Citation : 2009 Latest Caselaw 1284 Del
Judgement Date : 9 April, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)579A/2002
% Date of decision: 9th April, 2009
M/S JYOTI LTD. .......Plaintiff
Through: Ms Vibha Datta Makhija with Mr
Philemon Nongbri, Advocates
Versus
E.I.H. LIMITED ....... Defendant
Through: Mr H.L. Tikku, Sr Advocate with Ms
Yashmeet Kaur, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. Objections by the defendant under the Arbitration Act, 1940 to
the arbitral award dated 6th November, 2001 and as corrected on
24th December, 2001 are for consideration. The arbitrator was
appointed vide common order dated 28th February, 1996 in suit
No.622A/1995 filed by the plaintiff and suit No.1808A/1995 filed by
the defendant, both for appointment of arbitrator. On demise of the
appointed arbitrator, vide order dated 30th July, 1998 in
OMP.No.160/98 the arbitrator who rendered the award was
appointed as the sole arbitrator to continue with the proceedings.
2. Disputes arose between the parties out of an agreement titled
Hotel Operation Agreement dated 8th August, 1980 between the
parties. Under the said agreement, the plaintiff being entitled to
land, building and super-structure collectively known as Gulab
Bhawan and later christened as Oberoi Palace Hotel at Srinagar,
allowed the defendant to operate the said hotel. The said agreement
was for a term of 20 years. The agreement was terminated by the
parties by mutual consent on 18th June, 1993. Even prior to the
Hotel Operation Agreement dated 8th August 1980, the property had
been let out to by owners thereof and who now control the shares of
the plaintiff to Rai Bahadur M.S. Oberoi since the year 1954 and the
hotel was being run therein. However, the lease was terminated
w.e.f. 1st December, 1975 and thereafter a Hotel Operation
Agreement dated 24th November, 1975 was entered into between the
parties hereto. That was followed by the agreement dated 8th
August, 1980 aforesaid.
3. The plaintiff made the following claims against the defendant
before the arbitrator:
i. of minimum guarantee of Rs 20 lacs per year under the
agreement, for the years 1990-1991, 1991-1992 and 1992-
1993.
ii. for declaration that the agreement stood terminated on
18th June, 1993 and the defendant was liable to meet all
gross operating expenses of the hotel and liable for losses
to the tune of Rs 30,28,218/- suffered during the said three
years.
iii. for declaration that the liability for wages and fees of the
employees of the hotel for the said period, to the tune of Rs
47,82,220/- was of the defendant.
iv. for declaration that the defendant is liable to pay the gross
operating expenses of electricity charges, outstanding
payments to Telecommunication Department, bills of P&T
Department, milk vendors' claims and amounts of sundry
creditors for the said three years.
v. for recovery of amounts needed for carrying out repairs to
the building occasioned due to negligence of the defendant
in maintaining the building during the said years. A sum of
Rs 1,13,78,000/- was claimed on this account.
4. The defendant besides resisting the aforesaid claims also made
a counter claim for total Rs 94,68,389 comprising of (i) Rs
47,31,208/- as the amount payable towards supplies and services
rendered by the defendant to the hotel business; (ii) Rs 35,65,461/-
as insurance premium paid by the defendant on behalf of the plaintiff
and treated as loan; (iii) Rs 11,71,720/-owed by the plaintiff to the
defendant on various counts.
5. It was, inter alia, the case of the defendant before the
arbitrator that the business of the Hotel was in fact of the plaintiff
and the defendant was merely the operator, analogous to a Manager
and for the remuneration of 10% of the gross operating profits - the
defendant was thus not at all responsible for hotel operation
expenses as claimed by the plaintiff. It was further the case of the
defendant before the Arbitrator that due to insurgency conditions
prevailing in the State, the agreement between the parties stood
frustrated in May 1990 itself and in any case due to presence of
force majeure conditions, the obligations under the agreement stood
suspended. It was further the case of the defendant that the
minimum guarantee amount was payable out of the gross profit of
the hotel and if there was no profit there could be no question of
payment of minimum guarantee.
6. The award allows only the claim of the plaintiff of minimum
guarantee of Rs 60 lacs. All the other claims of the plaintiff have
been disallowed by the arbitrator. The arbitrator also found that
there was no contest by the plaintiff to the claim of the defendant of
Rs 94,68,389/- against the plaintiff. The award thus after adjusting
Rs 60 lacs held to be due from the defendant to the plaintiff from the
total sum of Rs 94,68,389/- admittedly due from the plaintiff to the
defendant, directed the plaintiff to pay the balance of Rs 34,68,389/-
to the defendant together with interest at 18% per annum from the
date of the award till the award was made rule of the court.
7. The plaintiff has not preferred any objection to the award. The
defendant has preferred objections limited to the finding of the sum
of Rs 60 lacs being due from the defendant to the plaintiff. It is thus
the case of the defendant that if the said part of the award of the
sum of Rs 60 lacs being due from the defendant to the plaintiff is set
aside, the defendant shall be entitled to recover the said amount also
from the plaintiff. The sum of Rs 34,68,389/- awarded by the
arbitrator to the defendant against the plaintiff has already been
paid by the plaintiff.
8. Before dealing with the objections of the defendant, two
preliminary objections of the plaintiff are considered. The counsel
for the plaintiff firstly contended that the objections were barred by
time. It was stated that the notice of filing of the award was served
on the defendants on 23rd May, 2003 and the limitation for filing the
objections expired on 24th June, 2003, while the objections had been
filed on 5th July, 2003. However, it was found that the objections had
been preferred on the first reopening day after the intervening
summer vacation and during which the limitation was suspended for
the purposes of institution. The said preliminary objection of the
plaintiff is thus meritless.
9. The second preliminary objection of the counsel for the
plaintiff is that the defendant after having received payment from
the plaintiff of the sum of Rs 34,68,389/- as well as the amount found
due under the other arbitration before the same arbitrator between
the same parties, was not entitled to prefer the objections. It was
contended that such conduct of the defendant amounted to
acceptance of the awards and if the objections are entertained it will
lead to injustice to the plaintiff. I, however, do not find any merit in
the said submission also of the counsel for the plaintiff. Nothing has
been shown that the amount was paid or received in full and final
settlement and/or in waiver of the right of defendant to prefer
objection to the part of award against it or as to how the plaintiff has
suffered any injury by such payment. As noticed in the award itself
and to which no objection has been filed by the plaintiff, the plaintiff
had not contested the counter claim of the defendant. The amount of
the counter claim was thus in any case payable by the plaintiff to the
defendant and payment thereof would not debar or estop the
defendant from challenging that part of the award which is against
the defendant. The inference of waiver statutory right of preferring
objections to the award cannot be drawn so lightly.
10. That brings me to the core issue in the present matter. Since
some time has elapsed since the parties were heard, it is deemed
expedient to list out in detail the submissions of the senior counsel
for the defendant.
i. The challenge is only to issues No. 2 and 5 in the list of
issues in para 4 of the award and relatable to whether the defendant
was liable under the clause in the agreement of minimum guarantee.
ii. The parties to the contract are the plaintiff and the
defendant only and none else. This was highlighted because Article
XI titled "Minimum Guarantee" of the Agreement is as under:
"Oberoi guarantees a payment of Rs 20 lacs per year as owner's share of profit. Operator will pay to the owner a minimum amount of Rs 15 lacs every year. Operator will make up the difference between Rs 15 lacs and Rs 20 lacs per year on or before the expiry of every three years period. This clause shall constitute an essential element of the agreement and shall remain in force for the term of the agreement except that the last period shall be of two years. For the first financial year pro rata payment will be made".
It was contended that the use of the word "Oberoi" can refer
only to the defendant and not to Shri M.S. Oberoi. The definition of
gross operating profits in Article 1(xi) was referred, to contend that
it was the difference between the income and the gross operating
expenses. It was contended that the minimum guarantee clause
referred to the same being the "owner's share of profit" and thus the
question of payment of minimum guarantee arose only when profits
were earned, even if of much less than the guaranteed amount and
could not arise when no profits were earned or when the venture
was in losses.
iii. Attention was invited to Article XXIV and XXVII of the Article
to buttress the aspect of frustration and force majeure. It was
contended that there could be no agreement for minimum guarantee
if the contract stood frustrated or a force majeure circumstances
intervened.
(iv) Attention was invited to the affidavit of Mr V. Srinivas Raju
Company Secretary of the plaintiff filed before the arbitrator and
containing in paragraph 16 thereof the computation of payments
made by the defendant to the plaintiff towards minimum guarantee
during the year 1982-1990 and it was contended that the same
showed that minimum guarantee amount was paid only when the
hotel earned profits. It was urged that there could be no payment of
the minimum guarantee amount during the years 1990-1993 when
the hotel did not earn any profit and was, in fact, incurring losses.
