Citation : 2008 Latest Caselaw 1711 Del
Judgement Date : 23 September, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ C.M. No. 4138/2008 in Writ Petition (Civil) No. 14645/2006
Reserved on: 11th September, 2008
Date of Decision: 23rd September, 2008
NAMGYAL INST. FOR RESEARCH ON LADAKHI ART & CULTURE AND ANR.
..... Petitioners
Through: Ms. Shyamala Pappu, Sr. Advocate, with Mr. R. Krishnamoorthy, Advocate.
Mr. K. Datta, Advocate.
Versus
DDA & ORS ..... Respondents
Through: Mr. Rajiv Bansal, Advocate and Mr. Lalit Gupta,
Advocate for applicant in CM No. 4138/2008.
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE MANMOHAN
1. Whether the Reporters of local papers may be allowed to see the
judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
ORDER
% 23.09.2008 : MANMOHAN, J
1. The writ petition has been filed on behalf of Namgyal Institute for Research on Ladakhi Art &
Culture (hereinafter referred as the 'Society') against the respondents praying for quashing of the
letter/order No. 12(33)/83/1L/1051 dated 10.05.2006 issued by the Respondent No.2 (Deputy Director
(IL) DDA) herein directing cancellation of perpetual lease dated 22.11.1995 and praying for further
directions for quashing the proceedings issued by the Respondent No. 3 (Estate Officer, DDA) pursuant
to letter/order dated 24.05.2006 in respect of built up property bearing No. B-25, Qutab Institutional
Area, New Delhi-110 016 (hereinafter referred to as the said property).
2. The present application has been filed for impleadment /intervention by Turner Morrison Land
Ltd. in Writ Petition (Civil) No. 14645-46 of 2006.
3. The brief facts of the case, as per the applicant are as follows:-
(a) The Society was registered on 02.03.1985 to carry on the activities for the promotion of Art,
Culture, Literature and Education.
(b) In order to promote its objective the Society approached DDA for obtaining lease of plot of
land to carry on its activities. Thereafter, perpetual lease deed was executed and registered and
executed on 02.11.1985.
(c) Clause 4 of the lease Deed stipulated that time for commencement and completion of the
proposed building was the essence of the contract.
(d) Due to paucity of funds the society was not in a position to comply with the terms of Clause 4
of the said Lease Deed and the society was unable to even commence the construction of a building on
the said property. In these circumstances, the society approached Turner Morrison Ltd.
(e) In pursuance of negotiations between the parties, a construction agreement dated 11.12.1995
(hereinafter referred as the Construction Agreement) was executed between TML and Petitioner
society.
(f) In terms of the said Construction Agreement, TML agreed and undertook as to costs to
commence and complete construction of a building on the said property by utilizing the maximum
Floor Area Ratio (FAR).
(g) Subsequently, the construction work was duly completed by the applicant company in or about
September, 1999 and the building so constructed by TML has a built up area of 71146 sq.ft. (approx.),
inclusive of 13510 sq. ft. of basement.
(h) However, TML decided to carry on its business of construction through another Company
named Turner Morrison Land Ltd. i.e. the applicant company (hereinafter referred as 'TMLL').
(i) Hence, TML decided to assign its rights and obligations under the said Construction
Agreement dated 11.12.1995 in favour of the applicant herein i.e. TMLL and this intention was duly
communicated to society vide letter dated 04.03.1996 and the society vide its letter dated 28.03.1996, duly gave its no objection in this behalf.
(j) Thereafter, by a Deed of Assignment dated 02.08.1996, all rights and obligations of TML
under the said construction agreement dated 11.12.1995 were assigned in favour of TMLL with the
knowledge and consent of the society. The society was also a signatory to the said Deed of
Assignment.
(k) The Petitioner society has not been able to clear its dues payable to the applicant company.
Apart from incurring huge expenses running into crores of rupees, the applicant company has also
entrusted security deposit of Rs. 3 crores to the petitioner society.
(l) On account of the failure of the society to repay the construction cost to the applicant company,
the present application has been filed.
4. The Clauses of the said Construction Agreement 2, 3.1, 3.2 and 4 executed between the first party, Namgyal Institute for Research on Ladakhi Art and Culture and the Second Party, Turner Morrison Ltd., dated 11th December, 1995 are reproduced below:
"2. It will be the obligation of the Second Party to do the following:
(a) To appoint Architect, Engineer, Sub-contractor for commencing the construction on the said plot.
(b) To prepare the plan for construction of a building/buildings on the said plot utilizing the maximum FAR permissible and get the same signed by the First Party and obtain necessary approvals from all relevant authority and authorities for construction of the building on the said plot of land.
(c) To commence and complete construction on the said plot utilizing the maximum FAR and consisting of Basement floors and other floors.
3.1 It will be obligation of the First Party to do the following:
(a) To cooperate with the Second Party for obtaining all necessary approvals and permissions and for that purpose to sign all applications, affidavits as may be required from time to time including the plans, revised building plan and all documents and papers for commencing the construction, completing the construction and for obtaining "C" form and "D" form and completion certificate.
(b) To pay the construction cost to the Second Party at the rate of Rs.1, 200/- per sq. ft. to the Contractor which the First Party shall pay to the Contractor in stages depending upon the progress of the work.
(c) The First Party further agrees and undertakes to sign all necessary papers and documents as may be required by the Second Party from time to time to enable the Second Party to commence and complete the construction.
3.2 (a) It will be the obligation of the First Party to make payments to the Contractor in accordance with the Schedule of payment annexed hereto and in the event delay in any payment, the First Party shall pay interest @ 36% per annum on the delayed payment.
(b) That till the entire construction cost is paid by the First Party to the Second Party, the Second Party shall have a lien over the said land along with constructions thereon and in that event shall have full authority and power to appropriate all its construction cost, interest and expenses by safe, transfer or lease of such constructed area so as to meet the outstanding liabilities of the First Party and in that event the First Party shall not raise any objection in any manner whatsoever.
(c) That further to secure the payments to be made to the Second Party the First Party shall deposit the original title deeds of the said property with the Second Party who shall retain the same as a security till the entire payment and entire construction cost and all the dues and expenses payable by the First Party to the Second Party is paid fully.
4. The construction shall be completed by the Second party within a period of 24 months from the date of sanction of the building plan by the relevant authority or within such extended period as may be agreed upon between the parties. (emphasis supplied)"
5. The relevant Clause 3.2 sub-clause b of the aforesaid Construction Agreement as well as the
Resolution of the Governing Body dated 25.09.1995 clearly stipulates that till the entire agreed
construction costs are paid by the Society to the contractor, a lien over the said property alongwith all
constructions thereon was created in favour of TML and TML was granted unfettered rights to recover
any outstanding construction cost, interest and expenses inter-alia by sale, transfer or lease of the
constructed area. The society was not entitled to raise any objection to such utilization of the said
building by TML. Further, in terms of Clause 3.2 (C) above, the society was also to deposit the
original title deed of the said property with the TML. Therefore, it is seen that TML has substantial
and valuable interest in the said property which formed the subject matter of the writ petition as can
also be noted from the abovementioned Construction Agreement and the Resolution of the Governing
Body of the Society.
6. It is also pertinent to note that TML decided to carry on its business of construction through
another Company TMLL i.e. the applicant Company. The Rights and Obligations of TML under the
said Construction Agreement were assigned in favour of the applicant i.e. TMLL under the Deed of Assignment dated 02.08.1996 with the knowledge and consent of the Society and the Society was also
signatory to the said Deed of Agreement. Therefore, the interest in favour of TML was assigned in
favour of the applicant company in the said property.
7. The learned Senior counsel for the petitioner, Ms. Shyamala Pappu contended that the said
TML have forged and fabricated documents purported to be executed by the officer bearers of the
petitioner. However, since the initial agreement has not been denied, therefore, we are of the opinion
that the applicant is a necessary and proper party.
8. In view of the above observations, the applicant Company is permitted to be impleaded as a
party in this writ petition and allowed to participate in the writ proceedings.
9. Mr. K. Datta, Advocate, contended that he has been appearing for the petitioner in Writ
Petition(C) No. 17210/2006. However, Mr. R. Krishnamoorthy, Advocate, contends that he is now
appearing for the petitioner. But we find that Mr. K. Datta has not been given a discharge by the
petitioner. Therefore, we direct the petitioner to be present in the court for further directions on 4 th
November, 2008.
MANMOHAN, J
SEPTEMBER 23rd , 2008 MUKUL MUDGAL, J
s/dr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!