Citation : 2008 Latest Caselaw 1571 Del
Judgement Date : 8 September, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS (OS) No.1476A/1999 & IA No.1125/2008
Reserved on : 14.08.2008
Announced on : 08.09.2008
M/s Bajaj Electricals Ltd. ...... Plaintiff
Through : Mr. S.B. Upadhaya, Sr. Advocate with Ms. Anisha
Upadhaya, Ms. Shubhra Goyal, Advocates
versus
Power Grid Corpn. Of India Ltd. ..... Defendant
Through : Mr. Atul Varma with Ms. Suman Dutta,
Advocates
CORAM:
Mr. Justice S. Ravindra Bhat
1. Whether reporters of local papers may be Yes
allowed to see the judgment?
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
Mr. Justice S. Ravindra Bhat
1. In these proceedings, the request to make an award of the arbitral
tribunal, appointed by the parties, rule of court has been made. In the award,
dated 31-5-1999, a majority of two arbitrators had found in favour of the
CS (OS) 1476A/1999 Page 1
claimant plaintiff (hereafter called "the contractor"). In the minority award of
Shri S.K. Sinha, the claims of the contractor were rejected. The defendant/
Respondent (hereafter "Corporation") assails the findings, in an application,
under Sections 30/33 of the Arbitration Act, 1940 ("the Act"), being IA
9419/1999.
2. The brief facts necessary for a decision in these proceedings are that
the National Thermal Power Corporation (NTPC, the predecessor of the
Corporation) had, in 1985, invited tenders for the supply and erection of
station lighting package; the contractor submitted its offer on 26th July 1985,
which, after evaluation, was found to be the lowest. The contractor was
awarded the work on 10th April 1986, concerning Station Lighting Package for
400 KV Durgapur Substation. Clause 2.0 of the contract spelt out the intent
and scope of work; Clause 2.5, which has some relevance in this dispute,
read as follows:
" 2.5: Notwithstanding the classification of the total scope of work under this award into two portions, the contract is awarded to you on single source responsibility basis and breach in any portion or part of the Contract shall be construed as breach of the entire contract.
The scope of work shall include all such items and works which although not specifically mentioned in the bid documents and/or in your proposal but are needed to make the equipment system complete unless otherwise specifically excluded under exclusion in our bid documents."
According to Clause 4, the agreed consideration for the contracted work was
Rs. 34,52,510, divided into the supply portion of Rs. 27,89,116/08 and Rs.
6,63,394/56.
CS (OS) 1476A/1999 Page 2
3. Clause 37.01 stipulated that no alteration, amendment, etc., (to the
contract) could be made by the contractor, except as directed by the
Engineer, in writing. The Engineer, however, had power (subject to other
terms) during execution of the contract, by notice in writing, to instruct the
Contractor to make such variation in the contract without prejudice to the
contract. Clause 37.04 provided as follows:
"37.04 If any Variation in the works, results in reduction of Contract Price, the parties shall agree in writing, so to the extent of any change in the price before the Contractor proceeds with the change."
Clause 37.06 stated that:
" Notwithstanding anything stated above in this clause, the Engineer shall have the full power to instruct the Contractor, in writing, during the execution of the Contract, to vary to quantities of the items or groups of items in accordance with the provisions of clause entitled „Change of Quality‟ in section INB of this volume I. The Contractor shall carry out such variations and be bound by the same conditions, as though the said variations occurred in the contract documents. However, the Contract Price shall be adjusted at the rates and the prices provided for the original quantities in the Contract."
4. The NTPC deemed it necessary to lay cables, i.e 3 core x 10 sq. mm &
4 core x 10 sq. mm 415V armoured AL PVC cables. The contractor agreed to
this, which was recorded in Minutes of Meeting between parties, dated 5-4-
1987. The work progressed and on 21st January, 1988 the second Running
Account (RA) bill was prepared which recorded that 5775.7 metres of 2Cx
10sq.mm cables laying and termination @ Rs. 65 per sq. metre, less 4%
rebate was supplied; the bill was passed, and amounts paid on 11-2-1988.
The entire work was completed and the material reconciliation statement
CS (OS) 1476A/1999 Page 3 was jointly prepared and signed by the parties, on 12-4-1988. NTPC took
over the work, on 31st May, 1988. In the meanwhile, the contractor had
requested, through letter dated 14-4-1988 for release of payments in respect
of 4C x 10 sq. mm cable. The parties also exchanged correspondence,
whereby the contractor asked for payments against work including supply of
3C and 4C x 10 sq.mm cables, at rates at least equivalent to what was
agreed to be paid in respect of 2C cables. On 2-8-1988 NTPC proposed an
amendment to the contract revising the quantity of work, both in respect of
the supply and erection parts of the contract. The total amount of
consideration was reduced from Rs. 34,52,510/64 to Rs. 29, 94,640/-. The
contractor expressed disagreement and did not consent to this change, and
communicated this intention through its letter dated 24th September, 1988. It
also mentioned, inter alia, that several outstanding amounts were payable to
it, under the contract, and that the NTPC had not finalized the cost of 4C x 10
sq. mm cables supplied.
5. The NTPC, in its letter dated 28th October, 1988, expressed its
assurance that it would look into the matter, and finalize it so that payment
could be released - to the contractor, at the earliest. Thereafter, on 18/19 th
April, 1989, the NTPC proposed yet another amendment ("the second
amendment") to the contract, whereby it reduced the contract price to Rs.
27, 59, 963.40. This amendment "fixed" the rates for items, such as laying
and terminating 415 V 4C x 10 sq. mm AL PVC armoured cable (Rs. 55,272);
laying and terminating 415 V 3C x 10 sq. mm AL PVC armoured cable (Rs.
CS (OS) 1476A/1999 Page 4 5,103/-); laying of 2C x 10 sq. mm AL PVC armoured cable in existing cable
trench panels, etc (Rs.33, 348.70); One end termination of 2C x 10 sq. mm
AL PVC armoured cable in existing cable trench panels, etc (Rs. 5126.40).
Besides these, the NTPC proposed recovery from the bills of the contractor.
This amendment was also not accepted by the contractor.
6. The parties to the contract attempted to resolve their differences; a
series of meetings were held for that purpose, including those held on 27-7-
1989; and letters exchanged between them. On 3-4-1993, the NTPC's
contracts and liabilities, in regard to the agreement in question, were taken
over by the corporation. Thereafter, on 13th April, 1993, the corporation and
the contractor held a meeting, where it became apparent that the former
was insisting on acceptance, by the contractor, of the two amendments,
proposed by it to the original contract. The contractor approached this court,
under Section 20, for filing the arbitration agreement. That petition was
disposed on 19th July, 1996; arbitrator nominees of each party were
appointed, and the said arbitrators appointed an umpire/ third arbitrator.
7. In the arbitral proceedings, a majority of two arbitrators held in favour
of the contractor, allowing his claims and directing refund of amounts
withheld by the corporation. The third arbitrator, however rejected the claims
and reference, holding, inter alia, that the demands were time barred.
8. Mr. S. B. Upadhyay, learned senior counsel, submitted that the
impugned award is unsustainable in law. It was urged that the arbitrators
CS (OS) 1476A/1999 Page 5 overlooked the fact that the dispute in this case was excepted as the
decision of the competent official, i.e the Engineer was final. Therefore, on a
proper application of the law laid down in Vishwanath Sood -vs- Union of
India AIR 1989 SC 952, it has to be held that the arbitrators lacked
jurisdiction in adjudicating upon the claims made by the contractor.
9. It was next contended that the award is unsupportable in law, since the
majority of arbitrators rejected the corporation's contention about the
contractor's claims being time barred. Counsel urged that the claim for
money arose in 1988; the contractor raised a dispute and approached the
court in 1994, for appointment of arbitrator. In such circumstances, the
award should not have allowed the claims. Learned counsel submitted that
the dispute, if considered to be with reference to the Minutes of Meeting of
July, 1989 was clearly time barred. It was also urged that the disputes first
arose on 28th August, 1989 when the parties disagreed in regard to the
amounts, payable to the contractor. Thus, applying Article 137 of the
Schedule to the Limitation Act, the disputes were clearly time barred and
could not have been entertained. Reliance was placed upon the decision
reported as S. Rajan -vs- State of Kerala 1992 (2) Arb LR. 281 and J. C.
Budhraja vs. Chairman, Orissa Mining Corporation Ltd 2008-(1)-Arb.LR 238. It
was submitted that there was no acknowledgement of liability as
contemplated by Section 18 of the Limitation Act.
CS (OS) 1476A/1999 Page 6
10. It was submitted that the award discloses a patent illegality in regard
to the merits, as the arbitrators concluded, without any materials that the
amendments could not be given effect to. The Engineer, it was submitted,
could amend the specifications; the power concededly existed in the
agreement. He exercised that power; the contractor could not have
therefore, contrary to the contract, made a grievance on this aspect, since
additional work, forming part of the contract, could be executed. The
contractor did not challenge the exercise of such power, nor could have done
so. Therefore, after being satisfied that the work done was of a particular
quality, the quantities were indicated. Counsel urged that the contractual
rate of Rs. 65/- was applicable only to the work of laying of 2C cables which
conformed to the original scope of work. The amendments provided for rates
of the work which did not fall in the original scope, but were executed by the
contractor. It was further urged that the original contractual rate of Rs. 65/-
could not apply to overground laying of 2C cables as that rate applied to
buried underground cable laying. In overlooking these aspects, and allowing
the contractor's claim the award discloses a patent error of law; it is also
contrary to contract between the parties.
11. Learned counsel relied on the decision reported as Mcdermott
International Inc. V. Burn Standard Co. Ltd. & Ors. 2006 (2) Arb.LR. 498, to
say that the award discloses errors which can be considered as patent
illegalities, warranting interdiction by the court. Counsel submitted further
that the award of Rs. 7,50,000/- as costs even while the contractor had
CS (OS) 1476A/1999 Page 7 claimed only Rs. 3 lakhs was unreasonable. it was not preceded by any
discussion on this aspect. It was also urged that the rate of interest awarded
is too high, in any case, and cannot be sustained.
12. The contractor's contention is that a look at the relevant conditions in
the contract would show that the disputes ultimately decided in arbitration
were not "excepted" matters. The further contention was that the reason
why the corporation withheld amounts was the variation in the agreement,
after execution of the contract. The contractor's version here is that there
was no question of any decision by the Engineer; he unilaterally changed the
quantities, through the amendments. When the contractor expressed
disagreement, the corporation kept postponing any final decision, and after
holding a series of meetings, surreptitiously prepared a so called final bill,
which was furnished for the first time to it, in 1993. In these circumstances,
the disputes raised were not "excepted" from arbitration.
13. The contractor's counsel urged that the claims in arbitration were not
time barred, because the final bill itself was not prepared, and the
amendments proposed were a subject of dispute. Eventually, when the
corporation declined to accede to its (the contractor's) position, the latter
approached this court under Section 20 of the old Act, and sought for
reference, which was allowed in 1996. Counsel relied on the judgment
reported in Major I. S. Rekhi vs. DDA (1988) 2 SCC 338 for the proposition
CS (OS) 1476A/1999 Page 8 that the cause of action to approach for arbitration did not arise till the final
bill was prepared.
14. It was next urged that under Clause 37.04, if any variation in the
contractual rates resulted in reduction of consideration, the Engineer could
not impose it without consent of the contractor. It was contended that in this
case, 4C x 10 sq. mm cable and other items, for which no rates were fixed,
the corporation was bound to pay consideration - an issue which remained
outstanding after the supply of the goods and services. Instead of fixing
reasonable cost, for the supplies and services, which could have had co-
relation to the agreed rates, the corporation reduced rates, unilaterally,
twice over. The award merely held that the contractor was entitled to
amounts for such supplies and services.
