Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Manohar Lal Sethi vs Dda
2008 Latest Caselaw 1753 Del

Citation : 2008 Latest Caselaw 1753 Del
Judgement Date : 26 September, 2008

Delhi High Court
Manohar Lal Sethi vs Dda on 26 September, 2008
Author: Manmohan
*      IN THE HIGH COURT OF DELHI AT NEW DELHI

+                          FAO(OS) 356/2006

                                    Reserved on: September 2nd, 2008

%                               Date of Decision: September 26th, 2008


MANOHAR LAL SETHI                        .... Appellant
                 Through:                Mr. Adarsh B. Dial, Senior
                                         Advocate with Ms. Sumati
                                         Anand, Advocate
                       Versus

DDA                                      ..... Respondent
                           Through:      Mr. Bhupesh Narula,
                                         Advocate.


CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE MANMOHAN

1. Whether Reporters of local papers may be allowed to see the judgment? No
2. To be referred to the Reporter or not?                                No
3. Whether the judgment should be reported in the digest?                No


                           JUDGMENT

MANMOHAN, J :

1. The present appeal has been filed under Section 37(1)(b)

of the Arbitration and Conciliation Act, 1996 seeking to set aside

the judgment and order dated 12th January, 2006 in OMP

No. 110/2002 whereby learned Single Judge has dismissed the

objections filed to the Arbitrator's Award dated 8th January, 2002.

2. The facts of this case are that DDA awarded to the

Appellant the work for development of land for construction of

storm water drain in Mangolpuri Industrial Area in pursuance to

an Agreement dated 28th June, 1985 being No. 28/EE/HD-

25/DDA/85-86. Some disputes arose between the parties which

resulted in rescission of contract by DDA on 23rd January, 1990.

In view of clause 25 of the terms and conditions agreed between

the parties, the Engineer Member of DDA referred the matter to

sole Arbitrator. The learned sole Arbitrator after hearing the

parties, published his Award dated 8th January, 2002. After the

publication of the Award, both the parties filed objections under

Section 34 of the Arbitration and Conciliation Act, 1996.

3. The primary submission of Mr. Adarsh B. Dial, learned

Senior Counsel for Appellant is that the Arbitrator having held

that the rescission of contract by DDA was unjustified, it

obviously meant that DDA was responsible for delay of 839 days

and consequently the Arbitrator could not have rejected the

Appellant's claim for loss of profit due to prolongation of contract.

Mr. Dial stated that even though 31st December 1985 was the

scheduled date of completion, the site was not handed over by

DDA till the year 1989 and on 23rd January, 1990 the contract

was rescinded by DDA.

4. Mr. Bhupesh Narula, learned Counsel for Respondent has

drawn our attention to the fact that the Arbitrator had rejected the

Appellant's claim for loss of profit as Appellant had not filed any

documentary proof to show that he had suffered any

loss/damage. Mr. Narula also drew our attention to the

Arbitrator's finding that the cost index issued by the CPWD was

not applicable to this work as it did not involve either timber or

steel or carpentry work. Mr. Narula further pointed out that

cement was issued by the Respondent at fixed rate and the

Arbitrator had separately awarded to the Appellant compensation

for statutory increase in wages of labour under Clause 10(c).

5. Before we deal with the aforesaid submission of learned

Senior Counsel for the Appellant, it would be useful to refer to

the findings of the Arbitrator in his Award dated 8th January,

2002. The relevant portions of the Award are reproduced

hereinbelow:-

"CLAIM No. 8: Claimants claim Rs. 28,04337/- on a/c of damages.........

Respondent argument is accepted that cost index issued by C.P.W.D. is applicable for building work and not applicable for this work. Item of timber, steel and carpenter are not there in this work. Cement is also being issued at fixed rate. Claimant has been awarded compensation under Clause 10( c) for statutory increase in wages of labour, mason. So claimant claim is not justified.

CLAIM No.9: Claimants claim Rs. 10 lacs on a/c of damages towards establishment.

........Respondent argument is accepted that claimant has never employed staff as claimed by him e.g. claimant has claimed for employment of two Engineers when on inspection of respondent executive, no engineer was found at site engaging of eight chowkidars, eight supervisors are not reasonable and further no documents have been filed to prove the expenditure done to claim damages. So claimant claim is not justified.

COUNTER CLAIM No. 2: Respondents claim a sum of Rs. 19,79,263/- on a/c of work done at risk and cost by M/s Vishal Engineering & Builders.

...........Thus there have been delay on both sides. It appears a mistrust came in the mind of claimant which lead the claimant to abandon the work. ........ As recission of the contract has been held not justified, accordingly respondent counter claim No. 2 is not justified.

CLAIMANTS CLAIM NO. 2:

........As while deciding the respondent counter claim No. 2 it has been held that there has been delay on the part of both the parties resulting in prolongation of contract, so claimant claim is not justified."

6. In our opinion, in view of Arbitrator's finding that both the

parties are responsible for prolongation of contract as well as the

fact that the Appellant had been compensated for statutory

increase in the wages and further as the Appellant had not filed

any documentary proof in support of its claim for loss of profit,

the Appellant's claim for loss of profit due to prolongation of

contract cannot be granted.

7. Lastly, Mr. Dial contended that the nature of reasons given

by the Arbitrator for rejection of Appellant's loss of profit did not

satisfy the parameter of a reasoned award. However, we find

that learned Senior Counsel for Appellant, on the instructions of

the Sole Proprietor of the Appellant, had stated before learned

Single Judge that he would not press the plea of sufficiency of

reasons as he did not want the entire Award to be set aside.

Consequently the Appellant is estopped from raising such a plea.

8. Since no other submission was raised before us, the

present appeal being devoid of merits is dismissed but with no

order as to costs.

[MANMOHAN] JUDGE

[MUKUL MUDGAL] JUDGE

September 26th, 2008 rn

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter