Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India & Ors. vs M/S. Adwave
2009 Latest Caselaw 1391 Del

Citation : 2009 Latest Caselaw 1391 Del
Judgement Date : 15 April, 2009

Delhi High Court
Union Of India & Ors. vs M/S. Adwave on 15 April, 2009
Author: Sanjay Kishan Kaul
*            IN THE HIGH COURT OF DELHI AT NEW DELHI


                                                       Reserved on: 12.03.2009
%                                                 Date of decision: 15.04.2009


+                                RFA (OS) No.5 of 1993


UNION OF INDIA & ORS.                                  ...APPELLANTS
                                 Through:    Ms. Avnish Ahlawat, Ms. Latika
                                             Chaudhary   &    Mr.  Saurabh
                                             Chadda, Advocates.


                                         Versus


M/S. ADWAVE                                             ...RESPONDENT
                                 Through:    Mr. R.K. Watel, Advocate.



CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MR. JUSTICE SUDERSHAN KUMAR MISRA

1.        Whether the Reporters of local papers
          may be allowed to see the judgment?                  No

2.        To be referred to Reporter or not?                   No

3.        Whether the judgment should be
          reported in the Digest?                              No


SANJAY KISHAN KAUL, J.

1. The plaintiff (i.e., respondent herein) filed a suit on the

Original Side of this Court for recovery of Rs.1,33,089/- with

pendent lite interest @ 18% per annum and future interest

on the decretal amount @ 18% per annum till realization,

with costs. In terms of the impugned order dated

08.12.1992, the suit has been decreed in favour of the

plaintiff for a sum of Rs.63,700/- with proportionate costs

and interest @ 12% per annum from date of the suit till

realization.

2. The case of the plaintiff as averred in the plaint is as under.

3. The plaintiff in the suit is a registered partnership firm

carrying on the business of construction of buildings and

publicity agents. Ms. Komal G.B. Singh is one of the

partners and Managing Partner of the plaintiff firm, who

was competent and authorized to file the suit and sign and

verify the pleadings.

4. The plaintiff was entrusted the work of construction of the

Delhi Police Pavilion at Pragati Maidan, New Delhi with a

stipulation that the work was to be completed by

13.11.1981. There were 3 works regarding which offer was

given by the plaintiff on 30th and 31st October, 1981. One of

the works was in respect of labour and raw materials etc.

for which the estimate of Rs.75,000/- was given, which was

reduced after negotiations with the concerned authorities

to Rs.70,700/-. The second estimate was for a sum of

Rs.73,000/- for creative work and this amount was reduced

after negotiations to Rs.63,000/-. The third estimate was

for production of A.V. and hire equipment for the Delhi

Police Pavilion at the India International Trade Fair, 1981 for

a sum of Rs.48,300/-, which was reduced after negotiations

to Rs.41,300/-. The plaintiff had also stipulated in respect

of all the three works that 50% payment would be made

immediately, 25% of the balance on 10.11.1981 and the

balance on 14.11.1981.

5. The work was started by the plaintiff after negotiations,

though letter dated 12.11.1981 (Ex. P-1) was issued by the

Commissioner of Police, Delhi under the signatures of

Deputy Commissioner of Police, Headquarters- I, Delhi to

the effect that the job was allotted to the plaintiff in terms

of the estimates, revised by the plaintiff. It was further

provided in the letter that the work should be executed in

accordance with the specifications and designs and the

work was to be completed by 13.11.1981.

6. It was further claimed by the plaintiff that besides the work

mentioned in the said three estimates, the plaintiff was

required to carry out additional work of the value of

Rs.28,089/- as per the details mentioned in para 3 (wrongly

shown as para 4) of the plaint. The plaintiff pleaded that

the work was completed as per the agreement by due date

for the exhibition and a sum of Rs.50,000/- was received by

the plaintiff on 06.11.1981 and another sum of Rs.20,000/-

on 09.11.1981. It was also pleaded that the balance

amount of Rs.1,05,000/- was due to the plaintiff on

14.11.1981, which had not been paid out of the agreed

contract and another sum of Rs.28,089/- for the additional

work. It was also claimed that notice under Section 80 of

the Civil Procedure Code, 1908 was issued to the

defendants making a demand of the amount of

Rs.1,33,089/-.

7. The defendants (i.e., appellants herein) contested the suit

by filing a written statement. A preliminary objection was

raised for want of knowledge that the plaintiff was a

partnership firm and Ms. Komal G.B. Singh was competent

to sign and verify the suit. However, it was admitted that

the work with regard to the Police Pavilion at the India

International Trade Fair, 1981 was awarded to the plaintiff

and that the fair was to commence from 14.11.1981 till

04.12.1981. It has also been admitted that after inviting

tenders, negotiations took place with the plaintiff and work

for the total sum of Rs.1,75,000/- was awarded to the

plaintiff. It was claimed that to facilitate the start of the

work immediately by the plaintiff, a sum of Rs.50,000/- was

paid on 06.11.1981 and another sum of Rs.20,000/- was

paid on 09.11.1981. It was also claimed that instead of

completing the work, it was left in between on 12.11.1981.

It was further averred that on account of the work being left

incomplete by the plaintiff, the inauguration of the Police

Pavilion had to be postponed to 16.11.1981 and the work

was got completed with great difficulty from another firm

viz. M/s. Architects Forum. It was pleaded that that no

additional work was either assigned or carried out by the

plaintiff. It is, in these circumstances, that the claim of the

defendants that nothing was due to the plaintiff and so a

prayer was made that the suit may be dismissed.

8. On the basis of the pleadings, the following issues were

framed on 06.02.1986 :

1. Whether the plaintiff is a registered partnership firm and Ms. Komal G.B. Singh is a registered partner competent to file the present suit? OPP.

2. Whether the plaintiff executed the total work of construction of Delhi Police Pavilion? It if, what was the extent of the work not completed? OP Parties.

3. Whether the defendant asked the plaintiff to execute additional work referred to in para 3 of the plaint? OPP.

4. If issue No.3 is held in favour of the plaintiff, to what amount is the plaintiff entitled for the additional work? OPP.

5. To what amount is the plaintiff entitled? OPP.

6. Whether the plaintiff is entitled to any interest, if so at what rate? OPP.

7. Relief.

9. In support of its case, the plaintiff examined Shri Rajeev

Mehrotra as PW-1, Ms. Komal G.B. Singh, partner of the

plaintiff firm as PW-2 and Mr. Siddharth Basu as PW-3. The

defendants in support of their case examined Mr. Maxwell

Pereira as DW-1, who was at the relevant time Deputy

Commissioner Police, Delhi State Industrial Development

Corporation in 1981, Mr. M.B. Kaushal as DW-2, who was

Addl. Commissioner of Police (Admn.), Delhi Police in

August 1981 and Shri Ravinder Chaudhury, Sole Proprietor

of M/s. Architects Forum as DW-3.

10. The learned Single Judge has held Issue No. 1 in favour of

the plaintiff. It has been noted that the originals of Ex. PW-

2/1 (photocopy of the Certificate of Registration) and Ex.

PW-2/2 (photocopy of the certificate issued by the Registrar

of Firms) were brought by the witness (PW-2) when she was

examined. The learned Single Judge has also noted that

there was nothing on record to show that the plaintiff was

not a registered partnership firm.

11. The learned Single Judge has, after perusing the pleadings

and the evidence placed on record, held in respect of Issue

No. 2 that the plaintiff had completed the work in respect of

Item Nos. 1 & 2 in time, but the plaintiff could not claim any

amount in respect of Item No. 3. The learned Single Judge

has noted that Ms. Komal G.B. Singh had made a

categorical statement that the work of labour and raw

material as well as creative work had been completed on

12.11.1981 and that bills were sent to the defendants and

in spite of demand, the balance had not been paid. The

learned Single Judge has also taken note of the letter dated

21.11.1981 (Ex. P-14) which was sent by the plaintiff to the

Commissioner of the Police, receipt of which had been

admitted by the defendants. A perusal of this letter showed

that the plaintiff had claimed having completed 2 works

and a demand was made of the balance amount and bills

for a sum of Rs.35,700/- and Rs.28,000/- were sent

respectively along with the said letter. It has been taken

note of by the learned Single Judge that there has been no

reply to this letter. A categorical finding was recorded by

the learned Single Judge that the relevant record indicating

how much work had been done by Mr. Ravinder Chaudhury

for the plaintiff and how much work was done by Mr.

Ravinder Chaudhury at the instance of the Commissioner of

Police had not been produced and the defendants did not

take any steps to get the work carried out by the plaintiff

assessed before Mr. Ravinder Chaudhury was asked to

carry out further work. Even photographs of the work

carried out by the plaintiff had not been taken. The learned

Single Judge has also taken note of the letter dated

02.12.1981 (Ex. P-16), written by the plaintiff to the

Commissioner of Police, in which a prayer was made to

preserve the work carried out by the plaintiff till the

accounts were settled and the details of the work carried

out by the plaintiff were mentioned therein. No action was

taken on this letter. The learned Single Judge has held that

there was no cogent and/or reliable material produced by

the defendants to indicate that the work was not completed

and how much work was left incomplete and, thus, it was

held that the work in respect of Item Nos. 1& 2 was

completed. In respect of Item No. 3, the learned Single

Judge has noted that there was no detailed information

about the number of slides / tapes as also the fact that the

plaintiff had written a letter dated 02.12.1981 (Ex. P-16) not

claiming anything in respect of this work.

12. The learned Single Judge has dealt with Issue Nos. 3 & 4

together and the same have been decided against the

plaintiff. It has been observed by the learned Single Judge

that the plaintiff has not produced any evidence in proof of

having done additional work and hence the plaintiff has

been unable to prove the issue.

13. In regard to Issue No. 5, the learned Single Judge has held

that the plaintiff is entitled to the amount of Rs.63,700/-

being the balance amount payable in respect of Item Nos. 1

& 2.

14. In respect of Issue No. 6, the learned Single Judge has

granted interest @ 12% per annum taking note of the fact

that the transaction was a commercial one and that the

amount had not been paid by the defendants in spite of the

demand having been made by the plaintiff.

15. In respect of Issue No. 7, the suit of the plaintiff has been

decreed for a sum of Rs.63,700/- with proportionate costs

and interest @ 12% per annum from date of the suit till

realization.

16. The learned counsel for the appellant has sought to assail

the finding of the learned Single Judge in respect of Issue

No.2 and consequently the decree which has been passed

in favour of the respondent.

17. The learned counsel for the appellant submitted that there

was no evidence on record to show that the Pavilion was

made ready by the respondents on 13.11.1981 except the

bald statement of PW-2. It was further submitted that since

the learned Single Judge had disbelieved the statement of

the said witness on the aspect of additional work and AV,

her bald statement that the pavilion was completed on

13.11.1981 could not have been accepted. Reliance was

also placed on the cross-examination of PW-2 where it was

admitted that for part of the work Item No. 1 in Ex. P-1, M/s

Architect Forum was engaged by her. It was further

pleaded that PW-2 admitted that in her letter sent to the

police, she did not mention about the happenings of 13 th,

14th and 15th November, 1981.

18. The learned counsel for the appellant also submitted that

the work had to be done by the respondent as per Ex. P-1

and Ex. D-1, D-2 and D-3 were only estimates. A reference

in this regard is made to the cross-examination of PW-2 and

DW-3. It was further submitted that Ex. D-1, D-2, and D-3

were estimates and after negotiations, the contract was

finalized between the parties was Ex. P-1.

19. The learned counsel for the appellant also submitted that

the respondent was not returning some important

documents of the Police Department and that an FIR was

lodged and the documents were recovered and later on

legal advice, the matter was not pursued further.

20. The learned counsel for the appellant also placed reliance

on the evidence of Shri Maxwell Pereira (DW-1) where the

said witness in his cross-examination has given the details

about the estimate of the work done by the respondent and

why persons from other pavilions could not be called for as

everybody was hard pressed for time. Reliance was also

placed on the affidavit of Sh. M.B. Kaushal (DW-2), which

mentions the contract in question and the respondent

leaving the same in between.

21. The learned counsel for the respondent submitted that the

respondent had completed the entire work entrusted to it

and has filed various documents and also produced three

witnesses in support of the same. Reliance was placed

upon Ex. P-2, P-13, P-14, P-16 & P-17, which have been

proved by PW-2, being the Managing Partner of the

respondent firm. It was also submitted that the appellants,

despite having been intimated, did not come forward to

take possession of the pavilion. It was further submitted

that the whole controversy arose as the appellants wanted

the respondent to do some additional work without any

payment to which the respondent did not agree and to

further harass the respondent, a false FIR was filed which

was not pursued later on.

22. The learned counsel for the respondent also submitted that

the claim of the appellants that the work had not been

completed is without any supporting documents and is only

based on bald statements. A reference was made to the

cross-examination of DW-3, where the said witness on

being shown Ex. D-1, D-2 and D-3 admitted that the work

shown in the said documents / orders had nothing to do

with the job that was assigned to him by the Police

Department and that he did the job of display boxes for the

appellants which is not part of Ex. D-1, D-2, and D-3.

