Citation : 2009 Latest Caselaw 1158 Del
Judgement Date : 6 April, 2009
* HIGH COURT OF DELHI : NEW DELHI
+ Arb. Petition No.90/2008
Judgment reserved on: 24th February, 2009
% Judgment decided on : 6th April, 2009
M/s. Valecha Engineering Limited ......Petitioner
Through : Mr. Chetan Sharma, Sr. Adv. with
Mr. Sanjeev Narula, Adv.
Versus
M/s. D.S. Constructions Ltd. & Anr. .....Respondents
Through: Mr. A.S. Chandiok, Sr. Adv. with
Mr. Ashish Dholakia and Mr. Adarsh
Priyadarshi, Advs.
Coram:
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether the Reporters of local papers may
be allowed to see the judgment? Yes
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
MANMOHAN SINGH, J.
1. This petition is filed under Section 11(6) of the Arbitration
and Conciliation Act, 1996 (for short „the Act‟) for appointment of an
independent Arbitrator.
2. Factual matrix of the case is that Valecha Engineering
Limited (VEL), petitioner herein is a company duly incorporated under
the Companies Act, 1956 having its registered office at Valecha
Chambers, 7th Floor, Plot No. B-6, New Link Road, Andheri (West),
Mumbai-400053. M/s. D.S. Constructions Limited (DSC), respondent
no.1 herein is also a registered company having its office at C-66, South
Extension Part II, New Delhi -110049.
3. The National Highways Authority of India (NHAI) awarded
the contract for Delhi-Gurgaon Access Controlled Highway NH-8 to
Jaypee DSC Venture Limited (JDVL). In order to execute the works of
the project relating to execution of Pile Foundation, JDVL invited bids
in response to which petitioner submitted a bid dated July 14, 2005.
The said bid was accepted by Respondent No.1 and vide letter dated
July 19,2005, it awarded the work to the petitioner at the bid price of
Rs.5,37,58,100/-. VEL also submitted another bid dated October 11,
2005 regarding construction of RTR Palam elevated structure on NH-8
Civil work for substructure and superstructure. Respondent No.1
awarded the said work to VEL at the bid price of Rs.25,91,38,559/-.
4. In both the contracts stated above, Clause 26 and Clause 30
respectively deals with the arbitration clause as under:-
"The decision of the M.D. DSCL shall be final and binding on any dispute or difference which may arise between the parties out of or in connection with this Contract."
5. Certain disputes arose between the parties regarding the
outstanding bills. By relying on the aforesaid arbitration clause without
protest or demur, the petitioner herein preferred two separate petitions
under Section 9 of the Arbitration and Conciliation Act being OMP No.
524/2007 and 562/2007 before this Court. Both the petitions are
pending in this Court. VEL preferred an appeal registered as FAO (OS)
No.391/2007 against an order dated 28 th September, 2007 in OMP
No.524/2007 which was disposed of vide order dated 1.10.2007. In
OMP No.562/2007, interim order has been passed and the petitioner has
been allowed to remove its material and equipment from the site.
6. After obtaining orders in the aforesaid petitions from this
Court, the petitioner vide letter dated 08.01.2008 wrote to the MD,DSC
i.e. arbitrator named in the contract and required him to, inter alia,
appoint an independent arbitrator.
7. The said named arbitrator, vide letter dated 25.01.2008
entered into the reference in view of the fact that he had been named as
arbitrator in the contract.
8. However, in February, 2008 the petitioner filed the present
petition under Section 11(6) (c) of the Act for appointment of arbitrator.
9. The learned counsel for the petitioner relied upon Section
11(6)(c) of the Arbitration and Conciliation Act, 1996. It is alleged that
the arbitrator has failed to perform his function entrusted to him and also
failed to perform any functions under the procedure set out in the clause
relating to settlement disputes. The petitioner alleged that the Arbitrator
named in the arbitration clause in both the contracts executed between
the parties is biased as he is also involved in stopping the certified bills
of the petitioner and stopped releasing the payments to the petitioner. It
is argued that referring the present disputes between the parties wherein
the named arbitrator is in close relation of the respondent company is
totally impermissible and against the principles of equity, justice and
good conscience. In fact the respondent No.1 is a closely held company
of the Narula family. The structure of Respondent No.1 clearly denotes
that it stands on the family pyramid. The respondent No.2 cannot be
Arbitrator in his own actions, he is an interested party being the
Managing Director of Respondent no.1 more so, in the context of the
dispute relating to the encashment of the bank guarantees, settlement/
certifying of the bills, demobilization of equipment, release of
outstanding payment etc, the respondent No.2 is not impartial and is
biased against the petitioner. Besides the respondent No. has been
actively and personally involved in respect of the disputes and
differences between the parties at each and every stage. The
respondent No.2 has in fact acted as an opposite party and rejected the
claims of the petitioner, as orally conveyed in the meetings.
10. It is further alleged that though the clause 26 and 30 of the
contracts satisfy the ingredients of Section 7(4) of the Act and thus
constitute an arbitration agreement, but normally the connotation and
sequence of an arbitration clause is distinct and different. Following
averment has been made by the petitioner in this context :
"7. A bare look at the Arbitration clause reveals the following salient characteristics :
(i) Normally, the arbitration clause is worded as follows : " Any dispute or difference that may arise between the parties arising out of the contract or in relation thereto shall be referred to arbitration of ____(nominated arbitrator-name/designation), whose decision shall be final and binding.
(ii) The said clause i.e. "Settlement of Dispute" is notably different in its character and tenor from the normal arbitration clauses.
(iii) It is styled and nomenclature as "Settlement of Disputes".
(iv) It makes no reference as to the appointment of the
arbitrator.
(v) The said clause in no manner identifies the procedure for reference.
(vi) The said clause makes the decision of the Managing Director of the Respondent as final."
11. It is further alleged that the Managing Director of DSCL
failed to take a decision on time and instead invoked the bank
guarantees. It is averred that a person who has acted personally against
the petitioner cannot now act as non-partisan and thus cannot be
permitted to be the Judge or Jury as well as and the audience. The
petitioner relied upon the case of Alcove Industries Limited vs.
Oriental Structural Engineers Lim., 2008 (1) Arb. LR 393 and,
Delhi and Interstate Constructions Vs. NPCC Limited, 114(2004)
DLT 746.
12. The learned counsel for the respondent submitted that
Section 11(6) (c) has no application in the facts of the present case.
Section 11 (6) (c) reads as under:-
"11. Appointment of arbitrator-
xxxxxx (6) Where under an appointment procedure agreed upon by the parties, xxxxx
(c) a person, including an institution, fails to perform any function entrusted to him or it under that procedure, a party may request the Chief Justice or any person or institution designated by him to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment."
13. It is submitted that the aforesaid provision is not attracted
because when the petitioner invoked arbitration/sought appointment of
arbitrator, the named arbitrator promptly entered upon the reference
within 30 days. Consequently, there was no occasion for invoking
Section 11 (6) (c) and the present petition is liable to be dismissed on
this ground alone.
14. The present petition is not maintainable as the conditions
precedent to the invocation of jurisdiction of this Court to appoint
arbitrator have not been fulfilled. It is settled law that in case of a
named arbitrator, reference has to be made to him and a party is
precluded from approaching the Court for appointing an arbitrator other
than the named arbitrator. In this regard, reliance is placed on the
following judgments:
(i) The Iron and Steel Company Ltd. vs. M/s Tiwari Road
Lines AIR 2007 SC 2064
(ii) Sterlite Optical Technologies Ltd. vs. Bharat Sanchar
Nigam Ltd. 2009 (1) Arb. LR 139 (Delhi)
(iii) Yashwith Constructions (P) Ltd. vs. Simplex Concrete Piles
India Ltd & Anr. (2006) 6 SCC 204
15. It is further submitted that in the two petitions filed by the
petitioner, the petitioner has invoked the jurisdiction of this Court while
stating that:-
"3. .....The agreement stipulated that any dispute or difference which may arise between the parties out of or in connection with the contract would be subject to the decision of the Managing Director of DSC, who is based in Delhi. Thus, this Hon‟ble Court has the jurisdiction to entertain the petition and grant prayers made herein."
It is submitted that the petition is barred by principles of
estoppel/waiver. Having obtained reliefs granted under the previous
petitions based on the above mentioned averment, it cannot be permitted
to take a contradictory stand and file the present petition.
16. On the allegation of arbitrator being biased, it is submitted
that the remedy against a plea of bias as raised by the petitioner is
available only under Sections 12, 13 and 34 of the Act. It has no
application in a petition filed under Section 11(6) of the Act. Reliance
in support of the above proposition is placed on:
(i) Ace Pipeline Contracts (P) Ltd. vs. Bharat Petroleum
Corpn. Ltd. (2007) 5 SCC 304 @ para 21
(ii) Ahluwalia Contracts (India) Ltd. vs. Housing & Urban
Development Corporation & Anr. (2008) 100 DRJ 461 @
para 16
(iii) Dharam Prakash vs. Union of India & Anr.(138) 2007 DLT
118(DB)@ para 5.
