Citation : 2008 Latest Caselaw 1857 Del
Judgement Date : 21 October, 2008
CS(OS) No.944/2001 Page No.1
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) NO. 944 OF 2001
% Date of Decision : 21st October, 2008.
M/S. T.T. LIMITED .... Plaintiff.
Through Mr. Rajiv Bansal, Mr.Harshit
Agarwal, Mr.Prashant Mehra, Advocates.
VERSUS
INDUSTRIAL FINANCE CORPORATION
OF INDIA LTD. .... Defendants.
Through Mr. Sandeep Sethi, Sr.Advocate with
Mr.Abhishek Kumar, Advocate.
CORAM:
HON'BLE MR. JUSTICE SANJIV KHANNA
1.
Whether Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not ? YES
3. Whether the judgment should be reported
in the Digest ? YES
SANJIV KHANNA, J:
1. Industrial Finance Corporation of India Limited (hereinafter
referred to as IFCI, or defendant for short)- had extended loan facility
to M/s. T.T. Ltd.-plaintiff vide four separate "term" loan agreements
for setting up of a new spinning unit. The said four loan agreements
are as under:-
Loan Scheme Agreement Amount Rate of Loan
date sanctioned interest Disbursed
(p.a.)
Project Finance 30.10.92 Rs.269.00 19.12% Rs.242.00
CS(OS) No.944/2001 Page No.2
Scheme lakhs Lakhs
Equipment 10.09.92 Rs.350.00 19.61% Rs.266.34
Finance Scheme lakhs lakhs
Equipment Credit 14.01.93 Rs.500.00 22.00% Rs.469.00
Scheme lakhs lakhs
Foreign Currency 10.09.92 DM1303,500 9.5% DM
Loan under (Equivalent to 1,234,115.
Project Finance Rs.231 lakhs) 45
Scheme
(in Deutsche
Mark)
2. Plaintiff by letter dated 11th December, 1996 (Exhibit P-2)
expressed concern at the high interest rate being charged and gave
three proposals to the defendant including proposal for pre payment
with a request that pre payment charges may be waived. This was
followed by letters dated 11th February, 1997 (Exhibit P-3), 24th May,
1997 (Exhibit P-4), 14th June, 1997 (Exhibit P-5&6) and 24th July,
1997 (Exhibit P-7) written by plaintiff to the defendant. In the letter
dated 24th July, 1997 (Exhibit P-7) the defendant was asked to inform
the plaintiff the total amount payable towards principal and interest so
that pre payment of the loans could be made. Similar request was
again made by the plaintiff by letter dated 31st July, 1997 (Exhibit P-
8), wherein it was also stated that necessary arrangement for pre
payment with Oriental Bank of Commerce required a letter from the
defendant.
3. Defendant by letter dated 8th August, 1997 (Exhibit P-9)
informed the plaintiff that they were agreeable to their proposal for
pre payment of outstanding term loans and the plaintiff would be CS(OS) No.944/2001 Page No.3
liable to pay pre interest and other charges and premium
calculated upto the cut of date as per prevailing standard norms
set by financial institutions. The total amount would be advised
separately. The charge of the defendant on the assets of the
plaintiff would be released after realization of the entire amount.
4. By four separate letters dated 11th September, 1997 (exhibit
P.10-13), the plaintiff made specific reference to letter dated 8th
August, 1997 (Exhibit P-9) and paid amount of Rs.1,22,75,276/-
towards Equipment Credit Scheme, Rs.1,77,59,857/- towards Project
Finance Scheme, Rs.1,93,55,646/- towards Foreign Currency Loan
under Project Finance Scheme and Rs.1,94,54,896/- towards
Equipment Finance Scheme. Along with the said letters the plaintiff
had enclosed copy of calculations made by them for payment of the
said amount. Thereafter, the plaintiff wrote letter dated 15th
September, 1999 (Exhibit P-14) informing the defendant about
payments made by them and received by the defendant in their office
on 12th September, 1997. The cheque/payments were received and
encashed by the defendant.
5. By letter dated 15th September, 1997 (Exhibit P-15) the
defendant informed the plaintiff that as per their calculations, the total
pre payment amount up to 12th September, 1997, i.e. the date of
payment, was Rs. 7,39,06,561/- and the total payment made by the
plaintiff was short by Rs.50,60,864/-. Along with this letter, calculation CS(OS) No.944/2001 Page No.4
sheets were enclosed.
6. Plaintiff by their letter dated 18th September, 1997 (Exhibit P-
16) replied stating, inter alia, that the defendant had claimed Rs.
53,75,350/- towards pre-payment premium for the four loans. It was
also stated that interest calculations had been made by defendant
upto 31st August, 1997 whereas payment had been made by them on
12th September, 1997 and therefore revised calculation charts were
required to be prepared. Comments were also made on calculation of
pre-payment premium under Project Finance Scheme, Equipment
Finance Scheme and Foreign Currency Loan under Project Finance
Scheme. With regard to Indian rupee loans under Project Finance
Scheme and Equipment Finance Scheme, it was stated that spread
of 2.5% was added for the purpose of calculations of the loan rate
mentioned in the document, therefore 2.5 % should be also added to
the Prime Lending Rate (PLR) to arrive at net loss. With regard to
Foreign Currency Loan, it was stated that the document rate and the
current lending rate of foreign currency loans in Deutsche Mark (DM)
was the same and the current PLR was higher and therefore nothing
was payable. If at all the plaintiff was entitled to refund in view of the
higher PLR. These aspects have been considered later in the
judgment.
7. Plaintiff along with the letter dated 18th September, 2008
(Exhibit P-16), enclosed a cheque of Rs.4,04,265/- as the net pre
payment premium payable by them and the defendant was requested CS(OS) No.944/2001 Page No.5
to issue No Due Certificate. Similar request for issue of No Due
Certificate was again made by letters dated 3rd October, 1997 (Exhibit
P-17), 17th October, 1997 (Exhibit P-18), 3rd November, 1997 (Exhibit
P-19), and further communications.