23. The learned counsel for the respondent also placed reliance

upon the fact the request of the respondent, which was

made to the appellants, that the work executed by the

respondent should be preserved, was not acceded to. A

reference in this regard is made to Ex. P-16 where the same

has been stated.

24. The learned counsel for the respondent also submitted that

it had claimed the amount for works executed in terms of

Ex. P-1 relating to three items and also for a fourth item,

i.e., additional work and that the learned Single Judge has

upheld the claim for the first two items and the claim for

the third item was disallowed as the respondent / plaintiff

had not furnished detailed information about the number of

slides / tapes of audio visual work as also the respondent

had written a letter dated 02.12.1981 (Ex.P-16). The claim

of additional work was also disallowed for want of evidence.

25. Lastly, it was submitted that the learned Single Judge had

exhaustively dealt with the documents and evidence

produced by the parties and that there no was no infirmity

with the impugned order and hence, the appeal should be

dismissed.

26. In our considered view, the submission of the learned

counsel for the appellants that there is no evidence on

record to show that the Pavilion was ready on 13.11.1981 is

without any merit. The learned Single Judge has correctly

taken note of the fact that the respondent had sent a letter

dated 21.11.1981 (Ex. P-14) to the Commissioner of Police,

claiming to have completed two works and a demand was

made of the balance amount. Bills for a sum of Rs.35,700/-

and Rs.28,000/- were also sent alongwith the said letter

after giving adjustment for the amount received in

advance. The appellants did not even reply to this letter.

The learned Single Judge has also taken note of the fact

that the respondent had sent a letter dated 2.12.1981 (Ex.

P-16) to the Commissioner of Police, in which a request was

made to preserve the work carried out by the respondent

till the accounts were settled and details of work carried out

by the respondent were mentioned/recorded. Another

letter dated 17.12.1981 (Ex. P-17) was sent by the

respondent to the Commissioner of Police, asking for

payment of the balance amount but to no avail. The

learned Single Judge has also taken note of the cross-

examination of Mr. Ravinder Chaudhury (DW-3), where a

suggestion was put to him that he was to be paid a sum of

Rs.50,000/- for carrying out the work envisaged in Item No.

1 and part of the work envisaged in Item No. 2 of Ex. P-1 to

which the answer was that he did not remember correctly.

In view of the above facts, it can hardly be said that there

was no evidence on record to prove that the respondent

had completed the work on 13.11.1981.

27. It is the admitted position that Ex. D-1, D-2 and D-3 were

only estimates. It has been correctly observed by the

learned Single Judge that Ex. P-1 is an approval of the three

estimates given by the respondent to the appellants. In Ex

P-1, it has been stated that the work should be executed in

accordance with the specifications and designs laid down in

the quotations and also given by the Committee. Hence,

the said letter (Ex. P-1) itself makes it clear that the work

had to be done as per the quotations.

28. In so far as the submission of the learned counsel for the

appellants that an FIR had been lodged and later on legal

advice, the matter was not pursued further, the learned

Single Judge had correctly noted that even a copy of the

challan had not been filed in Court. Since neither any

evidence has been produced in this respect more

particularly when the said matter was not pursued further

nor any categorical finding has been recorded by the

learned Single Judge, the same is liable to be ignored.

29. The learned counsel for the appellants placed reliance on

the evidence of Sh. Maxwell Pereira (DW-1) and Sh. M.B.

Kaushal (DW-2) to contend that the respondent did not

complete the work as per the contract and why persons

from other pavilions could not be called. In our considered

view, the appellants have not produced any evidence other

than mere statements of their witnesses to contend that

the work had not been completed on 13.11.1981. No

evidence has been brought on record to show the amount

of work which had been carried out by Mr. Ravinder

Chaudhury (DW-3) for the respondent and at the instance

of the Commissioner of Police. The appellants did not even

care to take photographs of the work carried out by the

respondent or to preserve the same even though the

respondent had sent a letter dated 2.12.1981 (Ex.P-16)

asking for the same.

30. In view of the aforesaid, we find no merit in the appeal and

the same is dismissed with costs of Rs.25,000/-.

SANJAY KISHAN KAUL, J.

APRIL 15, 2009                            SUDERSHAN KUMAR MISRA, J.
mk





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter