Citation : 2009 Latest Caselaw 1293 Del
Judgement Date : 9 April, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)385(A) of 1997
%09.04.2009 Date of decision: 09.04.2009
J K INDUSTRIES LTD. ....... Plaintiff
Through: Mr. Anil Nauria, Advocate
Versus
TEXMACO LIMITED ....... Defendants
Through: Sumit Sen, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may yes
be allowed to see the judgment?
2. To be referred to the reporter or not? yes
3. Whether the judgment should be reported
in the Digest? yes
RAJIV SAHAI ENDLAW, J.
1. Objections U/s. 30 & 33 of the Indian Arbitration Act, 1940 are
for consideration.
2. The disputes between the parties arose out of purchase order
dated 10th September, 1982 placed by the plaintiff J.K. Industries
Ltd. on the defendant M/s. Texmaco Ltd. for supply of Texmaco VU-
50 Type Coal fired Water Tube Boiler of 30,000 kgs per hour
continuous rating of steam at a working pressure of 300 PSIG at the
works of the plaintiff at Kankroli, Rajasthan. The value of the
contract was Rs.91.45 lakhs. The plaintiff paid Rs.111.14 lakhs
against the defendant‟s bills of Rs. 120.55 lakhs. The plaintiff
withheld payment of Rs.9.41 lakhs. The plaintiff also realized a sum
of Rs.4,57,230/- from the performance bank guarantee furnished by
the defendant in terms of the purchase order. It was the case of the
plaintiff that since the commissioning of the boiler in June 1984, the
plaintiff had been facing problems inter alia on account of
substandard workmanship faulty design and defective material. It
was further alleged that the boiler had failed to give the steam at the
rated capacity and on the account of breakdowns the boiler had to be
shut down several times. It was further contended that in spite of
various measures taken by the defendant on complaints by the
plaintiff, the boiler was never able to achieve the rated capacity.
3. In accordance with the arbitration clause in the purchase
order, the disputes and differences which had accrued between the
parties were referred to the Federation of the Indian Chambers of
Commerce and Industries (FICCI). FICCI in accordance with its
rules constituted an arbitral Tribunal of three arbitrators, one
arbitrator being nominated by each of the parties and the presiding
arbitrator being nominated by FICCI.
4. The plaintiff claimed from the defendant
(i) Rs.1,60,80,287/- towards extra coal consumption in the
boiler during the period January 1984 to December 1986
for the faulty design and substandard workmanship by
the defendant in the boiler.
(ii) Rs.15,38,000/- on account of losses suffered owing to the
frequent steam pressure drops from the boiler wherefor
tyres under process had to be scrapped.
(iii) Rs. 5,35,72,000/- on account of loss suffered in
production of tyre for steam shortage.
(iv) Rs.6,50,792/- on account of reduced life of boiler tubes,
elements, stoker main, drive shaft caused during the
three years prior to the inception of the arbitration
proceedings.
(v) Rs.9,32,000/- towards costs incurred in carrying out
works of modification/rectification of the boiler and
which works the defendant had failed to carry out and
which were stated to be necessary for making the boiler
workable. Originally a further sum of Rs.9 lacs was also
claimed under this head, towards further expenses to be
incurred on rectification/modification but the said claim
was subsequently not pressed.
(vi) Interest and costs of arbitration.
5. The defendant besides contesting the aforesaid claim also
made a counter claim before the Arbitral Tribunal against the
plaintiff for recovery of (i) Rs.10,42,942.29 on account of balance
amount due in respect of work executed under the contract (ii)
Rs.4,57,200/- illegally received by the plaintiff by encashment of
bank guarantee and (iii) for interests and costs.
6. The Arbitral Tribunal was unable to arrive at a consensus. The
presiding arbitrator and the arbitrator nominated by the plaintiff
rendered the majority award dated 21st September, 1996,
whereunder it was held
(i) That plaintiff was entitled to enforce the performance
bank guarantee and recover Rs. 4,57,230/- thereunder
from the defendant and the plaintiff was not liable to
refund this amount since the defendant was guilty of late
delivery of the boiler.