17. The respondents denied that the named arbitrator had already
determined the claims of the petitioner. It is submitted that the said
allegation is false to the knowledge of the petitioner since if this were
so, it would certainly not have written to the named arbitrator after the
alleged determination of the petitioners‟ claims had been made.
18. Regarding the contention of the petitioner that the arbitration
clause in the present case is worded differently from the wording
"normally" used in arbitration clauses contained in other contracts, it is
submitted that by filing petitions under Section 9 of the Act and the
present petition under Section 11 of the Act, the petitioner has admitted
that there exists a valid and subsisting arbitration clause, which is wide
enough to cover the disputes between the parties.
19. It is apparent from the provision of Section 11 (6) of the Act
that it applies only when a party or person concerned have failed to
act in terms of the arbitration agreement. In the case of Yashwith
Constructions (P) Ltd. vs. Simplex Concrete Piles India Ltd. & Anr.,
(2006) 6 SCC 204 following observations were made in para 4 :
"4......... There was no failure on the part of the party concerned as per the arbitration agreement, to fulfil his obligation in terms of Section 11 of the Act so as to attract the jurisdiction of the Chief Justice. Obviously, Section 11(6) of the Act has application only when a party or the person concerned had failed to act in terms of the arbitration agreement.
20. In the case of Ace Pipeline Contracts (P) Ltd. vs. Bharat
Petroleum Corpn. Ltd., (2007) 5 SCC 304, it was held that on failure
of the appointing authority to appoint arbitrator within a reasonable
time, mandamus can be issued under Section 11(6) to authority
concerned to appoint arbitrator, as far as possible as per arbitration
clause. However, in large number of cases, it is found that it would not
be conducive in the interest of parties or for any other reasons to be
recorded in writing and that the choice of arbitrator can go beyond the
designated persons or institutions in appropriate cases. But the court
should normally adhere to the terms of arbitration clause except in
exceptional cases for reasons to be recorded or where both parties
agree for a common name. It was held that once a party has entered into
an agreement with eyes wide open it cannot wriggle out of the situation
on the claim that the designated person being an officer of the other side
would be not be impartial or objective. However, if appellant feels that
the arbitrator has notched independently or impartially, or it has suffered
any bias, it will always be open to it to make application under S. 34 to
set aside the award on ground that arbitrator acted with bias or malice in
law or fact.
21. In the case of The Iron and Steel Company Ltd. v. M/s.
Tiwari Road Lines, AIR 2007 Supreme Court 2064, it was observed
that the legislative scheme of Section 11 is very clear. If the parites
have agreed on a procedure for appointing the Arbitrator or Arbitrators
as contemplated by sub-section (2) thereof, then the dispute between the
parties has to be decided in accordance with the said procedure and
recourse to the Chief Justice or his designate cannot be taken
straightway. A party can approach the Chief Justice or his designate
only if the parties have not agreed on a procedure for appointing the
Arbitrator as contemplated by sub-section (2) of Section 11 or in case
the various contingencies provided for in sub-section (6) have arisen. In
this case, the agreement executed between the parties contains an
arbitration clause and Cl. 13.1 clearly provides that all disputes and
differences whatsoever arising between the parties out of or relating to
the construction, meaning and operation or effect of the contract or the
breach thereof shall be settled by arbitration in accordance with the
Rules of Arbitration of the Indian Council of Arbitration and the award
made in pursuance thereof shall be binding on the parties. This clause is
in accordance with sub-section (2) of S. 11. There being an agreed
procedure for resolution of disputes by arbitration in accordance with
the Rules of Arbitration of the Indian Council of Arbitration sub-sections
(3), (4) and (5) of S. 11 can have no application. The stage for invoking
sub-section (6) of S. 11 had also not arrived. In these circumstances, the
application for appointment of Arbitrator moved by the respondent before
the City Civil Court, which was a Designated Authority in accordance
with the scheme framed by the Chief Justice was held to be not
maintainable at all and the City Civil Court had no jurisdiction or
authority to appoint an Arbitrator.
22. As regards the submissions raised by the petitioner about the
connotation and sequence of arbitration clause is concerned, it has
categorically held in the case of Punjab State and Others vs. Dina Nath
(2007) 5 Supreme Court Cases 28 that arbitration agreement need not be
in any particular form. However, it must indicate that the parties had agreed
that any dispute arising between them in respect of the subject-matter of the
contract, should be referred to arbitration. Moreover, it must be in writing
and must indicate the intention of the parties to treat the decision of the
arbitrator as final. If those requirements are satisfied, the mere absence of
the words „arbitration‟ or „arbitrator‟ therein cannot be a ground to hold that
the agreement in question was not an arbitration agreement. A clause in the
agreement in the Work Order providing that any dispute arising between the
principal and the contractor should be referred to Superintending Engineer
for his orders and that his decision would be final and binding on the
parties, held, was a binding arbitration agreement. Further held, the words
„any dispute‟ occurring therein were wide enough to cover all disputes
relating to the Work Order including a dispute relating to non-payment
of money after completion of the work. The word „orders‟ implied some
expression of opinion by the Superintending Engineer which would be
enforceable. The Supreme Court while dealing with the similar dispute in
the present case made the following observations in paras 8, 10, 12 and 14
wherein the clause in dispute is as under :
"Any dispute arising between the department and the contractor/ society shall be referred to the Superintending Engineer, Anandpur Sahib, Hydel Circle No. 1, Chandigarh for orders and his decision will be final and acceptable/binding on both the parties"
"8. A bare perusal of the definition of arbitration agreement would clearly show that an arbitration agreement is not required to be in any particular form. What is required to be ascertained is whether the parties have agreed that if any dispute arises between them in respect of the subject-matter of the contract, such dispute shall be referred to arbitration. In that case, such agreement would certainly spell out an arbitration agreement. (See Rukmanibai Gupta v. Collector AIR 1981 SC 479) However, from the definition of the arbitration agreement, it is also clear that the agreement must be in writing and to interpret the agreement as an "arbitration agreement" one has to ascertain the intention of the parties and also treatment of the decision as final. If the parties had desired and intended that a dispute must be referred to arbitration for decision and they would undertake to abide by that decision, there cannot be any difficulty to hold that the intention of the parties was to have an arbitration agreement, that is to say, an arbitration agreement immediately comes into existence.
xxxxx
10. We have already noted clause 4 of the Work Order as discussed hereinabove. It is true that in the aforesaid clause 4 of the Work Order, the words "arbitration" and "arbitrator" are not indicated; but in our view, omission to mention the words "arbitration" and "arbitrator" as noted herein earlier cannot be a ground to hold that the said clause was not an arbitration agreement within the meaning of Section 2(a) of the Act. The essential requirements as pointed out herein earlier are that the parties have intended to make a reference to an arbitration and treat the decision of the arbitrator as final. As the conditions to constitute an
"arbitration agreement" have been satisfied, we hold that clause 4 of the Work Order must be construed to be an arbitration agreement and dispute raised by the parties must be referred to the arbitrator. In K.K. Modi v. K.N. Modi (2003) 7 SCC 418, this Court had laid down the test as to when a clause can be construed to be an arbitration agreement when it appears from the same that there was an agreement between the parties that any dispute shall be referred to the arbitrator. This would be clear when we read para 17 of the said judgment and Points 5 and 6 of the same which read as under: (SCC p. 584) "(5) that the agreement of the parties to refer their disputes to the decision of the tribunal must be intended to be enforceable in law, and lastly (6) the agreement must contemplate that the tribunal will make a decision upon a dispute which is already formulated at the time when a reference is made to the tribunal." xxxx
12. Keeping the ingredients as indicated by this Court in K.K. Modi in mind for holding a particular agreement as an arbitration agreement, we now proceed to examine the aforesaid ingredients in the context of the present case:
(a) Clause 4 of the Work Order categorically states that the decision of the Superintending Engineer shall be binding on the parties.
(b) The jurisdiction of the Superintending Engineer to decide the rights of the parties has also been derived from the consent of the parties to the Work Order.
(c) The agreement contemplates that the Superintending Engineer shall determine substantive rights of parties as the clause encompasses all varieties of disputes that may arise between the parties and does not restrict the jurisdiction of the Superintending Engineer to specific issues only.
(d) That the agreement of the parties to refer their disputes to the decision of the Superintending Engineer is intended to be enforceable in law as it is binding in nature. xxxx
14. The words "any dispute" appears in clause 4 of the Work Order. Therefore, only on the basis of the materials produced by the parties in support of their respective claims a decision can be arrived at in resolving the dispute between the parties. The use of the words "any dispute" in clause 4 of the Work Order is wide enough to include all disputes relating to the said Work Order. Therefore, when a party raises a dispute for non-payment of money after completion of the work, which is denied by the other party, such a dispute would come within the meaning of "arbitration agreement" between the parties. Clause 4 of the Work Order also clearly provides that any dispute between the department and the contractor shall be referred to the Superintending Engineer, Hydel Circle No. 1, Chandigarh
for orders. The word "orders" would indicate some expression of opinion, which is to be carried out, or enforced and which is a conclusion of a body (in this case Superintending Engineer, Hydel Circle No. 1, Chandigarh). Then again the conclusion and decision of the Superintending Engineer will be final and binding on both the parties. This being the position in the present case and in view of the fact that clause 4 of the Work Order is not under challenge before us, the decision that would be arrived at by Superintending Engineer, Hydel Circle No. 1, Chandigarh must also be binding on the parties as a result whereof clause 4 must be held to be a binding arbitration agreement.
23. In State of U.P. v. Tipper Chand , (1980) 2 SCC 341, it
was held that the clause in dispute in that decision between the parties
did not amount to an arbitration agreement. In that decision, further held
that clause under consideration before them which provided that except
where otherwise specified in the contract the decision of the
Superintending Engineer for the time being shall be final, conclusive
and binding on all the parties to the contract upon all questions relating
to the meaning of the specifications, etc. and the decision of the
Superintending Engineer as to the quality, workmanship, etc. shall be
final, conclusive and binding between the parties does not constitute an
arbitration agreement but while arriving at such a conclusion, Apex
Court referred to a decision of the Jammu and Kashmir High Court in
Dewan Chand v. State of J&K, AIR 1961 J&K 58. In Dewan Chand
case the relevant clause runs as follows: (AIR p. 59, para5)
"For any dispute between the contractor and the Department the decision of the Chief Engineer, PWD, Jammu and Kashmir, will be final and binding upon the contractor."
24. The Supreme Court in Dewan Chand‟s case (supra) had put
strong reliance on the expression "any dispute between the contractor
and the Department" and approved the conclusions arrived at by the
J&K High Court. It came to the conclusion by interpretation of that
clause that there did not exist any arbitration agreement as the decision
of the Superintending Engineer in connection with the work done by the
contractor was meant for supervision and execution of the work and
administrative control over it from time to time.
25. In Bihar State Mineral Development Corpn. v. Encon
Builders (I) (P) Ltd. (2003) 7 SCC 418, Supreme Court held that:
(SCC p. 423, para 14)
"14. There is no dispute with regard to the proposition that for the purpose of construing an arbitration agreement, the term „arbitration‟ is not required to be specifically mentioned therein."
26. Recently in the case of Sterlite Optical Technologies Ltd.
vs. Bharat Sanchar Nigam Ltd., 2009 (1) Arb. LR 139 (Delhi), in a
petition filed under Section 11(6) of the Act for the appointment of
Arbitrator, the petitioner instead of approaching the arbitrator named in
the arbitration agreement i.e. CMD, BSNL approached DDG(MM) for
appointment of arbitrator. Rejecting the application of the petitioner,
learned Single Judge of this Court held as under :
"7.........What the petitioner was required to do was to approach this CMD of the respondent with its claims and only if the said CMD had failed to either himself act as an arbitrator or to nominate/appoint anyone else as the arbitrator, could the petitioner have any cause of action for approaching this Court. The petitioner having admittedly not done so, the petition is liable to be rejected as without cause of action.
27. It is not in dispute that the petitioner itself approached this
court under Section 9 of the Arbitration and Conciliation Act by filing
O.M.P. Nos. 524/2007 and 562/2007 and obtained interim orders
relying upon the clause 26 and 30 of the contracts relating to settlement
of disputes. It nowhere questioned or raised any objection regarding the
above stated clause. It has also written letters dated 8th January, 2008
to the MD, DSC for appointing an independent arbitrator.
28. The plea of the petitioner that the named arbitrator is
impartial and biased cannot be accepted in view of Dina Nath‟s case
(supra). When the petitioner itself has agreed that the dispute pertaining
to both the contracts ought to be referred to MD, DSC, it cannot now
take a stand that respondent no. 2 is acting in a subjective manner. The
respondent no. 2 has entered into reference and initiated arbitration
proceedings. If after making the award by the arbitrator, the petitioner
has any objections to the award, he can file objections under Section 34
of the Act. The provisions of Section 11(6)(c) cannot be invoked in the
present case. The clause referred above in both the contracts is clearly
an arbitration clause though the words „arbitration‟ or „arbitrator‟ are not
included (Dina Nath‟s case (supra).
29. In view of the above discussion, I find no merit in this
petition. It is hereby dismissed.
MANMOHAN SINGH, J APRIL 06, 2009 sa
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!