(v) Letters dated 24th August, 1981, 20th May, 1982, 5th April,
1990, 5th May, 1990, 25th March, 1991, 16th April, 1991 and 27th
August, 1991 from arbitrators record were shown to contend that
the payments were by way of loan and/or disbursement. Attention
was invited to letter dated 5th April, 1993 of Dr Karan Singh to Mr
P.R.S. Oberoi to contend that the same though in favour of the
defendant had been construed by the arbitrator as against the
defendant.
(vi) The evidence of the witnesses appearing before the arbitrator
was read to contend that (a) the liability of the defendant for
minimum guarantee was understood by the parties to accrue only if
there was a shortfall in profit and not if there was no profit. (b) it
stood proved that circumstances justifying frustration of the
agreement and/or existence of force majeure conditions existed and
owing to which the defendant could not be held liable for the
minimum guaranteed amount for the last three years. The balance
sheet of the plaintiff and certain other letters/documents were also
referred to in this regard. It was urged that the termination of the
agreement with mutual consent in August, 1993 was of no
consequence because the agreement already stood frustrated in
1990.
(vii) Strong emphasis/reliance was placed on para 80 of the award
where the arbitrator has held that "due to force majeure conditions
the respondent perhaps could not be made liable for not operating
the hotel for the period 1990 - 1993..... and it was contended that
the award for liability of the defendant of minimum guaranteed
amount inspite of the arbitrator finding the existence of force
majeure conditions was inconsistent and thus suffered from error on
its face and to that extent was liable to be set aside.
(viii) It was contended that the arbitrator has wrongly interpreted
the clauses of the contract. It was contended that though the
interpretation of contract by arbitrator could not be interfered with if
two views/interpretations were possible but if the interpretation
adopted by the arbitrator was not possible at all, such interpretation
of contract by the arbitrator was liable to be interfered with by the
court.
(ix) Fault amounting to error on the face was found with the
finding of the arbitrator that there was no impossibility in the
defendant paying the minimum guarantee amount to the plaintiff in
spite of existence of conditions of force majeure.
(x) It was further contended that the payments at the rate of Rs
1,20,000/- per month being made by the defendant to the plaintiff
between the years 1990-1993 were not adjusted in minimum
guarantee account by the plaintiff also and were treated by the
plaintiff also as loan.
11. Per contra, the counsel for the plaintiff has urged that (i) none
of the contentions of the defendant amounted to ground on which
award could be interfered with; (ii) misapplication of law by the
arbitrator does not entitle the court to interfere with the award; (iii)
the argument of the defendant of frustration of the agreement was
misconceived inasmuch as, had the contract stood frustrated, the
plaintiff in terms of the agreement would not have been liable for
insurance etc which the defendant continued to incur, claiming to be
on behalf of the plaintiff and for recovery of which amounts the
counter claim had been made by the defendant; (iv) force majeure
covered a case of total impossibility and not of onerous performance;
(v) the arbitrator had collectively looked at the claims and the
counter claims and had reached a decision which did not call for any
interference; (vi) the defendant had held on to the agreement even
after 1990 and did not want to terminate the agreement and in these
circumstances no fault could be found with the award holding the
defendant liable for the minimum guarantee amount under the
agreement; (vii) if the contract stood frustrated, there could be no
question of counter claim of the defendant against the plaintiff for
amounts as per the agreement due from the plaintiff to the
defendant.
12. Before considering the aforesaid contentions, it is appropriate
to cull out the findings in the award with respect thereto.
A. On the "Minimum Guarantee" clause it is held:
"Important terms of the contract in question clearly show that
the respondent, EIH, virtually was to be in full and complete control
of the hotel and there was to be no interference by the claimant in
operation of the hotel...... Earlier a clear agreement was in operation
which entitled the owner to draw specific monthly rental. The owner
spent a lot of money to add more infrastructure to the hotel.............
and wanted a safe return for all his investments besides hoping to
earn substantial income from the operations of the hotel business.
The owner wanted to avoid any financial liabilities coming to it in any
manner......... It is true that the contract provided only 10% income
to the respondent out of profits of the business. The gross operating
profits were to be arrived at by deducting gross operating expenses
from gross operating income being earned from the operation of the
hotel. 90% of the said profits were to go to the share of the claimant
but minimum of Rs 20 lacs per year had to be paid by the respondent
and that was termed as owner's profit. It is not the hotel which had
given this assurance of minimum guarantee but "Oberoi" had given
this guarantee. There is not a whisper in the terms of the agreement
that minimum guarantee was not payable in case there was to be
zero profit or even loss in the hotel business at any time. There was
not even a hint in the whole of the agreement that the losses in the
hotel business were to be responsibility of the claimant. .................
In order to test the rationality of this contention an extensive
example is visualized where the gross profit in any particular year is
only one rupee still as per minimum guarantee clause the respondent
(Oberoi) were bound to skull out from its pockets the minimum
guarantee amount. If liabilities of running the hotel business were to
be considered payable by the claimant then the rationality of having
minimum guarantee amount payable to the claimant by the
respondent becomes illusionary. That could not be the intention of
the parties. It is not acceptable that the minimum guarantee amount
was only payable out of the gross operating profits of the hotel. The
minimum guarantee clause does not say so. The words "owner's
profit" do not mean the gross operational profits of the hotel
business. In case losses to be suffered by the hotel were to be the
liability of the claimant then there could be no minimum guarantee
clauses promising payment of Rs 20 lacs per year to the claimant.
......... The minimum guarantee clause is not linked to any condition
or conditions...... if that were to be so the clause could have been
worded in different words indicating that minimum guarantee was
payable only from gross operating profits and not otherwise. The
clause does not say so....... In case the claimant was only entitled to
share of gross operating profits then there was no need to have
minimum guarantee clause at all. The sharing of such profits stood
already provided in the contract. The minimum guarantee clause
has no connection at all with gross operating profits defined in the
contract. The respondent may be having high expectations from the
hotel and thus in its business was agreed to give minimum guarantee
of payment of Rs 20 lacs guarantee of payment per year to the
claimant as its profit whatever may be the financial gains or losses
were to occur in running and operating the hotel business by the
respondent......... There cannot be any other interpretation of the
terms of the agreement."
B. On "Frustration" and "Force Majeure" it is held:
"The agreement was to remain in force for 20 years w.e.f. Ist
January, 1980. The facts as proved on record show that till 3rd May,
1993 the respondent never took the stand that the contract stood
terminated since May, 1990 due to frustration. It is a fact that the
operations of the hotels virtually came to a standstill from May,
1990. The correspondence exchanged between the parties in
between May 1990 to April, 1993 does not depict any intention of the
parties for treating the contract as terminated. Perhaps the parties
expected the conditions to improve which would revive the operation
of the hotel............. The respondent did not leave the hotel. It
continued to be in charge of the hotel................... In case the
respondent thought that the contract stood terminated due to
frustration, the respondent did not communicate this perception to
the claimant before May, 1993. Rather the respondent continued to
manage the hotel and continued to remain in possession of the hotel.
The respondent did not ask the claimant to take over the hotel at any
time in between 1990 to 1993.
The contract in question was for a long period of 20 years and
only half the period had been covered till 1990 so it is not possible to
hold that due to insurgency taking place from 1990 the contract
stood frustrated. The parties also never thought so till April, 1993.
They agreed to mutually terminate the contract.
It is not correct on the part of the claimant that none of the
conditions mentioned in Force Majeure clause existed in Srinagar
during relevant period. ........ Force Majeure clause does not bring
about the termination of agreement as in the case with frustration
clause. Only liability of the party for non performing particular
terms or condition of the contract stands obliterated and nothing
more. ................. It is further that the obligation to pay a minimum
guarantee amount is not such a term or condition which could not
have been performed due to existence of any of the events
mentioned in force majeure clause. It is thus evident that due to
force majeure conditions the respondent could not perhaps be made
liable for not operating the hotel for the period 1990 to 1993 but
such force majeure condition neither prohibited nor prevented the
respondent from its absolute obligation to pay minimum guarantee
amount. This minimum guarantee amount per year was payable
during the subsistence of the agreement and debars (dehors ?) the
actual operation of the hotel and the results thereof. In Force
Majeure and Frustration of contract a book edited by Evan
Meckendrisk at page 157, it is observed that Force Majeure is the
concept whereby the law recognizes that a contracting party may
without on its part provide an excuse for non performance when
circumstances beyond control render performance impossible. It is
further emphasized that the purpose of including such clause in a
contract is to seek to limit one's exposure to damages for non
performance. .... The respondent's obligation to pay minimum
guarantee amount has not become impossible of performance due to
the hotel becoming non- operable due to force majeure
conditions................... In case the claimant was to claim any
damages from the respondent on its failure to operate or run the
hotel, the respondent could be justified to resist such claim on the
ground of being prevented from performing its obligation to operate
and run the hotel due to presence of force majeure conditions.
However, the respondent's obligation to pay minimum guarantee
has not become impossible to perform as this amount was payable
despite the hotel not earning any income or profit. Thus, it is held
that the respondent's liability to pay minimum guarantee amount for
the year 1990-1993 totaling Rs 60 lacs has not become extinct due to
force majeure condition and the force majeure clause is not
applicable to its liability."
13. The contentions of the senior counsel for the defendant can
now be dealt under two heads; Firstly, the interpretation of minimum
guarantee clause and secondly Frustration and Force Majeure.
14. The interpretation by the arbitrator of the minimum guarantee
clause in the agreement between the parties is not found to be such
which could not have been reached by any person. The senior
counsel for the defendant also agreed that if two views were
possible, the interpretation adopted by the arbitrator could not be
interfered with. In the present case, the defendant had been running
and managing the hotel since 1954; till 1975 on payment of fixed
rent for the premises to the plaintiff and with effect from 1975 also
on payment of fixed amount annually, which, though under the hotel
operation agreement was termed by the parties as minimum
guaranteed profits rather than as rent.
15. I had, during the hearing, also put to the senior counsel for the
defendant that it appears that such change in nomenclature of the
fixed amount being paid to the plaintiff in lieu of the premises where
the hotel was being run/operated belonging to the plaintiff appeared
to be guided by reasons of tax planning/management; Otherwise
there does not appear to be any difference in the transaction
between the parties. The control and management of the hotel
vested in the defendant under the lease deed as well as under the
hotel operation agreement, though under the latter agreement the
possession was deemed to be with the plaintiff. The plaintiff
however had nothing to do whatsoever with the running and
management of the hotel, even under the Hotel Operation
Agreement, as under the Lease Deed. Even if this court in exercise
of power under Sections 30 and 33 of the Arbitration Act, 1940, was
entitled to interfere with a possible interpretation of agreement, on
an interpretation of Article XI read with remaining agreement, I am
not able to find any fault with the interpretation placed by the
arbitrator thereon. The said clause contains an obligation on the
defendant to pay to the owner the minimum amount without
reference to profits or losses. The first sentence of the clause only
gives the colour of the head under which the said minimum amounts
to be paid by the defendant to plaintiff were to be held i.e., as the
profit and not as rent. The payment had to be described by some
name. Since the parties had switched from lease deed to Hotel
Operation Agreement, whereunder the earning of the plaintiff were
to be its profits from hotel business being carried in the property and
not rent as earlier described in lease deed, the expression "owner's
share of profit" finds mention in Article XI of the Agreement.
However, immediately thereafter, the obligation is undertaken by the
defendant "to pay to owner minimum amount". The clause is
described as "constituting an essential element of the Agreement"
and to remain in force for the entire term of the agreement. Inkling
of the mandatory nature of payment is also apparent from the clause
providing for payment of minimum Rs 15 lakhs each year and for
difference between Rs 15 lakhs and Rs 20 lakhs being made up
before the expiry of every three years.
16. The Apex Court in State of Gujrat Vs Dharangdhra
Chemical Works Ltd 1985 (Supp) SCC 1 in relation to a minimum
guarantee clause in contract in that case held that it had been
deliberately inserted with the object and purpose of ensuring that
even in respect of lean years when the production fell short, the
minimum guaranteed amount had to be paid. It was held to be a
special provision in the contract. It was further held that any other
interpretation, as taken by the High court whose judgment was in
appeal, would result in completely rendering the clause of minimum
guarantee otiose and such interpretation could not be made.
17. The provision for minimum charges are often found in
electricity supply contracts. The Division Bench of Punjab High
Court in M/s Watkins Mayor & Co. Vs Jullundur Electric Supply
Co Ltd AIR 1955 Punjab 133 held that a minimum charge is not
really a charge which has for its basis the consumption of electrical
energy; it is based on the principle that the supplier incurs a certain
amount of capital expenditure in plant and machinery on which he is
to have a reasonable return; he gets a return when energy is
consumed by a consumer and when no such energy is consumed by
consumer, he is allowed minimum charges which are really a return
on his capital outlay for a particular consumer.
18. The Division Bench of this court also in Gulab Rai Vs MCD
ILR (1991) Delhi 97 also took the same view.
19. A reading of Article IV of the agreement shows that the entire
operation of the hotel including letting of shops therein was with the
defendant. Under Article V of the authorized representative of the
plaintiff was permitted access to the hotel and right to enter only for
the purposes of inspection and with as little dislocation to operations
of hotel as possible. The actual arrangement between the parties
can be gathered from the stand of the defendant in its reply cum
counter claim before the arbitrator to the effect that inspite of force
majeure and frustration of contract in 1990, the plaintiff did not
come forward even to secure the property and abandoned the
property and to protect its interest and for this reason, the defendant
as a prudent person had no choice but to continue in the property. It
shows that the entire responsibility of earning profits from the hotel
was of the defendant only and though the agreement was that the
gross profits shall be shared between plaintiff and defendant in the
ratio of 90:10, the defendant in lieu of the property provided by the
plaintiff and other expenses thereon under the agreement to be
incurred by the plaintiff and irrespective of whether the defendant
brought earnings to the hotel or not had assured a minimum return
of Rs 20 lacs per annum to the plaintiff on its investment in
infrastructure and upkeep. This was to be irrespective of whether
the operations of the hotel entrusted to the defendant resulted in
profits or not. If the operations resulted in profits, and share of
plaintiff therein was in excess of Rs 20 lakhs, the plaintiff was to get
the excess.
20. I find the controversy around use of "Oberoi" in Article XI to be
of no avail. The earlier agreements it appear were with Mr M.S.
Oberoi personally. The bank accounts of the hotel, under the
agreement were to be operated by the defendant. Similarly the
books of account were also to be maintained by the defendant. The
use of "Oberoi" in the clause shows that the defendant was to make
good the payment mentioned therein to the plaintiff, and the same
was not dependent on monies in the accounts/books of the hotel.
21. There is thus no error on the face of the award in this respect.
22. That brings me to the second challenge i.e., qua
Frustration/Force Majeure. The argument of senior counsel for the
defendant is that the award for minimum guarantee payment in spite
of finding existence of force majeure conditions is erroneous; if force
majeure had intervened, all obligations under the contract including
of payment of minimum guaranteed amounts would be
suspended/discharged.
23. Both Force Majeure and Frustration dealt under separate
heads in the award are facets of section 56 of the Indian Contract
Act, 1872. The arbitrator, under Frustration, has found that the
parties did not treat the contract to have been frustrated and on the
contrary treated the same as subsisting. The same
facts/circumstances/conditions were pleaded for the plea of
Frustration as well as Force Majeure. As noticed above, the plea of
the defendant was that though the agreement stood terminated in
May 1990 but since the plaintiff had abandoned the hotel and did not
come forward to take control/charge of the hotel, the defendant as a
prudent person continued to do so - not under the agreement.
24. The senior counsel for the defendant urged that under Article
XXIV of the agreement, relating to termination, there is no
requirement to give notice; the same is the position in Article XXVII
relating to Force Majeure. It was argued that upon finding the
conditions for termination under Article XXIV (1) (ii) existing,
irrespective of whether the defendant had informed the plaintiff so
or not, the agreement stood terminated and the liability for payment
of minimum guarantee amount came to an end.
25. The award finds that ten years of agreement were remaining in
1990. The contemporaneous correspondence shows that the
defendant was denying liability to pay minimum guarantee amount
for the reason of same being due only when there were profits and
not for the reason of agreement having been frustrated. That reason
has been found incorrect, hereinabove. The defendant in pleadings
before arbitrator set up case of agreement having come to an end
under Article XXIV thereof i.e., Frustration. If that were to be so, the
coming into operation of Article XXVII i.e., Force Majeure would not
arise.