15. Counsel submitted that the majority award of the arbitrators contains
reasons, which are sound in law and premised on available materials. On
application of settled principles guiding the court as to scope of judicial
intervention under Sections 30 and 33 of the Act, it has to be concluded that
there was no infirmity with the findings or the approach of the arbitrator,
calling for interference. Reliance was placed on the decisions of the Supreme
Court in Associated Engineering Co -vs- Govt of Andhra Pradesh AIR 1992 SC
232, and Rajasthan State Mines And Minerals Ltd. -vs- Eastern Engineering
Enterprises & Anr 1999 (3) Arb LR. 350. It was contended that even if the
Arbitrator commits an error of fact or law in reaching his conclusion on the
CS (OS) 1476A/1999 Page 9 disputed question submitted for his adjudication, the Court cannot interfere,
unless it is palpably capricious or manifestly erroneous.
16. The scope of a court's power interfere with an arbitration award, under
the Act has been repeatedly emphasized, by a string of decisions, starting
with Union of India -vs- A.L. Ralia Ram AIR 1963 SC 1685 down to the recent
decision in Food Corporation of India -vs- Chandu Construction 2007 (4) SCC
697. It has been ruled, thus that "misconduct" does not imply moral lapse or
perversity in findings, but to something unreasonable which would fall
outside the jurisdiction of the arbitrator. It has been further held that the
standard to be applied while considering whether the award is vitiated by
misconduct is irrationality, caprice, arbitrariness by the arbitrator, or acting
beyond the terms of the agreement (See Bhagwati Oxygen Ltd. -vs-
Hindustan Copper Ltd. 2005(6) SCC 462; Rajasthan State Mines and Minerals
Ltd. v. Eastern Engineering Enterprises and Another, (1999) 9 SCC 283). It
has been held in addition, (U.P. State Electricity Board v. Searsole Chemcials
Ltd. (2001) 3 SCC 397), that where the arbitrator had applied his mind to the
pleadings, considered the evidence adduced before him and passed an
award, the Court could not interfere by reappraising the matter as if it were
an appeal. Another test, indicated by the Supreme Court - Chandu
Construction(supra) and Bharat Coking Coal Ltd. v. M/s. Annapurna
Construction, (2003) 8 SCC 154,) is that where the arbitrator travels beyond
the contract, he acts in excess of jurisdiction, in which case, the award
becomes vulnerable and can be questioned in an appropriate Court.
CS (OS) 1476A/1999 Page 10
17. In the present case, the issue whether disputes were arbitrable, hinges
around interpretation of Clause 37.05, which is as follows:
" 37.05 In all the above cases, in the event of a disagreement as to the reasonableness of the sum, the decision of the Engineer shall prevail."
The other stipulation is Clause 33.3 which says that:
" The Engineer‟s decision and the filing of written objection thereto shall be a condition precedent to the right to request arbitration. It is the intent of the agreement that there shall be no delay in the execution of the works and the decision of the Engineers as rendered shall be promptly observed."
18. The decision in Vishwanath Sood and later, Food Corporation of India
vs. Sreekanth Transport (1999) 4 SCC 491 are authorities on what constitute
"excepted matters". In Vishwanath Sood, the condition read as follows:
"2. Compensation for delay. - The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be deemed to be essence of the contract on the part of the contractor and shall be reckoned from the fifteenth day after the date on which the order to commence the work is issued to the contractor. The work shall through out the stipulated period of the contract be proceeded with all due diligence and the contractor shall pay as compensation an amount equal to one percent, or such smaller amount as the Superintending Engineer (whose decision in writing shall be final) may decide on the amount of the estimated cost of the whole work as shown in the tender for every day that the work remains uncommenced, or unfinished, after proper dates. And further, to ensure good progress during the execution of the work, the contractor shall be bound in all cases in which the time allowed for any work exceeds, one month (save for special jobs to complete one-eight of the whole of the work before one-fourth of the whole time allowed under the contract has elapsed; three-eighth of the work, before one-half of such time has elapsed, and three fourth of the work, before three-
fourth of such time has elapsed). However, for special jobs if a time schedule has been submitted by the contractor and the same has been accepted by the Engineer-in-charge, the contractor shall comply with the said time schedule. In the event of the contractor failing to comply
CS (OS) 1476A/1999 Page 11 with this condition, he shall be liable to pay as compensation and amount equal to one per cent or such smaller amount as the Superintending Engineer (whose decision in writing shall be final) may decide on the said estimated cost of the whole for every day that the due quantity of work remains incomplete; provided always that the entire amount of compensation to be paid under the provision of this clause shall not exceed 10 per cent, on the estimated cost of the work as shown in the tender."
The terms of Clause 2 unambiguously envisioned that the determination of
compensation for the delay in execution of the work was only by the
Superintending Engineer and specifically mentions that the decision of the
Superintending Engineer "in writing shall be final." In this case, the
conditions concerned, i.e. Clauses 37.05 and 33.3 do not invest finality of a
similar kind. The latter merely outlines a mechanism for submission to
arbitration; the former states that the views of the Executive Engineer about
the price would prevail. Yet, these do not preclude submission of the dispute,
arising from disagreement to arbitration. Moreover, in the facts of this case,
the corporation was unable to show when, and what was the decision,
rendered by the said official, became final, and precluded arbitration. The
Engineer proposed amendments, after completion of contract; which were
never agreed to; the parties thereafter kept negotiating, and concededly
recorded minutes of meeting. The record does not reflect any final decision
by the Engineer, of the kind argued by the corporation, which inhibited
reference to arbitration. Therefore, it is held that the award does not disclose
any infirmity vis-à-vis findings concerning arbitrability of the disputes. They
were not "excepted" matters.
CS (OS) 1476A/1999 Page 12
19. Next, the issue of limitation. Here, the corporation argues that the
contractor's claims were time barred, since the earliest point in time, when it
was possible to refer the disputes, was in 1989; the court was approached in
1994. The contractor, on the other hand, counters by saying that the
question of downward revision of cost, contrary to agreement, was being
negotiated for a long time; eventually, on 13th April, 1993, the corporation
indicated its final opinion that the rates proposed through the two
amendments were not being revised. Till that time, the contractor could not
have visualized that a dispute would arise; it is also urged that the final bill
was furnished to the contractor in that meeting of 13th April, 1993, after
which reference was sought, by approaching the court under Section 20.
20. The corporation had relied on the ruling in J.C. Budhiraja (supra), where
no doubt it was held that if a party merely says, without admitting liability,
that it would examine the claim or the accounts, it may not amount to
acknowledgement and that an acknowledgement of liability is one which
consciously admits a party's liability to pay or admit his intention to pay the
debt. Yet, the facts of this case are different here. The final bill was made
sometime in 1992; the minutes of meeting show that there was no
agreement on the question of cost of the services, or the variations
indicated, in 1989, till the corporation expressed disinclination, finally on 13th
April, 1993. In such a case, the ruling of the Supreme Court in Major I. S.
Rekhi is apt. In that case, the contention about lack of arbitrable dispute, in
the absence of a final bill was upheld, in the following words:
CS (OS) 1476A/1999 Page 13 "...But in order to be entitled to ask for a reference under Section 20 of the Act there must not only be an entitlement to money but there must be a difference or dispute. It is true that on completion of the work, a right to get payment would normally arise but where the final bills as in this case have not been prepared as appears from the record and when the assertion of the claim was made on February 28, 1983 and there was non payment, the cause of action arose from that date, that is to say, February 28, 1983. It is also true that a party cannot postpone the accrual of cause of action by writing reminders or sending reminders but, where the bill had not been finally prepared, the claim made by a claimant is the accrual of the cause of action. A dispute arises where there is a claim and a denial and repudiation of the claim. The existence of dispute is essential for appointment of an Arbitrator under Section 8 or a reference under Section 20 of the Act. There should be dispute and there can only be a dispute when a claim is asserted by one party and denial by the other on whatever grounds. Mere failure or inaction to pay does not lead to the inference of the existence of dispute. Dispute entails a positive element and assertion of denial, not merely inaction to accede to a claim or a request. Whether in a particular case a dispute has arisen or not has to be found out from the facts and circumstances of the case."
