Citation : 2008 Latest Caselaw 1619 Del
Judgement Date : 11 September, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) No. 843A/1990 and I.A. No. 7640/1993
Date of decision : 11.9.2008
IN THE MATTER OF :
M/S UPPAL ENGINEERING CORPORATION ..... Petitioner
Through Mr. Pramod Kr. Seth, Adv.
Versus
C.W.C ..... Respondent
Through Mr. K.K. Tyagi with Mr. Iftekhar
Ahmad, Advs.
CORAM
* HON'BLE MS.JUSTICE HIMA KOHLI
1. Whether Reporters of Local papers may be
allowed to see the Judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the
Digest? Yes
HIMA KOHLI, J. (ORAL)
1. The present application filed under Sections 30 and 33 of the
Arbitration Act, 1940 (for short 'the Act') is directed against an award dated
05.9.1989 passed by the learned Arbitrator in respect of the disputes
between the objector/contractor and the respondent/CWC. In a nutshell, the
facts of the case are that the objector/contractor was awarded the work of
construction of 50,000 MT capacity godown along with the ancillary buildings
at Muzaffarnagar (UP), vide award letter dated 31.5.1979. The said work
was to be completed within a period of 15 months i.e. by 09.9. 1980.
2. It is the case of the objector/contractor that though it had geared
up its entire resources and mobilized to the site of work, the work could not
be proceeded with at the desired pace because of a stay order operating at
the site of work and later, because of shortage of diesel, which the
respondent/CWC failed to arrange, in spite of various requests made by the
petitioner. On the other hand, the case of the respondent/CWC is that the
objector/contractor had to complete the work by 31.3.1981 and the total cost
of work was Rs.1,43,32,130.10 paise, but the actual work done by the
objector/contractor was of the order of Rs.1,09,44,000/- till 05.8.1981 and
thereafter, the work was abandoned by him. As a result, a notice was issued
to the objector/contractor but it refused to hand over the possession of the
godowns and the stocks to the respondent/CWC. Hence, the respondent was
compelled to issue a notice to show cause to the objector/contractor, as to
why its contract may not be cancelled. As the response to the aforesaid
notice to show-cause was found to be un-satisfactory by the respondent, the
contract was rescinded vide letter dated 09.9.1981.
3. It is undisputed the disputes and differences arose between the
parties and the petitioner invoked the arbitration clause, as per clause 25 of
the agreement between the parties, seeking adjudication of the disputes by
appointment of an arbitral tribunal, vide letters dated 13/14.8.1981 and
14.10.1981. Thereupon, the Appointing Authority, in the first instance,
appointed one Sh. A.U. Rajsinghani as the Sole Arbitrator vide letter dated
22.10.1981. After a point of time, the said Arbitrator expressed his inability
to continue with the work and thereafter, the Managing Director of the
respondent/CWC appointed Sh. B.K. Sharma, as the Arbitrator, vide letter
dated 08.9.1988, who continued with the proceedings and has rendered the
award dated 05.9.1989, impugned by the objector/contractor herein.
4. The first objection raised by the learned counsel for the
objector/contractor to assail the impugned award is that the original
agreement governing the parties is missing from the records and thus, the
award having been rendered in the absence of the original agreement before
the arbitral tribunal, the same is liable to be set aside. In support of the
aforesaid submissions, learned counsel for the objector/contractor relies on
the judement of Bhai Sardar Singh & Sons vs. New Delhi Municipal
Committee, reported at AIR 1981 Delhi 374 and an unreported judgement
dated 09.2.2001 in the case of Uppal Engineering vs. UOI (Suit No. 412-
A/1990).
5. The aforesaid plea raised on behalf of the objector/contractor is
disputed by the counsel for the respondent/CWC who submits that a perusal
of the ground taken by the objector/contractor in the application shows that
there was no mention of such an objection taken by him now. Counsel for
the objector/contractor draws the attention of this Court to the last para of
pages 25 and 26 of the objections to state that such a ground was taken in
the aforesaid paras. A perusal of the aforesaid pages shows that the
objector/contractor has levelled an allegation against the Executive Engineer
of the respondent/CWC to the effect that the records of the arbitral
proceedings were given by the learned Arbitrator to him and upon an
inspection of the records, it is revealed that the papers have been replaced
from the original records and that the original agreement filed before the
learned Arbitrator, which contained the schedule of terms and rates of the
subject work are also missing and have been replaced by a blank booklet of
the contract conditions.
6. The aforesaid objection taken on behalf of the objector/
contractor cannot be interpreted to mean that any objection was taken to
the effect that the original agreement was missing from the arbitral records
and hence, it ought to be assumed that the learned Arbitrator rendered an
award without perusing the original agreement. On the contrary, the
objector/contractor has himself stated that the original agreement was filed
before the learned Arbitrator and that the same contains a certain schedule
of terms and rates, which were purportedly replaced by a blank booklet of
the contract conditions. In fact, what has been termed as a "blank booklet"
of the objector/contractor, is a printed format of the contract conditions.
Hence, the judgments sought to be relied upon by the counsel for the
objector/ contractor, can be of no avail. At this stage, learned counsel for
the objector/contractor submits that what was meant by the aforesaid
averment was that the booklet was unsigned. However, no such objection
has been raised in the grounds taken to assail the award and such an
objection taken at this stage in the course of arguments cannot be
permitted, being barred by limitation. For the aforesaid reason, the first
objection taken to the impugned award is rejected.
7. The second objection taken on behalf of the objector/contractor
is that no arguments were heard by the learned Arbitrator on claims No. 1 to
9 at any point of time. He relies upon the observations of the learned
Arbitrator, in the last para of page 2 of the award, in support of his
submissions. In the last para of page 2 of the award, the Arbitrator observed
that the previous Arbitrator had not framed any specific issues, and instead,
he had considered each of the 20 separate claims filed individually. He
further noted that he had examined 10 claims, and that the 10th claim was
only partly examined. Therefore, the learned Arbitrator started further
examination from the stage from where the earlier Arbitrator left.
8. The aforesaid observations of the learned Arbitrator have to be
examined in the light of the proceedings held by the previous Arbitrator. A
perusal of the arbitral record shows that, in the order-sheet dated 26.5.1989,
the sole Arbitrator observed as below:
"In the first instance, the progress in the case made by the previous Arbitrator Shri A.U. Rajshinghani was reviewed and the minutes pertaining to the 24th, 25th and 26th meetings held on 03.12.1984, 05.1.1985 and 19.1.1985 respectively were gone through. It was noted that Claim No. 10 and beyond upto No. 15th, as lodged by the claimants were to be examined."
9. Further, the records reveal that the meetings held on 03.12.1984
and 19.1.1985 by the previous Arbitrator, which have been stated to be
reviewed by the subsequent Arbitrator, give the details of the discussions
and the decisions taken by the earlier Arbitrator. Viewed in the aforesaid
light, the observations of the learned Arbitrator at page 2 of the award fall
into place. Taking it further from there, the claims of the objector/contractor
in respect of claims No. 1 to 9 have been dealt with at pages 4 & 5 of the
impugned award, and it shows that the learned Arbitrator duly considered
the material placed on the record, including the measurements of various
items taken in the Measurement Book, the terms and conditions of the
contract agreement and the nature of the work carried out by the
objector/contractor. Out of claims No. 1 to 9, claims No. 4, 6, 7 & 8 of the
objector/contractor were duly accepted. Hence, the objection raised by the
objector/contractor to the effect that no arguments were heard on claims No.
1 to 9 is not acceptable.
10. In this context, it is also relevant to note that the question of
hearing arguments by the learned Arbitrator, in respect of claims No. 1 to 9
would have arisen, had objector/contractor appeared before the learned
Arbitrator. A perusal of page 3 of the award shows that the
objector/contractor repeatedly sought long adjournments from the learned
Arbitrator. The learned Arbitrator was compelled to issue show-cause
notices to him on account of his non-appearance. He observed that the
proceedings were to be finalized and an award made by 05.9.1989 and as
the objector/contractor failed to appear before him, a show-cause notice was
issued on 31.8.1989 regarding ex-parte consideration of the claims. The
same was sent to the objector/contractor by registered post, special
messenger and also telegraphically. The objector/contractor refused to
accept the notice sent by special messenger. The registered AD notice was
not returned back and the telegraph was deemed to have been received in
normal course. Still, the objector/contractor did not appear on 04.9.1989
nor did he send any communication for explaining his absence, thus,
compelling the learned Arbitrator to proceed to render the award on the
basis of the documents on the record. It, therefore, does not lie in the mouth
of the objector/contractor to state that no arguments were heard by the
learned Arbitrator, in respect of claims No. 1 to 9 at any time. The said
objection is rejected.
