Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S N.P.A.Engineers & ... vs Government Of India & Ors.
2009 Latest Caselaw 1115 Del

Citation : 2009 Latest Caselaw 1115 Del
Judgement Date : 1 April, 2009

Delhi High Court
M/S N.P.A.Engineers & ... vs Government Of India & Ors. on 1 April, 2009
Author: Shiv Narayan Dhingra
          * IN THE HIGH COURT OF DELHI AT NEW DELHI

                                                      Date of Reserve: 26.03.2009
                                                     Date of Order: 01st April, 2009
OMP No.323/2006
%                                                                         01.04.2009

       M/s. N.P.A.Engineers & Contractors ... Petitioner
                       Through: Mr.G.Lal, Adv.

              Versus

       Government of India & Ors.            ... Respondents
                      Through:  Mr. V.K. Tandon, Adv.


JUSTICE SHIV NARAYAN DHINGRA

1. Whether reporters of local papers may be allowed to see the
judgment?

2. To be referred to the reporter or not?

3. Whether judgment should be reported in Digest?


Order

1.            By this petition under Section 34 of Arbitration and

Conciliation Act, the petitioner has assailed an award dated 9 th May,

2006 passed by the Arbitrator whereby the Arbitrator allowed part

of the claim of the petitioner and disallowed part of the claim.


2.            The petitioner filed these objections to the award claim-

wise. Regarding claim no.2, petitioner has stated that the Arbitrator

did not apply his mind to the facts admitted by the respondent

regarding delay. There was admitted delay of 348 days as recorded

by the Arbitrator.            The Arbitrator while dealing claim no. 1

considered this delay but while partly disallowing claim no. 2

OMP No.323/2006   M/s. N.P.A.Engineers & Contractors v. Government of India & Ors.   Page 1 of 4
 observed that out of this delay of 348 days 180 days delay was

because of the petitioner.              It is stated that this was an obvious

contradiction to the observation made by the Arbitrator in claim no.

1 and the Arbitrator wrongly considered that 180 days' delay was on

the part of the petitioner. The other ground taken by the petitioner

is that the Arbitrator wrongly took into consideration the income tax

return of the petitioner to assess the profitability of the petitioner.


3.            The petitioner is also aggrieved that the Arbitrator did

not allow his claim no. 3 for Rs.2,83,000/- on account of expenses

incurred by the petitioner on maintaining necessary staff during

extended period of contract.                   The claim was of Rs.2,83,000/-

whereas      the    Arbitrator       allowed       only      Rs.35,000/-.             Similarly,

petitioner is aggrieved by rejection of claim no. 4.                             A claim of

Rs.5,10,000/- was made                by the petitioner for deploying men &

machines etc. during the period of work. The petitioner claimed this

amount because the duration of the work got prolonged.                                       The

contention of the petitioner is that the Arbitrator wrongly rejected

the claim holding that the petitioner had not deputed Engineers, etc.

during the entire period since work stood standstill for quite a long

time. The petitioner has also assailed awarding of 6% interest

against 18% interest claimed by the petitioner and awarding of only

proportionate costs.


4.            I have heard counsel for the parties.                       It is settled law

that this Court while considering challenge to an award under
OMP No.323/2006    M/s. N.P.A.Engineers & Contractors v. Government of India & Ors.     Page 2 of 4
 Section 34 does not act as a Court of appeal and cannot re-

appreciate the evidence and arrive at an independent conclusion as

to what would have been a just decision.                        Under Section 34, an

award can be challenged only on limited grounds as enumerated

therein.    The petitioner has not assailed the award on any of the

grounds as enumerated under Section 34. The sole contention of

the petitioner during entire arguments was that there were

contradictions in the award and the learned Arbitrator has wrongly

held that part of the delay, i.e. 180 days was due to the petitioner.


5.            A perusal of award would show that the learned

Arbitrator has given reasons for allowing only a part of the claims

and rejecting rest of the claims made by the petitioner.                                  The

Arbitrator has also considered the delay in execution of the work

and who was responsible for the delay. There was an admission on

the part of the petitioner as recorded by the Arbitrator that the

labour of the petitioner had gone to their respective villages during

harvesting season. Part of the work could not be carried out during

rainy season and due to flood in Yamuna. The delay attributed to

the respondent has been found 53 days plus 13 days delay in

obtaining permission and 26 days delay for tree felling as recorded

by the Arbitrator.         The Arbitrator has specifically observed that

respondent could not be held responsible for 180 days delay when

contractor's labour was not available or there was flood in river

Yamuna etc. Beside that 39 days' delay was treated by both the

OMP No.323/2006   M/s. N.P.A.Engineers & Contractors v. Government of India & Ors.   Page 3 of 4
 parties as dies non.        Thus, no fault can be found with the award on

this count.


6.            This Court cannot re-consider the evidence and arrive at

a different conclusion from what has been arrived at by the

Arbitrator, neither this Court can sit in appeal over the decision of

the Arbitrator. I find that there is no infirmity in the award. The

objections raised by the petitioner to the award must fail.                               The

petition is hereby dismissed.




April 01, 2009                          SHIV NARAYAN DHINGRA, J.

ak

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter