are claimed by one or the
other party. The arbitrators have looked into the facts and figures
relied upon by the parties and thereafter arrived on their own
calculations. The Court cannot re-examine the correctness of the
conclusions arrived at by the arbitrator. The jurisdiction of the Court while
hearing objections to the award is not appellate in nature, and the award
passed by an arbitrator cannot be set aside on the ground that it is
erroneous. It is not open to the Court to interfere with the award merely
because in the opinion of the Court another view is equally possible. It is only
when the Court is satisfied that the arbitrator has mis-conducted himself or
the proceedings, or that the award has been improperly procured or is
otherwise invalid that the Court may set aside an award. Wrong or right, the
decision is binding if it is reached fairly after giving adequate opportunity to
the parties to place their grievance in the manner provided by the arbitration
agreement [see Bhagwati Oxygen Limited v. Hindustan Copper Limited
(2005) 6 SCC 462].
12. The challenge raised to the computation of the amount due
and payable to the petitioner claimant under Claim No. 23, in my view,
is not sustainable. No error on the face of the award is discernible and
none has been pointed out by the learned counsel for the petitioner while
contending that the learned arbitrators in their majority award have wrongly
computed the excess payment due to the petitioner. It is not even the
petitioner‟s case that the learned arbitrators have travelled beyond the
contract or that they have acted in excess of their jurisdiction. Paragraph
173 of the majority award reads as follows:
"173. I would, therefore, accept the computation of the Claimant that, as against the total value of work of Phase I at Rs.
1185.65 lacs, respondent had received a sum of Rs. 1194.78 lacs as at the close of the contract. Issue No. 23 is decided accordingly."
13. The aforesaid shows that the majority award in fact accepted
the computation of the claimant petitioner. It, therefore, does not lie in
the mouth of the petitioner to contend before this court that excess
payment to the tune of Rs. 2,07,04,398/- had been made by the
petitioner to the respondent. On what basis the aforesaid claim was
made by the petitioner has not been shown to me. The aforesaid
objection raised by the petitioner is, therefore, rejected.
14. I also find no merit in the submission of Mr. Mukherjee that
because the arbitrators did not go into the issue of legality of
invocation of the bank guarantees, adjustment of the amount received
by encashment of the said guarantees could not have been made in
the award. The issue with regard to the legality or otherwise of the
invocation of bank guarantee was an issue which was raised at the
instance of the respondent since it is the respondent who was
aggrieved by the said invocation. The learned arbitrators initially did
not go into the said issue as it was pending before the Supreme Court
at the relevant time. Later on, while dealing with the applications filed
by the parties they have noticed the fact that the S.L.P. filed by the
respondent questioning the legality of the invocation of the Bank
Guarantees has been dismissed. Therefore, the learned arbitrators
have proceeded on the basis that the invocation of the Bank
Guarantees was legal when made. However, that does not mean that
the arbitrators could not have taken into account the fact that the
claimant petitioner had already pocketed the aforesaid amount upon
invocation of the said bank guarantee. The learned arbitrators in view
of the aforesaid development, in the correction order held as follows:
"The position, as at present, therefore, is that as against its entitlement of Rs. 50,99,564.06, Claimant has received a sum of Rs. 2,53,97,261.00, being in excess of the amount to which it was entitled by Rs. 2,02,97,696.94. The Claimant would refund the aforesaid excess amount to the Respondent, within one month without interest. In case the payment is delayed Respondent would be entitled to interest, on the outstanding amount at 18% per annum, from the date of the expiry of one month from the date of the Award, until payment".
15. I also find no merit in the submission of Mr. Mukherjee that
the arbitrators erred in denying the interest to the petitioner on the
amount of Rs.9.13 Lakhs awarded on issue No.23. The arbitrators
have given two reasons, and not one, for denying the claim of interest
in favour of the petitioner. Firstly, the arbitrators have noted that
under the contract there is no express provision with regard to grant of
interest. Consequently, there is no contractual obligation towards the
payment of interest on outstanding amounts. Secondly, the
arbitrators have also taken into consideration the poor financial
condition of the respondent SCIL and the fact that it was a sick
company whose case was proceeding before the BIFR. Mr. Mukherjee
submits that the petitioner claimant was entitled to interest by virtue
of Interest Act 1978. He submits that "Court" includes a tribunal and
an arbitrator. He further submits that in any proceeding for recovery
of damages, or in any other proceedings in which the claim of interest
or damages already paid is made, the court may, if it thinks fit, allow
the interest to the person entitled to damage or to the person making
such claim.
16. A perusal of Section 3 of the Interest Act 1978 shows that the
same is an enabling provision. However, it does not mandate that in
every case it is incumbent either for the court or for the arbitrator or
the tribunal to grant interest. It is for the court to consider the facts
and circumstances of each case and thereupon exercise its discretion
judiciously to grant or deny the claim for interest. Since the arbitrators
have, after considering the respective claims and counter claims of the
parties exercised their discretion to deny interest to the claimant, in
my view, it is not for this court while hearing these objections to the
award to interfere with the award and grant interest to the petitioner.
It cannot be said that the factum of the respondent being a sick
company was not a relevant consideration. I may also note that the
amount found by the arbitrators to be due to the petitioner on account
of excess payment, upon the taking of accounts, was to the extent of
Rs. 9.13 lacs only which was a small fraction as compared to the total
value of the contract. This figure was arrived at by the arbitrators
upon adjudication. Prior to that the actual amount due was not even
known to either of the parties. In fact, the respondent had substantial
counter claims as is evident from the fact that their counter claim to
the extent of Rs.1.17 Crores were allowed by the arbitrators. It was,
therefore, not a case where the respondent had withheld a payment of
an amount which it was aware of as being its liability. Moreover, the
arbitrators did not even grant interest to the respondent on the excess
amount recovered by the petitioner by invoking the Bank Guarantees
from the time the petitioner received the said amount till one month
after the date of the award. In my view, these are germane reasons
why the petitioners claim towards interest could not have been
sustained.
17. For all the aforesaid reasons, I see no merit in this petition
and the same stands dismissed. The majority award made by the
learned arbitrators is made rule of the court. In case the petitioner has
not refunded the amount of Rs.2,02,97,696.94 within the period of one
month from the date of the correction order dated 09.10.1997, the
petitioner shall be liable to bear interest on the said amount @ 18%
p.a. from 09.01.1998 upto date, and further interest on the said
amount of Rs.2,02,97,696.94 @ 9% p.a. from today till payment or
realization, as the case may be.
VIPIN SANGHI, J.
APRIL 16, 2009 dp/rsk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!