8. Defendant by their letter dated 3rd November, 1997 (Exhibit P-
20) referred to letter dated 18th September, 1997 written by the
plaintiff and informed them that plaintiff‟s request for spread over of
2.5% above the PLR for the purpose of calculation of differential loss
cannot be accepted and accordingly the plaintiff was asked to make
payment of Rs.53,03,252/-.
9. By another communication dated 20th March, 1998 (Exhibit P-
21), the defendant informed the plaintiff that the revised calculation of
pre-payment premium works out to Rs.51,49,392/-. It was further
stated that the difference between DM rate of Rs.20.58 as on 12th
September, 1997 and the actual rate prevailing on the date of
realization of the cheque would be payable by the plaintiff. Again by
letter dated 20th April, 1997 (Exhibit P-24) the defendant submitted
that the prepayment premium charges were based upon standard
norms set by financial institutions and policies and therefore cannot
be changed. It was further stated as under:-
"Please note that the payment as informed to you on the basis of cut off date i.e. 12.9.97 has not been received in full inspite of our repeated requests. Since the said offer of prepayment has not been concluded, which may be treated as withdrawn and the said contract of CS(OS) No.944/2001 Page No.6
prepayment become null and void. Kindly further note that the amount received is lying pending "on account" for adjustment to the respective loan facility."
10. Plaintiff thereafter filed Civil Writ Petition No. 2497/1998.
On the interim application, plaintiff was asked to furnish bank
guarantee to the tune of Rs.52 lakhs and thereupon the defendant
was asked to issue No Due Certificate. However, the said Writ
Petition itself was dismissed by judgment dated 25th January, 2000,
inter alia, holding that the jurisdiction of the Court under Article 226 in
contractual matters was circumscribed and limited and the defendant
had raised their demand as per discretionary terms mentioned in the
loan agreements. Operation of the judgment was however stayed by
learned Judge to enable the plaintiff to file an appeal.
11. Letters Patent Appeal No. 68/2000 filed by the plaintiff
was disposed of by Order dated 31st August, 2000 recording, inter
alia, that the plaintiff herein was "withdrawing the writ petition" and
would approach the defendant herein by means of a representation
for grant of benefit including waiver of interest and prepayment
premium. Consequently, the writ petition was dismissed as withdrawn
and the appeal, it was held, "did not survive" and "was disposed of as
such". Plaintiff had stated that they would deposit Rs.40 lakhs with
the defendant herein within 24 hours and Rs.12 lakhs in the Court
and the deposit made would be subject to the decision taken by the Board
of the defendant. In case representation of the plaintiff was rejected, CS(OS) No.944/2001 Page No.7
Rs. 12 lakhs deposited in the Court shall be handed over to the
defendant.
12. On 19th September, 2000, the defendant rejected the
representation of the plaintiff for waiver of interest and prepayment
premium. Thereafter, an application was filed before the Division
Bench, which was disposed of on 30th October, 2000 issuing direction
to the defendant to furnish Form Nos. 13 and 17 of the Companies
(Central Government General Rules & Forms) simultaneously with
receipt of Rs.12 lakhs from the Court. Defendant was also directed to
furnish copy of the statement of accounts.
13. Thereupon, the plaintiff has filed the present Suit for
recovery of Rs.14,17,000/-, Rs.11,56,000/-, Rs.22,19,000/- and
Rs.1,60,000/- (total Rs.49,52,000/-) on account of excess payment
made under Equipment Finance Scheme, Equipment Credit Scheme
and Foreign Currency Loans respectively and Rs.1,60,000/-, it is
claimed is excess amount lying with the defendant-IFCI.
14. Defendant in their written statement has raised the plea of
estoppel and has also pointed out that the prepayment premiums had
been calculated on the basis of interest loss i.e. difference between
the document rate of interest and the prevailing prime interest lending
rate (PLR) and the amount so calculated had been discounted at the
prevailing interest lending rate(PLR). Similarly, with regard to the
Foreign Currency Loan, six months LIBOR rate has been taken for
calculating loss of interest. It is also stated that loss of interest was CS(OS) No.944/2001 Page No.8
caused when loans were prepaid. A prepayment loss was caused
due to parting of funds and as defendant was liable to pay interest on
their borrowings. Defendant had made their own arrangement and
therefore prepayment premium was justified.
15. On the basis of the pleadings of the parties, by Order
dated 8th July, 2004, issues were framed. But these were
subsequently modified on 9th July, 2004 with additional four issues.
The modified issues read as under:-
"1. Whether any cause of action to file the present suit exists in favour of the plaintiff and against the defendant? (OPD).
2. Whether the plaintiff has repaid the entire liability under the Loan agreements entered into between the parties? (OPP)
3. Whether the plaintiff is stopped from challenging the terms and conditions of a concluded contract which has been acted upon and under which benefits have been availed of by the plaintiff? (OPD)
4.Whether the defendant could adopt different criteria for charging prepayment premium in respect of Rupees Loans disbursed all most contemporaneously under different schemes of financing to the same industrial unit? (OPD)
5. Whether the premium charged by the defendant on prepayment of loan availed by the plaintiff under the Project Finance Scheme Equipment Finance Scheme and Foreign Currency Loan of the defendant is legal being in terms of the contract between the parties? (OPD)
6. Whether the plaintiff is entitled to a sum of Rs.55,46,000/- as detailed in paragraph 52 of the plaint? (OPP)
7. Whether the plaintiff is entitled to any interest on the amount of Rs.55,46,000/- if so at what rate and for what period? (OPP)
8.Relief."
CS(OS) No.944/2001 Page No.9
16. Plaintiff has adduced oral evidence of PW-1 Mr.Sunil
Bhanot, Company Secretary of the plaintiff and on behalf of the
defendant, Mr. S.K. Mazumdar, Deputy Legal Manager (Law)/PW-1
has given oral evidence. Both the witnesses have been cross
examined.
17. Issue no.1 as framed is rather vague and not specific.
Defendant in the written statement has raised preliminary objection
to maintainability of the suit on the ground of estoppel. However, on
that aspect a separate issue being issue no.3 stands framed.
18. During the course of arguments, learned counsel for the
defendant had submitted that the orders passed in the writ petition
and the Letters Patent Appeal being judgment dated 25th January,
2000 and Order dated 31st August, 2000 operate as res judicata. Plea
of res judicata has not been specifically raised in the written
statement. Plea of res judicata requires reference to earlier
proceedings including pleadings and orders passed in the earlier
proceedings. In most cases plea of res judicata is one of law as well
as facts. Normally, therefore, a party should not be permitted to raise
a plea of res judicata without specific contention in the pleadings, as
the other side may be well taken by surprise and denied opportunity
of a fair trial. Moreover, for judgment dated 25th January, 2000
passed in Writ Petition No. 2497/1998 to apply as res judicata, the CS(OS) No.944/2001 Page No.10
same should have attained finality. By Order dated 31st August, 2000
passed in LPA No. 68/2000, the Writ Petition was itself dismissed as
withdrawn and therefore it was observed that the appeal does not
survive and was disposed of. The appellate court did not go into the
merits but had allowed the plaintiff herein to withdraw the writ petition
as if the same was never filed. The plea of res judicata therefore even
on merits has no force and is liable to be rejected. Issue no.1 is
accordingly decided in favour of the plaintiff and against the
defendant.
ISSUE NOS. 2, 4-6
19. Clause 2.5 of Equipment Credit Scheme (Exhibit D-39) is
a specific clause relating to premature payment. The said Clause
reads as under :-
"2.5 Premature repayment If, at the request of the Company, IFCI agrees to accept premature repayment of the Cost of the Equipment, the Company shall, immediately upon such acceptance, pay/repay:
(a) the Cost of the Equipment;
(b) Interest on the Cost of the Equipment at the rate of @ 22% per annum calculated from the due date of last instalment paid till the date of payment of the Cost of the Equipment;
(c) Premium at the following percentage of the Cost of the Equipment:
i) In the event of premature repayment is made by the Company before the expire of the period of one year from the date of payment of the Cost of the Equipment by IFCI, at 5%;
ii) In the event the premature repayment is made by the Company after the expiry of the period of one year but before the expiry of two years from the date of payment of the Cost of the Equipment by CS(OS) No.944/2001 Page No.11
IFCI, at 3%;
iii) In the event the premature repayment is made by the Company after the expiry of two years from the date of payment of the Cost of the Equipment by IFCI, at 1%;
(d) All other monies due and payable under or pursuant to this Agreement.
(e) Disbursements made pending creation of final security as stipulated in clause 3 hereof shall from the date of first disbursement carry further interest at a rate of 1% p.a. till creation of final security."
20. There is no dispute between the plaintiff and the
defendant that as far as Equipment Credit Scheme Agreement is
concerned, the said Clause will apply and accordingly the plaintiff is
liable to pay premature prepayment premium in terms thereof i.e. @
1% of the cost of the equipment as per Clause 2.5(c) and (d).
Payment of premium under the Equipment Credit Scheme Agreement
is not subject matter of the present Suit.
21. Similar clause does not exist in the other three loan
agreements. The dispute between the parties relates to the other
three agreements.
22. Relevant clauses in the Equipment Finance Scheme
(Exhibit D-5) being Clause no.4.8 and Project Finance Scheme
(Exhibit D-24) being Clause no. 2.2A, read as under:-
"Equipment Finance Scheme :
Section 4.8 PREMATURE REPAYMENT
The Borrower shall not prepay the outstanding principal amounts of the Loan in full or in part, before the due dates except (after the conversion right is exercised in full, or has lapsed and*) to be CS(OS) No.944/2001 Page No.12
deleted if conversion clause not applicable after obtaining the prior approval of IFCI (which may be granted conditionally).
Project Finance Scheme :
2.2 A The Borrower shall not repay the loan or any part thereof before the due date except with the prior written approval of the Lenders on such terms and conditions as may be stipulated by the Lenders."
23. In other words, the two Clauses stipulate that the plaintiff
shall not repay the loan or part thereof before the due date except
with the prior approval of the defendant and would be subject to
terms and conditions stipulated by the defendant. It is the case of the
plaintiff that the above Clauses are uncertain and therefore hit by
Section 29 of the Contract Act, 1872 (hereinafter referred to as the
Act, for short). The contention of the defendant is that the above
clauses are not uncertain or vague and are to be interpreted in
harmony with other provisions of the contract.
24. Two Clauses quoted above are in the nature of an option.
It gives liberty, to the borrower, to make a request for prepayment of
loan. The Clauses do not specify the amount of premium payable or
conditions which can be imposed by the defendant when a request
for prepayment is made. It gives wide discretion to the defendant to
unilaterally fix terms and conditions of the pre-payment. The Clauses
do not even stipulate that the terms and conditions would be
reasonable, fair and as per common practice. It does not provide for
machinery for ascertainment of the amount paid. The two Clauses CS(OS) No.944/2001 Page No.13
merely permit the plaintiff to make a request for prepayment and
thereupon the defendant has right to fix terms and communicate their
proposal or offer to the plaintiff. The plaintiff may accept or reject the
offer or terms of prepayment. When a request is made, the plaintiff or
the borrower invites an offer from the lender, i.e.; the borrower.
Clauses quoted above permit the plaintiff to make a request and
invite the defendant to make an offer.
25. The two Clauses, therefore, do not create an enforceable
contract, but, provide that the defendant can examine request for pre-
payment of loan but on terms and conditions to be fixed by them. A
concluded contract will come into existence once the defendant
makes an offer with pre-payment terms and the same is accepted by
the plaintiff. The Clauses give liberty to the plaintiff to make a request
to the defendant to make a proposal or offer as defined in Section
2(a) of the Act. After examining the request, the defendant has a right
to make a proposal under Section 2(a) of the Act and the plaintiff has
option to accept the said proposal as provided under Section 2(b) of
the Act and upon acceptance thereof a binding agreement would
come into existence as defined in Section 2(j) of the Act. In view of
the above discussion, reference to Section 29 of the Act in
connection with the two Clauses mentioned above by both the parties
is entirely misplaced and irrelevant. Clauses by themselves do not
create a binding contract or agreement under Section 2(j) of the Act
for prepayment of premium. Both sides have misconstrued the two CS(OS) No.944/2001 Page No.14
Clauses. The two Clauses create no absolute or legal obligation for
prepayment of premium. A chance, possibility or potentiality of an
obligation is distinct from an absolute obligation, which is not
conditional and immediately legally enforceable. The question
whether it was mandatory for the defendant to make an offer on the
request of the plaintiff under the two clauses is not required to be
examined, for the request was accepted and offer was made by the
defendant to the plaintiff. For purpose of record, law recognizes
undertaking to make an offer as in cases of pre-emption.
26. In view of the above facts, we have to now examine
whether the conduct of the parties and exchange of letters has
resulted in formation of a concluded and enforceable contract for pre
payment and prepayment premium.
27. Plaintiff by their letters marked Exhibit P-2 to P-8 had
requested the defendant to examine their request for prepayment of
the loan. The request was considered and proposal was sent by the
defendant to the plaintiff by their letter dated 8th August, 1997 (Exhibit
P-9). Relevant portion of the said letter reads as under:-
"In this connection, we are agreeable to your proposal of prepayment of our outstanding term loans. Accordingly, you are requested to arrange funds for payment which includes principal, interest, other charges and premium, which has been calculated upto the cut-off date i.e. 14th August, 1997 as per our prevailing standard norms, set by the CS(OS) No.944/2001 Page No.15
financial institutions. The total amount payable will be advised separately. We further inform that any delay in repayment of outstanding term loans shall lead to revised calculations of premium etc."
(emphasis supplied)
28. The letter (Exhibit P-9) stipulated that the plaintiff would
be liable to pay principal, interest, other charges and premium as per
the prevailing standard norms, set by the financial institutions. The
said letter constitutes a „proposal‟ as defined in Section 2(a) of the
Act.
29. The proposal was accepted by the plaintiff by their four
letters dated 11th September, 1997 (Exhibits P-10 to P-13) and the
same resulted in an enforceable contract as defined in Section 2(j) of
the Act. In letters dated Exhibits P-10 to P-13, it is stated as under:-
"SUB : PRE-PAYMENT OF IFCI TERM LOAN (. . . .) Please refer to your letter ref.
no.DRO/GROUP-V/Proj./97-6923 dated August 8, 1997 regarding our proposal to pre- pay all our outstanding loans.
Accordingly, we enclosed herewith our Pay Order No. ...... Dt. .... for Rs...... (Rupees......) drawn on ...... towards payment of outstanding .... loan amount including interest payable thereon as per details attached.
You are requested to acknowledge receipt of the above payments and let us know, if any balance amount is still payable by us. You are also requested to provide us the details of the balance amount payable, if any. "
Thus both parties have entered into an enforceable agreement to CS(OS) No.944/2001 Page No.16
pay principal, interest, other charges and premium as per standard
norms set up by the financial institutions.
30. It is not the case of the parties that there was any
difficulty or uncertainty with regard to the principal amount and
interest due thereon upto the cut of date. To this extent there is no
dispute. It is the contention of the plaintiff that the stipulation with
regard to the payment of premium and other charges as per
prevailing standard norms set up by the financial institutions is
indefinite and uncertain and therefore violates Section 29 of the Act.
31. A contract is bad for uncertainty if it is incapable of
being made certain. Where a criteria or mechanism has been fixed by
the parties and it is possible to ascertain and determine the amount
payable as per the criteria/mechanism fixed by the parties, an
agreement is not void for lack of uncertainty. An agreement which
lacks clarity but is capable of definite and precise meaning
attributable to the parties is not bad for uncertainty. Maxim id certum
est quod certum reddi potest that which is sufficiently certain can
be made certain, is applicable. If on a fair reading of a term of an
agreement, the intention of the parties can be ascertained, courts will
be reluctant to declare the contract to be void on the ground of
uncertainty.
32. Illustration „e‟ to Section 29 of the Act provides that even
when two parties to the contract have not fixed the price and the
same is to be fixed by a third party, the agreement is not void for CS(OS) No.944/2001 Page No.17
uncertainty as the third party has the right to fix the price. The said
illustration will apply to the facts of the present case as letter dated 8 th
August, 1997 (Exhibit P-9) and the acceptance letters dated 11th
September, 1997 (Exhibits P-10 to P-13) make reference to the
prepayment premium which is chargeable as per the prevailing
standard norms set up by financial institutions. The prepayment
premium can be ascertained with reference to the prevailing standard
norms set up by financial institutions, the basis mentioned in the letter
dated 8th August, 1997 (Exhibit P-9).
33. Courts are normally reluctant to strike down commercial
contracts on the ground of uncertainty unless the terms cannot be
ascertained. In commercial contracts a narrow pedantic approach is
not warranted and a fair and a broad approach is adopted. The
contract and the terms thereof have to be interpreted in a reasonable
manner. Difficulties in ascertaining the term does not make the
contract fatal and is not synonymous with uncertainty. Even when,
there are gaps these can be bridged and filled up with reference to
previous course of dealings between the parties, usual customs and
practice and what is considered to be reasonable unless contractual
terms are to the contrary or the exercise shall result in formation of a
new contract or bar under Section 93 of the Evidence Act applies.
Courts normally protect bargains and do not destroy them. It will be
appropriate to refer to the decision of the Madhya Pradesh High Court in M/s.
Uttam Singh Duggal and Company versus Hindustan Steel Ltd.
CS(OS) No.944/2001 Page No.18
reported in AIR 1982 MP 206, wherein it has been stated :-
"10. Solemn contracts entered into between the parties are not to be readily declared invalid for uncertainty as to certain terms, at any rate in those cases where the parties have acted upon the contracts which have been fully executed. In construing a contract the object of the Court is to do justice between the parties and the Court will do its best, if satisfied that there was an ascertainable and determinate intention to contract, to give effect to that intention, looking at substance and not mere form. It will not be deterred by mere difficulties of interpretation. Difficulty is not synonymous with ambiguity so long as any definite meaning can be extracted. (See Scammel v. Ouston 1941 (1) All. ER 14 at p.25). As observed by a Full Bench of this Court: "Documents embodying a business agreement should be construed fairly and broadly and there must be implied in such documents a term which will give such business efficacy to the transaction as must have been intended by the parties. No doubt, one cannot add to a contract an implied term inconsistent with or which contradicts the express terms of the contract. But in a suitable case one ca imply a term if it is necessary to give it business efficacy." (Gulab Chand v. Kudilal, AIR 1959 Madh Pra 151) (at p.162) (FB). Lord Denning has expressed or imposed a term whenever it is reasonable to do so in order to do what is fair and just between the parties (see, The Discipline of Law, page 37). He expressed this view in the case of Liverpool City Council v.
Irwin, (1975) 3 All ER 658. In appeal, however, the House of Lords though agreeing with the conclusion of Lord Denning did not accept the broad proposition that the Court is entitled to read in by implication all reasonable terms. The House of Lords observed that terms may be implied on the basis of established usage or for giving business efficacy to the contracts or on the ground of necessity. ((1976) 2 All ER 39 (HL) at pp.43,44). A reference in this connection may also be made to Section 29 of the Contract Act which says that agreements, the meaning of which is not certain, or capable of being made CS(OS) No.944/2001 Page No.19
certain, are void. A contract can become void under the section only when its terms cannot be made certain. Mere vagueness or uncertainty which can be removed by proper interpretation cannot make a contract void. In dealing with commercial and business contracts which have been acted upon by the parties, the Court should be very slow in finding defects and to reject them as meaningless. This should be done only in extreme cases."
Supreme Court in M/s. D.Gobind Ram versus M/s. Shayma K. & Company reported in AIR 1961 SC 1285 had held that the words "force majeur" are very wide, ambiguous and therefore uncertain, but when prefixed with the word "usual" are capable of definite meaning and this ensues certainty to the contract. Clause stipulating that the parties will be governed by "usual force majeure" is specific and capable of being made certain and not hit by Section 29 of the Act.
34. Conduct of the parties in form of exchange of
correspondence specially letter dated 8th August, 1997 (Exhibit P-9)
and letters dated 11th September, 1997 (Exhibits P-10 to P-13) show
that the parties wanted to enter into a binding legal relationship.
There was no dispute that pre-payment premium would be payable.
There was also no dispute that the premium payable would be as per
standard norms set up by financial institutions. There was no
indefiniteness of the nature which would make the contract vague
and indefinite. It cannot be said that the terms settled between the
parties cannot be ascertained.
35. I may also note that the parties have acted on the basis
of the two letters, exhibit P-9 and exhibits P-10 to P-14 and the CS(OS) No.944/2001 Page No.20
contract was performed with principal and interest amount being paid.
In fact as per the defendant, the entire contract has been performed
and therefore there is no question of refund. The terms set out in the
letter dated 8th August, 1997 (Exhibit P-9) was acted upon. In these
circumstances, it would be unfair and inequitable to set at naught the
entire bargain. This is not in the interest of the plaintiff also. To use a
popular expression "eggs cannot be unscrambled". Far greater
latitude and assistance to uphold commercial bargain is given by the
courts where agreements have been executed. In some cases of
executed contracts, even principles of fairness and reasonableness
or quantum meruit have been applied to determine and decide
consideration payable. Court has to approach the agreement in
question to effectuate the same and uphold the bargain and not to
interpret the terms with astuteness to find faults and defects. The
parties were ad idem on the terms of the contract including the
question of payment of prepayment premium. The consideration
mentioned in the contract in terms of the letter is ascertainable and
therefore the plaintiff is liable to pay prepayment premium as per the
prevailing standard norms set up by the financial institutions.
36. The above reasoning will equally apply to the Foreign
Currency Loan Agreement and the question that there was no
stipulation or a clause in the original contract for payment of
prepayment premium is rendered irrelevant and inconsequential in
view of the subsequent letters and correspondence exchanged CS(OS) No.944/2001 Page No.21
between the parties i.e. letter dated 8th August, 1997 (Exhibit P-9)
and letters dated 11th September, 1997 (Exhibits P-10 to P-13), as
per which the plaintiff had agreed to pay prepayment premium as per
the prevailing standard norms set up by the financial institutions.
37. Learned counsel for the parties had drawn my attention to
Clauses 4.4, 4.8A of Article IV and Section 7.3A(iii) of Article VII of
Foreign Currency Loan Agreement. These Clauses, read as under:
"Section 4.4 REPAYMENT
(i) The Lenders may, in suitable circumstances, revise, vary or postpone the repayment of the principal amounts of the Loans or the balance outstanding for the time being or any instalment(s) of the said principal amounts of the Loans or any part thereof upon such terms and conditions as may be decided by the Lenders.
"Section 4.8 APPROPRIATION OF PAYMENTS
(a) Unless otherwise agreed to by the Lenders any
payment due and payable under the Loan Agreement and made by the Borrower shall be appropriated towards such dues in the following order viz.-
(i) Premium on prepayment;"
"Section 7.3 GENERAL COVENANTS
(A) Without the prior approval of the Lead Institution, the Borrower shall not
(i) NEW PROJECT
Undertake any new project, diversification, modernization or substantial expansion of Project described herein. The word substantial shall have the same meaning as under the Industries (Development and Regulation) Act, 1951.
(ii) LOANS AND DEBENTURES Issue any debentures, raise any loans, accept deposits CS(OS) No.944/2001 Page No.22
from public, issue equity or preference capital, change its capital structure or create any charge on its assets or give any guarantees. This provision shall not apply to normal trade guarantees or temporary loans and advances granted to staff or contractors or suppliers in the ordinary course of business or to raising of unsecured loans, overdrafts, cash credit or other facilities from banks in the ordinary course of business.
(iii) PREMATURE REPAYMENT Prepay any loan availed of by it from any other party."