26. Articles XXIV, XXV and XXVII appear to be overlapping each
other and are set out below:
"XXIV. THIS AGREEMENT SHALL STAND TERMINATED:
(i) In the event either party hereto shall suspend or discontinue business or shall be adjudicated a bankrupt or insolvent or shall make an assignment for benefit of creditors or a composition with creditors, or shall file a voluntary petition or an answer admitting the jurisdiction of the court, and the material allegation of an insolvency petition or shall consent to an involuntary petition pursuant to any bankruptcy, reorganization or insolvency law of any jurisdiction or country, or an order shall be entered and continue in effect for sixty days pursuant to any such law approving an involuntary position seeking reorganization or to effect an arrangement or plan for, or appointing any receiver or trustee of or for either party, or for all or any substantial portion of the property of either party, or either party shall apply for or consent for the appointment of such receiver or trustee.
(ii) If the Hotel or any part thereof at any time during the term of this agreement becomes inoperable as Hotel by reason of compulsory acquisition, expropriation, condemnation or other act of any competent authority, or from any cause beyond the reasonable control of the Owner or the Operator or by act of God (subject,
however, to the rights of Operator to claim compensation from the appropriate authority).
(2) The Owner retains the right to require the Operator by written notice to remedy within sixty days any non- performance and/or nonobservance of the conditions of this agreement and/or nonpayment of any amount lawfully due to Owner under this agreement. Unless the matters so complained of are adjusted within the period specified above, the Owner may give a further written notice to the Operator of its intention to terminate this agreement upon a date to be specified in such notice which date shall not be less than sixty days from the date of such further notice. In the event, such further notice is given and he matters complained of are still not complied with, this agreement shall terminate on the date specified in such further notice unless within thirty days from the date of receipt of such further notice either party hereto shall have requested arbitration as provided for in this agreement, in which event this agreement shall remain in force and effect pending the decision in such arbitration proceedings.
XXV. DESTRUCTION OR SUSPENSION OF OPERATION OF HOTEL
In case the Hotel shall be destroyed or damaged to an extent which shall materially interfere with the operation of the Hotel, Owner shall undertake within ninety days after the commencement of such interference to begin repairs, rebuilding or replacing, within a reasonable period of time, so that after such repairs, rebuilding or replacing the Hotel shall be substantially the same. If the Hotel becomes totally inoperable and it is not viable for the Owner to rebuild it, either party shall have the right, without limiting any other rights which either party may have hereunder, to terminate this agreement by notice in writing to the other party. However, it will not be open to the Owner to rebuild the hotel and to manage it either itself or to handover the operations to any third party during the original term of this agreement and the Operator shall have the right to operate the said hotel in terms and conditions contained herein in the event the hotel has been rebuilt, repaired or restored for satisfactory running as a hotel for the remainder of the term.
XXVII. FORCE MAJEURE
This agreement shall not in any way be affected nor shall any party hereto be held liable for any failure or delay in the performance of any undertaking, term or condition herein, if such failure or delay is due to any cause or causes beyond its control, including but not limited to fire, flood, damage by the elements, perils of the sea or air accident, act of God, strike, lock out or other labour disorder, act of foreign or domestic de jure or de facto government, whether by law, order, legislation, decree, rule, regulation or otherwise,
revolution, civil disturbance, breach of the peace, declared or undeclared war, act of interference or action by civil or military authorities or due to any other cause beyond the control of Owner or Operator."
27. The settled principle of interpretation of contracts is that first
an attempt should be made to give effect to each and every clause of
the contract and only if that is not possible, the clause appearing
first prevails over that appearing latter.
28. Clause XXIV (1) (ii) deals with cases where the hotel is
inoperable for reasons mentioned therein. Clause XXV also deals
with hotel becoming inoperable for reason of destruction of property
and requiring any rebuilding work. Clause XXVII deals with failure
of a party to the agreement to perform its obligations for reasons
mentioned therein. To harmoniously construe these clauses it has to
be necessarily held that what is expressly covered in one is not
within the ambit of the other. Thus, Clause XXVII would apply
only where inspite of circumstances mentioned therein, the
agreement is not terminated under clause XXIV.
29. The obligation of the plaintiff under the agreement was only to
make its property/business of hotel being run therein available to the
defendant for operation and to provide initial inventories and capital,
insure the hotel and to carryout structural repairs. The obligation of
the defendant was to operate the hotel and gross profits of which
business where to be shared to the extent of 90% by the plaintiff,
subject to payment of minimum of Rs 20 lakhs per annum by the
defendant to the plaintiff.
