Citation : 2008 Latest Caselaw 2077 Del
Judgement Date : 25 November, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) NO.159/2004
Date of Decision : November 25, 2008
M/s. Sikka Associates .....Appellant
Through : Mr. V.K. Makhija,
Sr.Advocate, with Mr. S.K. Chandwani, Advocate.
Versus
Airports Authority of India .....Respondent
Through : Mr. Advocates.
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE MANMOHAN
1. Whether the Reporters of local papers may be allowed to
see the judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
JUDGMENT
MUKUL MUDGAL, J. (ORAL)
1. The present appeal has been filed by the appellant above-named being
aggrieved from the judgment of the learned judge of this Court passed in OMP
No.179 of 2000 whereby the arbitral award dated 12th June, 2000 awarding an
additional sum of Rs.12,25,575/- in favour of the appellant as fees @ 4.5% on the
cost of the project against the tender cost and also upon the amount of escalation charges payable to the architects and a further sum of Rs.40,000/- as interest on
the delayed payment of bill has been set aside.
2. Briefly, the facts of the present case are :
i) That the appellant had submitted its offer vide letter dated 5th January,
1989 relating to the work of 'providing consultancy services for the work of
construction of New International Block, Domestic Departure / Arrival Block and
associated work at Goa Airport'. It was accepted by the respondent vide letter
dated 22nd February, 1989 at the remuneration payable to the appellant for such
work at "4.5% of the executed cost of the project".
ii) That while accepting the said offer given by the appellant vide its letter
dated 5th January, 1989, the respondent vide its letter dated 22nd February, 1989
categorically stated that for the services to be rendered by the appellant, the
appellant would be paid 4.5% of the executed cost of the project and other terms
and conditions were also attached to the said letter accepting the said offer. The
relevant term is Clause 3 of the terms & conditions of Agreement which relates
with the 'Mode of Payment' and reads as follows :-
"3. MODE OF PAYMENT
For each of the services in the scope of the work the consultant shall be paid in the following stages consistent with the work done plus reimbursable expenses as agreed upon.
Payments made to the Consultants are on account and shall be adjusted against the final amount payable :
PRELIMINARY STAGE
Stage 1 On submitting conceptual 10% of the total fees
designs and preliminary payable based on cost
estimates of costs estimates as per Clause
2.03
Stage 2 On submitting the final 20% of the total fees
preliminary payable less payment
drawings/designs and already made cost.
model along with the
modified estimates.
Stage 3 On submitting preliminary 25% of the total fees
drawings for obtaining payable less payments
approval from statutory already made.
bodies.
WORKING DRAWING STAGE
Stage 4 On preparation of basic 35% of the total fees
working drawings and payable less payments
details sufficient for already made.
preparing item-wise
estimates of costs.
Stage 5 On submitting detailed 55% of the total fees
specifications, bill of less payments already
quantities detailed made based on the cost
architectural working estimate as given in this
drawings structural and stage.
services designs together
with estimates of costs
and to invite tenders.
Stage 6 On submission of 65% of the total fees
complete set of working payable less payments
drawings and details. already made.
CONSTRUCTION STAGE
Stage 7 During the course of Further 25% to be paid
construction of work at in instalments
site. consistent with the
value of work done.
Stage 8 On completion of Balance payment
(to be paid within six 10% making the total
months of completion of equivalent to 100% of
the work) the fees payable based
on the actual cost of the
work.
3. That it is not disputed before us that the tender cost for the civil work was
Rs.5,31,09,985/-, while the actual cost when the work was completed came to Rs.6,58,35,000/-. The appellant was paid 4.5% on Rs.5, 31, 09,985/-, but was not
paid this amount on the actual cost upon completion of the work which became a
root cause of the disputes between the parties.
4. That accordingly, as provided under the agreement, the appellant invoked
the arbitration and Shri C.B. Rai, Engineer-in-Chief (Retd.) was appointed as an
arbitrator by the Chairman, Airports Authority of India, to act as a sole arbitrator.
5. That the main controversy between the parties before the arbitrator was
whether the appellant was entitled to his remuneration @ 4.5% on the tender cost
or on the actual cost worked out at the time of completion of the said project.
The appellant has been claiming his remuneration on the actual cost incurred for
completion of the said project, while the respondent has been saying that the
appellant is entitled to remuneration only on the tender cost. Thus, the arbitrator
was to decide as to on what amount the remuneration was to be paid to the
appellant.
6. That the arbitrator while giving reasons in his award made reference to the
letter of acceptance dated 22nd February, 1988 which stipulated the remuneration
payable at "4.5% of the executed cost of the project" and reference was also
made to clause 3 of the Agreement and more particularly Stage 8 of the Mode of
Payment wherein balance payment 10% making the total equivalent to 100% of
the fees payable based on the actual cost of the work. The arbitrator thus
returned the finding that the appellant was entitled to its fee @ 4.5% on the
actual cost of the work which is the executed cost inclusive of escalation and not
on the tender cost and accordingly awarded an amount of Rs.12,25,575/- to the appellant under Claim No.1 and Rs.40,000/- was awarded to the appellant under
Claim No.4 and the interest was granted @ 18% on the amount of award from the
date of its publication till the date of its payment.
7. That after the said award was published, the respondent has filed
objections under Section 34 of the Arbitration & Conciliation Act, 1996 which
became the subject matter of OMP No.179 of 2000 wherein the respondent raised
a contention that the arbitrator has mis-interpreted the provisions of the contract
and has wrongly awarded remuneration @ 4.5% on the executed cost / actual
cost, whereas he ought to have held that the appellant was entitled to 4.5% of the
tender cost only.
8. On the other hand, the appellant resisted the said objections and stated
that the arbitrator is the final arbiter in law and the provisions of the contract
were within the domain of the arbitrator to interpret. The arbitrator being the
Engineer-in-Chief (Retd.) was well conversant with the said services and has
interpreted the provisions of the contract rightly and, thus, the award of the
arbitrator in this regard is final and cannot be assailed in law. However, such a
contention of the appellant did not find favour with the learned judge of this Court
and by order dated 26th May, 2004 allowed the petition under Section 34 of the
Arbitration & Conciliation Act, 1996 and set aside the arbitral award dated 12th
June, 2000.
9. That aggrieved by the said judgment, the appellant has filed the present
appeal.
10. We have heard both the counsels in detail. The learned Senior Counsel for the appellant had contended that the only controversy between the parties before
the arbitrator was whether the appellant had to be paid remuneration @ 4.5% on
the tender cost or had to be paid upon executed / actual cost. The learned Senior
Counsel also referred to the definition of the word 'executed' given in Black's Law
Dictionary. The word 'executed' means "completed, carried into full effect" and
thus stated that the executed cost as mentioned in the letter of award means the
cost of the work upon completion. The learned Senior Counsel for the appellant
also contended that clause 3 of the Agreement deals with the stage by stage
payment also refer to the actual cost of the work would be the cost which has
been incurred by the department for completing the said work which also includes
in it the escalation paid to the contractor. It was also contended that the
arbitrator was well within its rights to interpret the terms and conditions of the
contract and the arbitrator had interpreted the said provisions and had held that
the appellant has to be paid remuneration on the actual cost of the work which is
the executed cost which also includes in it the escalation as well.
11. That according to the learned Senior Counsel for the appellant, the said
interpretation by the arbitrator is final and cannot be assailed in law and the
reference was made by the counsel to following judgments of Hon'ble Supreme
Court:
i) Sudershan Trading Co. Vs. Govt. of Kerala
(AIR 1989 SC 890)
ii) Food Corporation of India Vs. Joginder Pal Mahinder Pal
(AIR 1989 SC 1263)
iii) Hind Builders Vs. Union of India
(AIR 1990 SC 1340)
12. That it was also contended by the learned Senior Counsel for the appellant
that even if any term and condition of the contract is capable of having two
plausible interpretation, then if the arbitrator has accepted one out of two, the
court cannot set aside the said interpretations by substituting its view that the
arbitrator should have accepted the other plausible view. Thus, it was contended
that the award could not have been assailed in law and the objections in this were
was beyond the scope of Section 34 of the Arbitration & Conciliation Act, 1996.
13. On the other hand the learned Senior Counsel for the respondent reiterated
the stand taken before the learned Single Judge that the arbitrator misconducted
the proceedings by mis-interpreting the provisions by granting remuneration on
the actual cost, whereas it ought to have been granted on the tender cost. The
learned Senior Counsel for the respondent without prejudice to their arguments
further contended that the rate of interest awarded by the arbitrator is on the
higher side and it ought not have been granted @ 18% p.a.
14. We have gone through the provisions of the contract and we feel that the
interpretation given by the arbitrator is absolutely reasonable and justified. The
word used in the letter of acceptance is the 'executed' cost while in the other
terms and conditions of the Agreement, it has used actual cost of the work. The
same cannot be the tendered cost. It is a matter of common practice that some
times during the execution of the work there are deviations in the work and
certain additional work as well which enhances the cost of the work, therefore, it
is the executed cost or the actual cost which assumes importance. Furthermore,
it is no where provided either in the letter of acceptance or in the terms and
conditions of the contract that remuneration has to be paid on the tender cost. Thus, the plea of the respondent that the remuneration has to be paid on the
tender cost/amount put to tender cannot be accepted. Escalation is also the part
of the executed cost, thus, if the arbitrator has taken a view that the appellant is
entitled to remuneration on the executed cost of Rs.6,58,35,000/- nothing wrong
can be found in the same so as to warrant interference in appeal.
15. That from the impugned judgment, we find that the learned Judge has
adopted its own interpretation by differing from the interpretation adopted by the
arbitrator which according to us could not have been taken in view of the law laid
down by the Hon'ble Supreme Court of India in the aforementioned judgments of
Sudershan Trading Co., Food Corporation of India and Hind Builders.
(supra) Accordingly, we do not agree with the said view expressed by the
learned Judge. So far as the contention of the respondent is concerned that
interest awarded is at the higher side, we feel the interest of justice would be met
if the interest @ 18% p.a. is reduced to 12% p.a.
16. We, therefore, set aside the impugned judgment and dismiss the petition
under Section 34 of the Arbitration & Conciliation Act, 1996 for setting aside the
arbitral award dated 12th June, 2000. However, we modify the said award, so far
as it awards interest @ 18% p.a. to 12% p.a. No orders as to costs.
(MUKUL MUDGAL) JUDGE (MANMOHAN) JUDGE November 25, 2008 Sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!