38. Section/clause 4.4 gives power to the lender i.e. the defendant
to revise, vary or postpone the payment of the loan amount upon
terms and conditions as would be decided by the lender. Section 4.8
gives power to the lender to decide prepayment premium and
appropriate the amount towards the same. The lender, i.e. the
defendant had exercised the said right in terms of letter dated 8th
August, 1997 (Exhibit P-9). Clause 7.3A(iii) has no application to the
facts of the present case. It imposes an embargo on the plaintiff to
prepay any loan availed of by it from any third party. This is clear from
the use of the words "other party" in the said Section. The intention
behind the Section being that the plaintiff should not repay any loan
taken from any third party as it would or may have implication or
adverse effect on the payment of the loan taken by the plaintiff from
the defendant.
39. The contention raised by the defendant in the written
statement that the plaintiff had on his own accord deposited
payments vide four separate letters dated 11th September, 1997 CS(OS) No.944/2001 Page No.23
(Exhibits P-10 to P-13) is not correct. Exhibit P-11 has an
endorsement of the officer on behalf of the defendant who had
received the said letter that the pay orders were accepted subject to
approval and the balance amount due. This obviously had reference
to payment of the prepayment premium in terms of letter dated 8th
August, 1997 (Exhibit P-9). Letter dated 8th August, 1997 (Exhibit P-
9) constitutes an „offer‟, under the Act. In law, the promisor while
making an offer is not required to compute and calculate total
consideration. Terms of the contract including the consideration
should be certain and it is not necessary that the same should be
quantified. Therefore, letter dated 8th August, 1997 (Exhibit P-9) and
thereafter payments made in terms of the said letter by letters dated
11th September, 1997 (Exhibits P-10 to P-13) have resulted in a
concluded contract. It is thus not possible to accept the contention of
the defendant that these two letters had not concluded the contract
for payment of the prepayment of the loans and these got concluded
subsequently when the defendant by their letter dated 17th
September, 1997 (Exhibit P-15) had computed and calculated the
total amount payable towards prepayment premium. Calculation and
quantification of prepayment premium is subsequent to the
conclusion of the contract. The said prepayment premium could be
calculated only in terms of letter dated 8th August, 1997 (Exhibit P-9)
i.e. as per the prevailing standard norms as set out by the financial
institutions. Quantification of the prepayment premium could be CS(OS) No.944/2001 Page No.24
done only in terms thereof and not on any other terms and conditions.
40. Similarly, the contention of the plaintiff that the conditional
acceptance of payment was only in respect of one of the loans,
namely, term loan under Project Finance Scheme as conditional
endorsement was made only in the letter dated 11th September, 1997
(Exhibit P-11) and not on letters of even date, namely, Exhibits P-10,
P-12 to P-13 has to be rejected. The plaintiff in the plaint in para 15
has stated that the representative of the plaintiff who had handed
over the pay orders towards prepayment of the loans was asked by
the defendant to deposit further amount on charges for prepayment of
loans. The plaintiff and the defendant always understood that the
conditions mentioned in Exhibit P-11 would be equally applicable to
Exhibits P-10, P12 and P-13.
41. The defendant has failed to produce and file copy of the
prevailing standard norms set out by the financial institutions as
stipulated in the letter dated 8th August, 1997 (Exhibit P-9). The
prevailing standard norms were set out by the financial institutions
were within the knowledge of the defendant, a financial institution and
the lender. Onus was squarely on the defendant to establish and
show the prevailing standard norms set out by the financial
institutions as on 8th August, 1997. DW-1, Mr. S.K. Mazumdar,
Deputy General Manager (Law) when cross examined on the
question of prevailing standard norms and whether the relevant
circular had been placed on record had stated as under:-
CS(OS) No.944/2001 Page No.25
"Q. Mr. Majumdar, in your affidavit by way of evidence, you have referred to circular dated February 20, 1995 issued by IFCI regarding premature repayment of rupee loans. This was obviously after the rupee term loans have been availed by Plaintiff.
Ans. Yes.
Q. Mr. Majumdar, can you please show me from the record of the Hon‟ble Court before you, any communication of the circular to the Plaintiff?
Ans. No. There is no such practice of
communicating internal circulars to our
borrowers."
42. The aforesaid cross examination of the defendant‟s
witness was with reference to paragraph 3(x) of the preliminary
submission of the defendant wherein reference was made to Circular
dated 20th February, 1995 regarding premature prepayment. It was,
inter alia, stated that interest loss i.e. difference between document
rate (excluding interest tax) and the prevailing floor rate (excluding
interest tax) thus calculated was discounted at the prevailing lending
rate to arrive at the net payable value of interest lost. I deem it
appropriate to reproduce relevant paragraphs of the written statement
and replication:
WRITTEN STATEMENT "(x) The policy for charging the premium prevalent on the Rupee Term Loan at the relevant point in time was/is contained in Operational Circular No. 6(1205)/95 dated February 20, 1995 issued by the Defendant. As per the said Circular No. 6/95 dated 20.2.1995 regarding premature repayment, the interest loss i.e. difference between the document rate (excluding interest tax) and the Prevailing Floor Rate (excluding interest tax), thus calculated shall be discounted at the Prevailing Lending CS(OS) No.944/2001 Page No.26
Rate (PLR) to arrive at NPV of interest loss. The interest tax on premium would be recovered @2% on the premium amount.
(xi) Premium on Foreign Currency Loan, as per Defendant‟s Circular dated 4.3.1998 is calculated on the basis of the following formula:
NPV discounted at prevailing six month LIBOR, and interest differential by applying = lending rate LESS prevailing six month LIBOR.
NPV1
Discounting factor (1 + (r/100) Ʌn
n = Cumulative nos. of days reckoned from the date of realization.
r = applicable discount rate.
In case of Foreign Currency Loan (FCL), the days would be 360.