11. As far as the third objection raised on behalf of the
objector/contractor to the effect that there was no application of mind by
the sole Arbitrator, in view of the fact that claim No. 3, relating to anti-
termite treatment for a sum of Rs.9,05,331.18/- was rejected is concerned,
counsel for the objector/contractor states that, despite the fact that vouchers
in respect of the work of anti-termite treatment were filed before the learned
Arbitrator and are a part of the arbitral record, the said claim was rejected on
the plea that the petitioner never produced the desired vouchers or any
evidence, in support of the said claim. Counsel for the respondent states
that the aforesaid claim was opposed by the respondent/CWC as the same
was not part of the work awarded to the contractor. He further states that
the objector/contractor failed to place on record any documents along with
claims/submissions to establish the said claim, and furthermore, even if
notice is taken of the document indicated at page No. 28 of the arbitral
proceedings, which was a reminder dated 7.5.1980 by a contractor to the
objector for payment of a sum of Rs. 3,48,540/- towards anti-termite
treatment, the aforesaid document could not have substantiated the claim
raised of over Rs.9,00,000/- raised by the objector/contractor in claim No.3.
12. It is further pertinent to note that the aforesaid document came
to be filed by the objector/contractor only on 26.5.1989. In the order-sheet
of the proceedings dated 03.12.1984, the objector/contractor was specifically
directed that it should submit the vouchers in respect of purchase of Aldrex
by the next date i.e. 20.12.1984. It was also recorded that, in case any party
fails to bring the relevant documents desired by the Arbitrator on the said
date, the Arbitrator would proceed and finalize the discussions even without
reference to such documents. The aforesaid document came to see the light
of the day only on 26.5.1989, that is, after a period of over four years from
the date of the aforesaid order. Furthermore, as per the records, the
objector/contractor chose to stay away from the arbitral proceedings on the
date when it was fixed for arguments, as is apparent from the perusal of the
impugned award. In these circumstances, the learned Arbitrator cannot be
blamed for dis-allowing the said claim on the ground that the claimant never
actually produced the desired vouchers, in respect of the said claim.
13. The last objection taken by the learned counsel for the
objector/contractor is in respect of claim No. 14, which relates to an amount
of Rs.11,75,000/-, claimed on the ground of an all around increase in the
prices of building materials etc. Counsel for the objector/contractor submits
that the increase claimed by his client was @ 18%, as detailed in „Ext. C-97‟
and there was no question of absorbing 10% escalation and thus, there is an
error on the face of the award. In reply thereto, counsel for the
respondent/CWC states that the claim for escalation has to be seen in the
light of the provisions of the contract. The escalation was governed by
Clause 10(C) of the Contract Agreement, under which the
claimant/contractor was required to absorb the first 10% of the increase in
prices/wages. Taking that into consideration, the learned Arbitrator held that
at best, he could be compensated for increase upto 8%. However, looking at
the time span for which the execution of the work remained held up for
reasons beyond the contractor‟s control, the learned Arbitrator decided to
give to the respondent/contractor 2% increase as against 8%. Thus, a sum
of Rs.1,30,000/- was awarded to the objector/contractor.
14. There appears no error on the record, as far as observations of the
Arbitrator in respect of Claim No.14 is concerned. It is settled law that this
Court, while deciding the objections under Sections 30 & 33 of the Act, is not
required to go into the reasonableness of the reasons given by the learned
Arbitrator (Refer : State of Rajasthan vs. Puri Construction Co. Ltd. & Anr., JT
1994 (6) SC 412). Furthermore, merely because this Court could arrive at a
different conclusion on the same set of facts and evidence on the record, as
compared to the award given by the Sole Arbitrator, cannot be a ground for
the Court to interfere with the award and hold it to be perverse or arbitrary.
(Refer: DDA vs. Bhagat Construction Co. Pvt. Ltd., 2004 (3) Arb. LR 481).
The observations made by the learned Arbitrator are based on sound
reasoning as indicated in the impugned award and does not deserve
interference. Hence, the said objection is also rejected. No other ground is
urged on behalf of the objector/contractor.
15. In view of the aforesaid discussion, it is held that there is no
merit in the objections filed by the objector/contractor. The application is,
therefore, rejected. The award dated 05.9.1989 rendered by Sh. B.K.
Sharma, Sole Arbitrator is made rule of the Court. The respondent shall
be entitled to receive future interest on the awarded amount payable @ 9%
p.a. from the date of the decree, till the date of realization. Decree sheet be
drawn up accordingly.
HIMA KOHLI,J
SEPTEMBER 11, 2008 KA/sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!