(ii) That the plaintiff is entitled to recover a sum of
Rs.9,32,000/- on account of expenditure incurred on the
rectification and modification of the boiler by replacing
the underthrow type by overthrow type manufactured by
Isgec John Thomson; the boiler supplied was defective.
(iii) That the plaintiff is not entitled to loss of profits because
the claim of the plaintiff was found to be for exceptional
loss and abnormal profits. However, the plaintiff was
held entitled to some general and perhaps conjectural
sum for loss of business reasonably to be expected, as
held by Asquith L.J. in Victoria Laundry case.
(iv) The defendant is not entitled to the claim in the sum of
Rs.10,42,942.29 on the ground that the boiler supplied
was defective and did not conform to the contract
specifications.
(v) In all the circumstances of the case a lumpsum award of
Rs.20 lakhs in favour of the plaintiff and against the
defendant inclusive of Rs.9,32,000/- and Rs.4,57,230/-
aforesaid was made. The defendant was thus held liable
to pay to the plaintiff Rs.20 lakhs in all in full and final
settlement of all the claims of the plaintiff in the
arbitration proceedings. Since this amount included
Rs.4,57,230/- realized by the plaintiff under the
performance bank guarantee, after deduction thereof, a
sum of Rs.15,42,770/- was directed to be paid by
defendant to plaintiff together with interest @18% p.a.
from the date of the award till the date of payment or
decree of the court whichever is earlier.
(vi) The parties were directed to bear their own costs of
arbitration.
7. The minority award dated 29th September, 1996 was rendered
by the nominee arbitrator of the defendant. Minority award
comprising of 9 pages, in the first over seven pages odd, the claim of
the plaintiff has been held to be barred by time, even though that
objection had admittedly not been taken by the defendant; thereafter
it proceeds to criticize the procedure in the arbitration proceedings
followed/adopted by the presiding arbitrator. Thereafter on last two
pages, in bullet points, it states that there was no breach of contract
on the part of the defendant; that it was the plaintiff which was not
ready with the coal feeding system when the boiler was installed
and it was the plaintiff which failed to feed the specified coal to the
boiler resulting in the same not meeting the agreed specified
specifications. It further held that the defendant gave every kind of
gratuitous help and cooperation to the plaintiff to sort out the
problems which was agreed by the plaintiff itself; that the plaintiff
had several other boilers which were supplying steam to its plant
and the plaintiff did not suffer any damage at all by reason of the
non-functioning of the boiler supplied by the defendant and which
non-functioning was entirely due to the plaintiff‟s default. It was
further held that the plaintiff having not suffered any loss, the
question of award of any damages did not arise. The minority award
also directed the plaintiff to refund Rs.4,57,230/- realized by the
plaintiff by encashment of the performance bank guarantee, together
with interest of 18 % per annum from 28th June, 1986.
8. The record shows that FICCI forwarded the majority as well as
the minority award together with the arbitral record to the Registrar
of this Court, having been authorized to do so under the majority
award. Upon receipt thereof in this Court, on 24th February, 1997,
notice of filing of the award was issued to the parties. The defendant
filed I.A. 3991/1998 U/s. 30 & 33 of the Act. The plaintiff has not
challenged the award. Upon completion of pleadings on 5th May,
1998, an issue was struck as to whether the award was liable to be
set aside on the objections of the defendant. Affidavit evidence has
been filed by the parties.
9. I may notice that I.A. 2297/1999 was preferred by the
defendant for summoning the arbitrator who had rendered the
minority award, before this Court. The said application was
dismissed on 10th March, 1999.
10. Before discussing the objections of the defendant, I.A.
7855/2008 filed by the defendant U/s. 141 of the CPC may be dealt
with. The defendant by the said application states that the questions
forming the subject matter of the arbitration primarily related to the
supply of the boiler at Kankroli, Rajasthan and the Courts at Delhi
had no nexus and /or connecting factors with the questions forming
the subject matter of the reference. Only the arbitration sittings
were held at New Delhi and which could not confer jurisdiction U/s.
2(c) of the 1940 Act. It is pleaded that the question of territorial
jurisdiction goes to the root of the matter and should be decided by
the Court before proceeding to hear the objections of the defendant
on merits. As recorded in the said application, at the time of filing
thereof, the matter was part heard before another Judge of this
Court. The record does not show any notice of the said application
having been issued. However, at the time of hearing of the
objections, the counsel for the defendant was permitted to argue the
aspect of territorial jurisdiction also.
11. It may be stated that in the objections as originally filed in
1997, no plea of this Court not having the territorial jurisdiction to
entertain the objections to the award or to entertain proceedings
U/s. 14 & 17 of the Act was taken. The said plea was taken after the
objections had remained pending for nearly 11 years. Not only the
said conduct but even otherwise I find the said plea of territorial
jurisdiction to be vexatious and malafide. A perusal of the purchase
order dated 10.09.1982 in the arbitral record shows that the same
was issued by the plaintiff from Delhi to the defendant at Calcutta.
The said purchase order in Clause 14 of Schedule B thereto provides
that all suits arising out of the order should be instituted in the Court
of competent jurisdiction situated in New Delhi and in no other
Court. The defendant vide its letter dated 21st September, 1982
accorded its acceptance to the purchase order. Though some
clarifications were also sought in the letter dated 13.10.1982, but no
clarification or controversy was raised with respect to the
jurisdiction clause aforesaid.
12. The record also reveals that the advocate for the defendant
also wrote a letter dated 04.11.1996 to FICCI enquiring as to
whether the award had been filed by FICCI in Delhi High Court, as
requested by the advocate for the plaintiff. At this stage also, it was
not said that the Delhi High Court had no territorial jurisdiction and
the award could not be filed there or ought to be filed in any other
Court. Such conduct of the defendant certainly estopps the
defendant from now objecting to the territorial jurisdiction of this
Court.
13. The counsel for the plaintiff has also contended that the
performance bond under the purchase order was to be negotiated
through bankers of the plaintiff in Delhi, payment were made by
plaintiff from Delhi, amendments were sought by the defendant from
the plaintiff at Delhi, discussions from time to time were held at
Delhi, the defendant also had a subordinate office at Delhi.
However, in my view, in the face of the clause aforesaid in the
purchase order restricting the jurisdiction to the Courts at Delhi,
attempt by the defendant at fag end of the proceedings to contest
the territorial jurisdiction of the Court ought to be deprecated.
14. Coming to the objections of the defendant to the majority
award, it was one of the contentions of the counsel for the plaintiff
that the arguments made by the counsel for the defendant during the
hearing were not pleaded. It is thus necessary to first record the
objections pleaded.
15. The bulk of the pleadings in the application U/s. 30 & 33 of the
Act are with respect to the procedure followed by the Presiding
Arbitrator and which in fact is a repetition of the minority award also
deprecating the procedure followed by the presiding arbitrator. It is
pleaded that the version in the minority award as to conduct of
proceedings ought to be accepted U/s. 114 of the Indian Evidence
Act. Besides it has been pleaded that the evidence of the witnesses
of the defendant has been ignored, that the minutes of the
inspections carried out jointly by the parties clearly establish that
the defendant had delineated the breach of contractual specifications
committed by the plaintiff; that the majority award has misconstrued
the letter dated 19.12.1983 of the defendant to the plaintiff; that if
all the evidence, material and records furnished by the defendant
had been considered, it would have been established that there was
no breach of contract on the part of the defendant and in fact the
plaintiff itself had failed to adhere to contractual specifications and
that the plaintiff had not suffered any damages at all by reason of
non-functioning of the boiler supplied by the defendant and which
non-functioning was entirely due to the plaintiff‟s fault.
16. From the aforesaid, it is clear that (A) the majority as well as
the minority award are in unison on at least the aspect that the
boiler did not perform as per the contracted specifications. This is
not disputed in the objections also.
(B) Neither the majority nor the minority award awarded the sum
of Rs. Rs.15,00,142/- claimed by the defendant. There is no
objection also with respect thereto.
(C) The minority award does not deal with that part of the majority
award where a sum of Rs.9,32,000/- has been awarded to the
plaintiff against the defendant for the expenditure incurred by the
plaintiff in carrying out modifications/ rectifications in the boiler.
There are no objections also in that respect. Thus the factum of
plaintiff having incurred the said expense is not in dispute.
17. The objections of the defendant to the majority award is (A) to
the manner of conduct of proceedings by the presiding arbitrator, (B)
to the award of approximately Rs. 15,42,770/- to the plaintiff against
the defendant upon finding in the majority award that the defendant
was in breach and out of which Rs.9,32,000/- is towards expenses
incurred by plaintiff in modification or rectification of the boiler and
the balance Rs.6,10,770/- is towards losses suffered by the plaintiff
on account of supply of defective boiler by the defendant and (C) to
the finding in the majority award of the performance bank guarantee
having been correctly encashed by the plaintiff.
18. The counsel for the defendant during the hearing has urged
that under the purchase order the liability of the defendant was
limited to only repair of the boiler and to the amount of the
performance bank guarantee; that the finding in the majority award
that the plaintiff was entitled to encash the performance bank
guarantee for delay by the defendant was incorrect because for the
reason of the delay the performance bank guarantee was to be
extended; U/s. 44 of the Contract Act, the defendant was entitled to
reasonable notice. It was further contended that as per the law in
Maulabux Vs. Union of India, 1970 SC 1955, the plaintiff can be
entitled to any damages only if had suffered a loss and the majority
award did not show any loss to have been suffered by the plaintiff
and the award of damages was conjectural. It was further contended
that the defendant had sent parts/accessories for repair/rectification
of the boiler and which had not been used by the plaintiff on the plea
of time being of the essence; no monetary compensation for any
defect in the boiler could be awarded as the loss of the defendant
was limited to replacement only. Even though no objection in this
regard has been pleaded as aforesaid but it was also argued that the
counter claim of the defendant had been summarily rejected without
any reason whatsoever. It was further contended that the majority
award merely states that the statements of witnesses and the
documents had been considered and it has not discussed or
assessed. The award of interest at 18 % per annum was also
contested though again there is no plea in that regard in the
objections filed. The counsel for the defendant in rejoinder
reiterated that cryptic discussion was not enough and the
contentions as to procedure followed by the presiding arbitrator in
the majority award had not been answered by the arbitrators
rendering the majority award. It was further contended that the
expert evidence of the defendant had not been considered. It was
thus the contention that the award was liable to be remitted for
reconsideration U/s. 16 of the 1940 Act.
19. The purpose of pleadings is to confine further proceedings i.e.
evidence and arguments within confines thereof. Ordinarily
arguments made at the time of the hearing and with respect whereto
no foundation in pleadings has been laid are to be rejected.
20. In the aforesaid conspectus in my view the objections can be
considered under the following heads :
(i) Misconduct if any in the matter of procedure by the presiding
arbitrator.
(ii) Award of damages of Rs.6,10,770/- on conjecture even
according to the majority award.
(iii) The legality / illegality of the encashment of the performance
bank guarantee.
(iv) Interest @18% p.a. in the majority award.
21. Though the defendant has supported the minority award but as
noticed above, the minority award also does not deal
with/discuss/assess any documents or evidence. The findings are
given in bullet points. In fact, the same does not contain any reason
whatsoever.
22. Coming to the misconduct owing to the procedure followed, it
is the version in the minority award that after 17 sittings had been
held by the earlier presiding arbitrator (who subsequently resigned)
and witnesses examined on several dates, the presiding Arbitrator
subsequently appointed by FICCI, stopped the plaintiff‟s witnesses
in mid-examination and announced that evidence would discontinue.
23. The plaintiff in the reply to the objections has stated that till
the making of the award, orders in the proceedings prior thereto had
been signed by all the three arbitrators and without objection /
demur whatsoever from the arbitrator who subsequently rendered
the minority award. This is not disputed in the rejoinder also. The
counsel for the defendant has also not shown any dissent being
raised by the arbitrator rendering the minority award, to the
procedure earlier being followed. The hearings having been held
and the procedure having been followed with the consent of all
members of the arbitral tribunal, in my view, it was not proper for a
member thereof to after the hearings berate of or decry the
procedure followed and to which he was a party. Had he any
reservations with respect thereto, he ought to have raised objection
at that time only instead of commenting adversely on the procedure
followed to which he was a party, in the award. The objections in
this regard are thus not found to be constituting any misconduct.
24. The arbitration proceedings remained pending for over seven
years. If the contention of the defendant as to the procedure to be
followed and as borne out from minority award were to be accepted,
the arbitration proceedings would have gone on for another 10
years. The arbitral record discloses that cross-examination of
witnesses running into hundred of pages was recorded. During the
hearing of the objections at least no reference thereto was made by
the counsel for the defendant. It is not as if the arbitrator rendering
the minority award has decided any differently. In fact the minority
award is found bereft of any reasons whatsoever. The majority of the
arbitrators were fully conscious of the plethora of documents and
evidence already adduced in the arbitration proceedings and
concluded:
"This performance test as envisaged in the purchase order was
not carried out. That no formal acceptance test was carried out is
not disputed by Texmaco. All that they say is that J.K. was never in a
position to ensure that the coal as specified would be made available.
.................................. By a registered letter dated 10/12 July, 1985,
J.K. called upon Texmaco to remove all the defects in the boiler.
They were told that if the defects are not removed in the boiler so as
to give satisfactory working, they, J.K. themselves, will arrange to
have the necessary modifications made in the boiler. Ultimately a
new feeder spreader system was obtained from M/s. Isgec John
Thomson and installed in the factory in June 1986. On the wording
of clause 6(d), it appears to us that Texmaco cannot be said to have
fulfilled their obligations under the contract because performance
test is a must to prove the fulfillment of the performance
guarantee.............The technical literature produced by J.K. also
shows that most, if not all, rotors manufactured today are of
overthrow type and that overthrow rotor design has the widest
usage. The underthrow type is not what we call state-of-the-art
technology in the industrial world........The contract in question was
for sale of the warranted machinery which owing to breach of the
warranty could not be used as it was not fit for the purpose for which
it was required............. In a case of breach of warranty, the buyer is
entitled to damages naturally resulting from breach of warranty. But
he is not entitled to damages for unusual consequences because they
are too remote.............The defect in the boiler prevented J.K. from
using it for the purpose for which they purchased it. A consumer will
certainly feel injured if he has to pay the full price for goods with
such defects as here where the boiler was not giving 30,000 kg per
hour steam. We, therefore, hold that the boiler was not of
merchantable quality nor fit for the purpose it was required..........
The seller has blamed the buyer for the quality of coal
fed in the boiler. We are not persuaded that the defect was in the
coal handling plant and not in the design of the boiler. In his letter
dated December 19, 1985, Ramesh Maheshwari, President of
TexMaco Ltd. wrote to Shri S.C. Sethi, President of J.K. Industries
Ltd. "However, notwithstanding the above, we have all the same
decided to effect major modifications in the Spreader design to
convert to the overthrow type. With this proposed arrangement we
feel quite confident that all your problems of wear and tear of the
blades, jamming and bearing failures would be duly resolved. As
agreed with your plant authorities, these changes shall be carried
out during the third/fourth week of February, 1986. We are
manufacturing the requisite components for the modifications on the
priority basis". Texmaco did not carry out major modifications. J.K.
had to do at their own expenses. This establishes, in our opinion,
beyond doubt that the defect resided in the design of the boiler. The
design was defective. The evidence shows that the underthrow type
is an out of date technology.................When J.K. at their own
expense changed from underthrow to overthrow type, the results
were quite satisfactory. This shows that there was a major defect in
the design of the boiler. The boiler was not fit for the purpose for
which it was purchased...............In our opinion, the boiler makers
have not been able to show that the boiler manufactured by them
was fit for the purpose for which it was required. Therefore, the
responsibility for the defects in the plan and design of the boiler
must be laid at the door of the maker and the manufacturer, that is,
Texmaco. They cannot blame the buyer because under the contract,
they have incurred an absolute obligation that the goods will be fit
for the purpose for which they were ordered.........
The particular purpose for which the goods were ordered
was expressly made known to the seller; the buyer relied on the skill
and the judgment of the seller; the sale was by description; the boiler
did not correspond with the description; the boiler was not fit for the
purpose for which it was ordered".
25. This Court is not sitting in appeal on the award. The counsel
for the plaintiff has rightly relied upon Arosan Enterprises Ltd.
Vs. Union of India (1999) 9 SCC 449 laying down that issues raised
in the matter on merits relating to default, time being of the essence,
quantum of damages are all issues of fact and the arbitrators are
within their jurisdiction to decide the issue as they deem it fit and
the courts have no authority or right to interdict an award on a
factual issue.
26. On merits of the pleas, though not required, he also relied
upon China Cotton Exporters Vs. Beharilal Ramcharan Cotton
Mills Ltd. 1961(3) SCR 845 to show that merely because there was
a provision of extension of time, as in the performance bank
guarantee in this case, did not mean that the time was not of the
essence. Since the majority award relies on the Victoria Laundry
case, the counsel for the plaintiff also invited the attention to M/s.
Murlidhar Chiranjilal Vs. M/s. Harishchandra Dwarkadas
1962(1) SCR 653 where the Apex Court while referring to Victoria
Laundry (Winsdsor) Ltd. Vs. Newman Industries Ltd. (1949 ) 1
All E.R. 997 did not hold that the same was contrary to the
principles of Sections 73 of the Contract Act.
27. Per contra the counsel for the defendant relied upon (i)
Essban Paints Pvt. Ltd. Vs. Union of India 2002 (1) RAJ 536 (Del)
wherein the single Judge of this Court had reiterated Maula Bux
(Supra) (ii) Sikkim Subba Associates Vs. State of Sikkim
2001(2) Arb. LR 17 (SC) where the award on the quantum of
damages was set aside by the Supreme Court while balancing the
equities and to ensure that no one is allowed to have their pound of
flesh unjustly against the other, (iii) Saroj Bala Vs. Rajive Stock
Brokers Ltd. 2005(3) Arb. LR 162 (Delhi) where another single
Judge of this Court in relation to the Arbitration Act 1996
emphasised the requirement therein of giving reasons (however this
is a case under the 1940 Act), (iv) Indo Gulf Industries Ltd. Vs.
U.P. State Industries Development Corporation 2003 III AD
(Delhi) 254 on the aspect of limitation and which as aforesaid was
not the plea before the Arbitrator and the minority award on its own
considered the same and on (v) Golden Peacock Overseas Ltd. Vs.
M/s. Ranjit Industries 2006 II A.D. (Delhi) 130 again on the aspect
of territorial jurisdiction ( and I may add that this judgment was
reversed by the Division Bench in Appeal).
28. In the present case on the basis of findings returned in the
majority award and as culled out herein above, I do not find any case
of interference U/s. 30 & 33 to have been made out. The findings are
factual in nature and/or on interpretation of the contract and the
correspondence between the parties and the arbitrator being the
forum chosen by the parties is final on such aspects.
29. As far as the objections on the ground of award of damages of
Rs.20 lacs on a conjectural basis is concerned, the majority award
after detailed discussion of law and facts holds:
"J.K.‟s claims are of two kinds. One is for late delivery of the
boiler. This is fully covered by contract clause 4(b). Under this
clause they were entitled to encash the performance guarantee of
Rs.4,57,200/-. Texmaco were guilty of delay and they cannot claim
refund of it. For delay J.K. has been fully compensated. This covers
the period of delay beyond 15.01.1984. But actually it was delivered
in June, 1984.................. The question is whether the buyer is
entitled to damages for loss caused by the defective goods prior to
repair or replacement by John Thomson. The answer is „yes‟
provided the loss is not too remote and subject to the duty to
mitigate. The claim is for breach of warranty. The boiler was not
rejected. Still the buyer is entitled to damages for breach of
warranty..........Damages are governed by Section 73 of the Indian
Contract Act, 1872 which is based on the rule in Hadley Vs.
Baxendale decided in 1854. The policy is to limit the liability of
defendants against amount of damages unforeseeable to an
unlimited number of plaintiffs over an indefinite period of time
(Pollock and Mulla - Indian Contract 11th ed. Vol. II p. 833) On a fair
reading of the terms of contract, we are of the view that the claim for
damages of this kind and loss of this type as made here is
inconsistent with clauses 4(b) and 7 of the Purchase Order. All that
can be awarded to J.K. is some general and perhaps conjectural sum
for loss of business reasonably to be expected, to use the words of
Asquith L.J. in Victoria Laundry‟s case........... In our opinion the
damages claimed by J.K. are of a speculative nature. Expected
profits are not allowable unless such a loss is proved to be within the
contemplation of the parties.............It appears to us that the present
case is a case of unexpected consequences and unexpected loss of
profits resulting from the breach of warranty.................On the
evidence, we cannot hold that the loss of the magnitude as has been
claimed by J.K. was within the horizon of the contemplation of
Texmaco. It is true that Texmaco with their engineering experience
cannot reasonably contend that the likelihood of some loss of
business was beyond their pre-vision. But the loss of profit now
claimed was not contemplated loss in their given state of knowledge.
We have to look at the contract with the eyes of the parties who
made them n 1982...........the assessment of damages is not an exact
science.
30. Therefore after holding the plaintiff entitled to Rs.9,32,000/-
towards replacement cost and not entitled to the damages claimed of
over rupees seven crores, but at the same time finding the plaintiff to
have suffered owing to breach of contract by the defendant, the
majority of the arbitrators awarded nominal damages of
Rs.6,10,770/- to the plaintiff, besides Rs.9,32,000/- towards costs of
modification/rectification and Rs.4,57,230/- for delay in delivery, i.e.
total Rs.20 lacs.
31. Such lumpsum award by arbitrators cannot faulted with. From
the face of the award it cannot be said that there is any error in the
factual finding of the plaintiff having suffered loss, specially when it
is the admitted position that the boiler supplied by the defendant did
not perform as agreed. The majority of arbitrators found fault to be
of the defendant. Considering the nature of goods and the purpose
for which they were required by the plaintiff, it cannot also be said
that for such breach by the defendant, no loss damage would have
been suffered by plaintiff. The arbitrators have assessed such
damage at Rs.6,10,770/- which is approximately 6% of the total value
of goods ordered and no error can possibly be found therewith.
32. That leaves the question of interest. The arbitrators have not
awarded interest for during the period of seven years when the
proceedings remained pending before them. Interest at 18 % per
annum w.e.f. the date of award has been allowed. Though the
counsel for the defendant challenged interest but it may be noticed
that even the minority award which is supported by the defendant,
awards interest at the rate of 18% per annum. The arbitrators are
thus unanimous as far as rate of interest is concerned. The
Arbitration Act, 1996 also provides for interest at such rate in the
absence of any direction as to interest in the award. I, therefore, in
the entirety of the facts specially when the arbitrator has made a
lumpsum award and while doing which they must have also taken
the rate of interest being awarded into consideration, find the rate
of interest also incapable of interference. However, I find these two
large corporates as the two parties herein are, involved in this
litigation for the last over 20 years. The stakes in the litigation do
not match up to the efforts and expenses which must have been
incurred therein. The litigation appears to be more of an ego issue
between the officers of the two corporates. Only for this reason and
in an attempt to bring this litigation to an end, I by way of incentive
and following the principle in Krishna Bhagya Vs. G.
Harischandra Reddy(2007) 2 SCC 720 of reduction in rate of
interest owing to the rates having fallen in the interregnum, reduce
the rate of interest from 18 per cent awarded, to 15 per cent subject
to the condition that the payment is made by the defendant to the
plaintiff within 30 days hereof. If the payment is not so made, there
would be no change in the award qua interest also.
33. The objections to the award are, therefore, dismissed. The
award is made rule of the Court; save for the modifications as
aforesaid qua interest a decree be drawn
up in terms thereof. The plaintiff shall also be entitled to future
interests from the date of the decree till the date of payment at the
rate of 12 % per annum. The plaintiff shall also be entitled to costs
of these proceedings from the defendant. Counsel‟s fee assessed at
Rs. 1,00,000/-.
RAJIV SAHAI ENDLAW (JUDGE) April 09, 2009 Jr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!