(xii) Thus, in Rupee Term Loan cases, calculations are based on difference between the document rate i.e. 19.12% LESS prevailing floor rate (PLR) i.e. 14.5% and discounted at prevailing floor rate to arrive at NPV, and in case of FCL, document rate i.e. 9.50% LESS LIBOR i.e. 3.44 (as on 12.9.1997)"
REPLICATION Reply to para (x) & (xii) in replication
"(x) to (xii) The contents of paras (x) to (xii) of the "Preliminary Submissions" are incorrect, misconceived, misleading hence denied. The alleged operational circular 6(1205)/95 dated 20th February, 1995 issued by the Defendant is not binding on the Plaintiff. The alleged circular was issued subsequent to the entering of the Loan Agreements by the parties. The alleged formulae for the calculation of pre-payment premium are not applicable to the loan agreements between the Plaintiff and the Defendant herein."
CS(OS) No.944/2001 Page No.27
43. A reading of the above paragraphs show that the plaintiff
has not disputed contents of Circular dated 20th February, 1995 as
reproduced in para 3(x) of the written statement. Therefore, I feel the
defendant will be entitled to claim prepayment premium as mentioned
in para 3 (x) i.e. difference between the document rate and the
prevailing floor rate after excluding interest tax from both and
discount interest at the prevailing PLR to arrive at the net payable
value of the interest loss. I may note here that the interest is being
discounted because it was to be paid over a period of time in future,
but in view of one time premature payment, this interest though
payable in future was being paid immediately. While arriving at the
above finding/conclusion, I have also relied upon the principle that
averments made in the pleadings but not specifically denied by the
other side is deemed to be admitted. (See, Order VI of the Code of
Civil Procedure, 1908).
44. With regard to the Foreign Currency Loan, the circular
relied upon and quoted in para 3(xi) of the written statement by the
defendant is dated 4th March, 1998. The said circular was not
prevailing on the date when letter dated 8th August, 1997 (Exhibit P-9)
was issued and in terms of which payment of the principal amount
with interest was made on 11th September, 1997 (Exhibits P-10 to P-
13). Circular dated 4th March, 1998 cannot be the basis for payment
of premium. This will be contrary to the concluded contract between
the plaintiff and the defendant. The defendant cannot rely upon a CS(OS) No.944/2001 Page No.28
subsequent circular dated 4th March, 1998 for a concluded contract
based upon prevailing policy of prepayment as it existed when letter
dated 8th August, 1997 (Exhibit P-9) was issued and offer was made
in terms thereof. The said formulae therefore, as mentioned in para
3(xi) of the written statement, cannot be applied. As already observed
above, the defendant has failed to discharge the onus and place on
record the relevant prevailing standard norms for payment of
prepayment premium on Foreign Currency Loan. Onus on the
defendant in terms of Issue No. 5 has not been discharged by the
defendant. The defendant has also withheld the relevant document
and therefore has to face consequences. It is not the case of the
defendant that the relevant standard norms as on that date are on
record or were known to the plaintiff. Witness of the plaintiff was also
not cross examined by the defendant on this aspect.
45. The aforesaid view taken by me is fortified and
corroborated by the subsequent letters and correspondence
exchanged between the parties. The defendant by their letter dated
17th September, 1997 (Exhibit P-15) had calculated prepayment
premium with reference to Net Payable Value of the interest loss as
calculated in terms of Circular dated 20th February, 1995 in form of a
chart for both rupee loans and the Foreign Currency Loan. In the
case of rupee loan the document rate of interest was reduced from
PLR as on the relevant date and the difference was then discounted
with a reference to the prevalent lending rate (PLR) + 1%. The net CS(OS) No.944/2001 Page No.29
effect was that the plaintiff was liable to pay the difference between
document rate of interest, which was higher and the PLR on the date
when payments were made, which was lower. The resultant figure,
i.e. net loss of interest was then discounted to arrive at the sum
payable in case of rupee loans.
46. In response to this letter, the plaintiff wrote letter dated
18th September, 1997 (Exhibit P-16) making reference to the
calculations for Net Payable Value. The only objection raised by the
plaintiff was that the defendant had charged premium of 2.5% over
prevailing lending rate when documents of loan were executed and
therefore the same 2.5% premium should be added to the current
prevailing PLR to calculate and the difference between the current
prevailing PLR + 2.5% should be treated as interest loss. In other
words, the plaintiff accepted the calculations in terms of Circular
dated 20th February, 1995 except that 2.5% premium was charged on
the lending rate at the time of execution of the document should also
be added to the current prevalent PLR. It was also stated that the
discounting should be done at the prevalent PLR + 2.5% instead of
prevalent PLR + 1% as made by the defendant.
47. As far as Foreign Currency Loan was concerned, the tabulation enclosed with the letter dated 17th September, 1997 (Exhibit P-15) had made reference to the rate of interest mentioned in the document i.e. 9.5% and the prevalent LIBOR rate of interest at 3.06% in respect of DM. However, for calculating the discounted Net Payable Value, calculations was done by the defendant with a reference to CS(OS) No.944/2001 Page No.30
prime lending rate (PLR) + 1%. The plaintiffs in their letter dated 18th September, 1997 (Exhibit P-16) disputed the entire calculation of prepayment premium on Foreign Currency Loan. It was specifically stated that no prepayment premium should be charged since the lending rate mentioned in the document was 9.5% p.a. and the current lending rate for Foreign Currency Loan in DM is not less than 9.5% p.a. Thus, no loss was being caused to the defendant on prepayment and in case prepayment premium was to be discounted, the defendant would be liable to make payment to the plaintiff.
47. Defendant replied to this letter on 3rd November, 1997
(Exhibit P-20) rejecting the claim of the plaintiff, both in respect of
Rupee loans and foreign currency loan stating that the same cannot
be accepted as prime lending rate concept was not in existence at
the time when the loans were sanctioned. However, the defendant
did not specifically deny and give reply to the contention of the
plaintiff that the interest rate of 9.5% mentioned in the Foreign
Currency Loan document and the current lending rate of Foreign
Currency Loan in DM was not less than 9.50 i.e. same as mentioned
in the document or the loan agreement. If the current lending rate
and the document rate were the same, no loss of interest was
caused to the defendant. The defendant has not lead any evidence to
show loss on account of prepayment of foreign currency loan. PLR on
8th August, 1997 was much higher than the document rate of interest
mentioned in Foreign Currency Agreement.
48. In view of the findings given above, it is held that as far as Indian rupee loans are concerned, the plaintiff is liable to pay CS(OS) No.944/2001 Page No.31
prepayment premium in terms of para 3(x) of the preliminary submissions as mentioned in the written statement and in terms of circular dated 20th February, 1995 as calculated by the defendant as per chart enclosed with letter dated 17th September, 1997 (Exhibit P-
15). However, with regard to the Foreign Currency Loan the defendant has failed to produce and prove the existing settlement norms as on 8th August, 1997 and the fact that there was a difference between the document lending rate and the current lending rate for Foreign Currency Loan in DM as on 8th August, 1997 in terms of their letter of even date marked Exhibit P-9. The defendant is, therefore, not entitled to claim any prepayment premium in respect of Foreign Currency Loan over and above 1% for which the plaintiff was/is agreeable and to which extent no claim has been made in the plaint also. It is accordingly held that the plaintiff is entitled to refund of prepayment charge of Rs.22,19,000/- as claimed in para 52 of the plaint.
49. With reference to claim of Rs.1,60,000/- on excess payment made by the plaintiff to the defendant, no evidence has been led to justify the claim. The said claim is accordingly rejected.
ISSUE NO.3
50. Defendant in their written statement has submitted that the
plaintiff in making the prayer for refund wants to go behind and
challenge the terms and conditions of the loan agreements. Having
taken the benefit of the loan agreements, the plaintiff is estopped
from raising this plea now. It is also submitted that the plaintiff is
estopped from challenging the premium charged as the plaintiff has
accepted the defendant‟s discretionary right to charge prepayment CS(OS) No.944/2001 Page No.32
premium and the parties have acted on this basis. The plaintiff
cannot challenge the quantum of prepayment premium. In the written
submission filed by the defendant, it is submitted that the suit is
barred on the principle of "issue estoppel" and "action estoppel".
51. On the question of "issue estoppel", principle of res judicata
has been examined above and answered in the negative i.e. in favour
of the plaintiff and against the defendant. As already stated above,
the decision of the writ court dated 25th January, 2000 is not binding
and stands obliterated in view of order passed by the Division bench
permitting the plaintiff to withdraw the writ petition itself. In these
circumstances, it cannot be said that decision on any issue had
attained finality to be binding on the plaintiff.
52. On the question of "action estoppel", virtually nothing is pleaded
in the written statement. However, I have referred to the contentions
raised by the defendant in their written statement and the
contemporaneous correspondence exchanged between the parties
and the basis on which prepayment of loans were made. I have
already quoted above, the relevant portion of letter dated 8th August,
1997 (Exhibit P-9) written by the defendant company making an offer
on the plaintiffs‟ request for prepayment of the entire loan amount
with interest. In the letter dated 8th August, 1997 (Exhibit P-9) it was
specifically stipulated that the plaintiff would be liable to pay principal
amount, interest and other charges and premium which would be
calculated as per the prevailing standard norms set up by financial CS(OS) No.944/2001 Page No.33
institutions, but the said calculations would be made separately. After
receiving letter dated 8th August, 1997 (Exhibit P-9) the plaintiff made
prepayment of the principal amount along with interest by their letters
dated 11th September, 1997 (Exhibits P-10-13). The said letters make
specific reference to letter dated 8th August, 1997 (Exhibit P-9) and
the terms and conditions mentioned therein.
53. In these circumstances, plaintiff will be bound by the terms and
conditions mentioned in the letter dated 8th August, 1997 (Exhibit P-
9). The quantum of premium would be as per prevailing standard
norms set by financial institutions. The plea of estoppel will apply but
only to that extent and not beyond the terms and conditions
mentioned in the letter dated 8th August, 1997 (Exhibit P-9). Issue
no.3 is accordingly decided holding, inter alia, that the plaintiff in view
of letter dated 8th August, 1997 (Exhibit P-9) and the payment made
thereafter by letters dated 11th September, 1997 is bound by the
principle of estoppel to pay prepayment premium as per prevailing
standard norms set up by financial institutions. The defendant is also
bound on the same basis. This issue is accordingly decided.
ISSUE NO.7
54. The plaintiff has also not led any evidence to show that any
notice was issued to the defendant under the Interest Act.
Accordingly, claim for pre-suit interest is rejected. The plaintiff will
be entitled to pendente lite and future interest on Rs.22,19,000/- @
12% p.a. CS(OS) No.944/2001 Page No.34
ADDITIONAL PLEA
55. Learned counsel for the defendant had submitted with
reference to prayer „a‟ in the plaint that the suit was barred by
limitation. The said prayer reads as under:
"(a) pass a decree of declaration to the effect that the amount of pre-payment premium charged by the defendant from the plaintiff in respect of loan advanced under Project Finance Scheme is beyond the terms of contract between the parties and illegal besides being arbitrary, unconscionable and not enforceable and that the defendant is liable to refund the same."
56. I have already rejected the said prayer of the plaintiff in view of
the finding given with reference to issue nos.2, 4 to 6. On the
question of limitation, I do not find any pleadings or evidence on
record. It is not only the date of the contract which is relevant for
deciding question of limitation for a prayer of declaration. The date on
which dispute arose is also relevant. A party need not seek
declaration when there is no dispute or difference about the term of
the contract. Cause of action to sue or make a prayer for declaration
shall accrue only after disputes have arisen. Till disputes arise, the
plaintiff had no cause of action. Plea of limitation with reference to
prayer clause (a) in the present case cannot be decided without
evidence being on record to show and establish when the cause of
action had first arisen. I may also notice here that if this plea had
been raised, several defences were available to the plaintiff. The said
plea is therefore rejected. However, as pointed out above, I have CS(OS) No.944/2001 Page No.35
held that no decree of declaration is to be passed.
RELIEF
57. Decree of Rs.22,19,000/- is passed in favour of the plaintiff and
against the defendant along with pendente lite and future interest @
12% p.a.. The plaintiff will be entitled to proportionate cost. Decree
sheet will be prepared accordingly.
58. Suit is disposed of.
(SANJIV KHANNA)
JUDGE
OCTOBER 21ST , 2008.
P
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!