The above ruling has been followed in Pandit Munshi Ram & Associates (Pvt.)
Ltd.,V. Delhi Development Authority & Anr., 2002 (Supp) Arb. LR 659 -DEL; it
has also been approved in J. C. Budhraja. In Hari Shankar Singhania & Others
V. Gaur Hari Singhania 2006 (2) Arb.LR. 1 (SC), following Rekhi it was held
that:
"In the instant case, correspondence was not merely in the nature of reminders but also instruments to resolve the matter and amicably negotiate. Therefore, when the negotiations were taking place between the parties by way of various letters written by both parties the right to apply can be said to accrue when it becomes necessary to apply, that is to say when a dispute in fact arose. Furthermore, the respondent did not ever dispute the claim of the appellants."
21. Having regard to the above position in law, it is held that the claims in
this case were not time barred, since the final bill was prepared in 1992, and
CS (OS) 1476A/1999 Page 14 the disagreement which was referred to arbitration, took place on 13th April,
1993. The award therefore, does not show any jurisdictional infirmity, calling
for interference by this court.
22. As far as the merits are concerned, the court does not discern any
scope for holding that the award discloses any perversity in approach,
caprice, or unreasonableness. The majority award is a fairly reasoned
document. It has dealt with each contention raised by the parties, who had
submitted written notes of arguments, besides voluminous documents. The
substratum of reasoning is that the amendments were made after
performance of the contract; they reduced the amounts agreed, unilaterally.
The corporation's actions were held to be beyond the scope of the contract,
since Clause 37.04 visualized consensual change, particularly in reduction of
the value of the contract. The contractor here was asked to perform jobs
which were unspelt in the contract and yet, by two amendments, the value
was progressively reduced. The arbitrators, not unreasonably, held that this
was unjustified. This court is of opinion that no error of law, or fact, or
infirmity in the approach of the arbitrators, can be discerned here. The court
cannot fault the award, merely because it can arrive at contrary findings, on
a different process of reasoning; such conclusions would amount to
impermissible appellate review, clearly beyond the scope of Sections 30 and
33.
CS (OS) 1476A/1999 Page 15
23. As far as the grievance of the corporation regarding costs are
concerned, the court is of opinion that the approach of the arbitrators cannot
be supported. The contractor had claimed Rs. 3 lakh towards cost of
arbitrator. The additional amount of Rs. 5 lakhs appears to have been
claimed during the course of submissions, and finds mention in Volume D-1.
The addition is towards counsel's fee; there is no discussion or supportive
material by the majority award, on this head. The award, grants Rs.
7,50,000/- cannot therefore, be sustained; it is set aside, to the extent it
exceeds Rs. 3,00,000/-.
24. The majority award grants Rs. 4,05,212/60 to the claimant, for the
erection portion, and Rs. 1,79,029/41 for the supply portion (aggregating Rs.
5,84,242/01). After adjusting recoveries, the amount admissible was held to
be Rs. 5,55,419/27. An amount of Rs. 1,48,564/- towards refund was also
allowed. The award allowed 18% interest p.a compounded annually, on the
sums granted; a specific amount was also indicated in the award. Such
interest, for the entire period, in the opinion of the court, is unsupportable,
having regard to bankers depressed prime lending rates in the mid 1990's. In
the circumstances, the court hereby modifies the interest to 15% simple
interest, from 1-6-1988 to 31-5-1993 and thereafter, from 1-6-1993 till
award, and future interest, till payment at 10% per annum, (simple interest).
25. In view of the above reasons, IA 1476-A/1999 has to partly succeed.
The costs, to the extent it is in excess of Rs. 3,00,000/- is set aside. The
CS (OS) 1476A/1999 Page 16 award of interest too, is modified, to the extent indicated in the preceding
paragraph. The award is made rule of court, in these terms; the suit and
application are decreed accordingly. No costs.
DATE: 8th September, 2008 S. RAVINDRA BHAT, J CS (OS) 1476A/1999 Page 17
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!