30. The arbitrator found the defendant to have between 1990-1993
not taken a stand that the agreement stood terminated under Article
XXIV. That finding of arbitrator bring factual cannot be interfered
with. Even otherwise I find the defendant to have in letter dated 12 th
August, 1991 denied liability for minimum guarantee amount for the
reason of there being no profits and not for the reason of agreement
having been terminated. However, before the arbitrator stand was
taken that agreement stood terminated under Clause XXIV. If the
insurgency conditions fell within XXIV, then naturally XXVII would
not apply. I do not find any error in the finding of arbitrator in this
regard also. I do not agree with the contention of the senior counsel
for defendant that no notice was required to be given. Undoubtedly
the agreement does not provide giving of a notice. But where the
circumstances were such that the defendant could have either
immediately treated the contract as terminated or in expectancy of
improvement, treat the agreement as subsisting, notice was essential
specially when control/charge of hotel admittedly remained with the
defendant. Here the contract on inception was not to do an
impossible act to make it void ab initio. According to the defendant,
the act of operation of hotel became impossible after ten years of
inception of contract. Ten years of contract were still remaining. If
according to the defendant the contract had become void, it ought to
have given a notice under Section 66 of the Contract Act. In SBI Vs
Earnest Traders 67 (1997) DLT 218 relied upon by the senior
counsel for the defendant, there was a banning order dissolving the
contract and in that context it was held there was no need for
termination notice in case of Frustration. There was no such order
in this case and thus notice was essential.
31. The defendant having not succeeded on Article XXIV wants to
fall on Article XXVII. But as aforesaid they are mutually exclusive.
The defendant cannot blow hot and cold i.e., on the one hand say
that the agreement stood terminated and on the other hand say that
it was saved and only performance of obligation dispensed.
32. Be that as it may it having been found that minimum
guaranteed amount was payable irrespective of profits and for the
reason of the plaintiff having made available its property and
business to defendant and which the plaintiff was not prevented even
by events pleaded, from doing, as long as the defendant held the said
property and business and as it admittedly did till 1993, the
defendant remained bound to pay the said amount. No error is
found with this part of award also.
33. Though I have reached the same conclusion as the arbitrator. I
must notice State of UP Vs Allied Constructions (2003) 7 SCC
396, Sudershan Trading Co. Vs Govt of Kerala (1989) 1 SCR 665,
Union of India VS A.L. Rallia Ram AIR 1963 SC 1685, Firm
Madan Lal Roshan Lal Mahajan Vs Hukamchand Mills Ltd and
Champsey Bhara & Co. Vs The Jivrag Ballo Spinning &
Weaving Co Ltd XXVIII CWN 397 (PC) cited by counsel for the
plaintiff, all on the proposition that on interpretation of contract, on
findings on plea of frustration of contract, the court cannot
substitute its own opinion for that of arbitrator and that court cannot
correct mistakes if any in adjudication unless objection to legality is
apparent on the face of the award.
34. Per contra, the senior counsel for the defendant cited
(a) Trustees of Port of Madras Vs Engineering Constructions
Corporation Ltd (1995) 5 SCC 531 holding that arbitrator cannot
go beyond the contract and cannot misapply the law.
(b) Rajasthan State Mines & Minerals Ltd Vs Eastern
Engineering Enterprises (1999) 9 SCC 283 holding that arbitrator
cannot award an amount which is ruled out or prohibited by the
agreement.
(c) Steel India Authority of India Ltd Vs J.C. Budhiraja (1999)
8 SCC 122 again holding that if arbitrator disregards express term of
contract, interference is called for.
It was in the light of these judgments and at first blush finding
some inconsistency in award in holding defendant liable for
minimum guarantee amount inspite of existence of force majeure
that I independently verified the correctness of the findings. I have
reached the same result as the arbitrator.
35. The senior counsel for the defendant has also filed a number of
other judgments on the concept of Frustration. However, in the
facts above and this being a jurisdiction under sections 30 and 33 of
the Arbitration Act it is not deemed expedient to deal with those.
36. The objections to the award are dismissed. The arbitral award
is made rule of the court. Decree in terms thereof be drawn up.
However, in view of the past relations of parties and the other
payments as per award having already been made and admittedly no
business having been carried in last three years it is not deemed
expedient to impose any costs.
RAJIV SAHAI ENDLAW (JUDGE) April 09, 2009/M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!