Citation : 2008 Latest Caselaw 943 Del
Judgement Date : 4 July, 2008
* HIGH COURT OF DELHI
% Date of decision: July 4th, 2008
+ FAO(OS)No. 08/2007
Union of India ...Petitioner
through
Mr. Bijender Singh, Advocate
Versus
M/s. Mecano Export Import S.A. ...Respondent
through
Mr. Brajesh K. Srivastava with
Mr.Dinesh K.Gaur, Advocates
Coram :
Hon'ble Mr.Justice Manmohan Sarin
Hon'ble Mr.Justice Manmohan
(1) Whether reporters of local paper may be Yes
allowed to see the judgment?
(2) To be referred to the reporter or not? Yes
(3) Whether the judgment should be reported Yes
in the Digest ?
Manmohan Sarin, J.
1. Appellant, Union of India in this appeal assails the order
dated 8.2.2006 passed by the Single Judge in OMP No.381/2003,
dismissing the objection petition filed under Section 34 of the
Arbitration and Conciliation Act, 1996. The appellant herein in the
Objection Petition had challenged the arbitral award dated
27.6.2003. Learned Single Judge while dismissing the petition
held that the Award passed by the Arbitral Tribunal was on
consensual terms and the same could not, therefore, be
challenged.
2. Before considering the grounds raised in the present appeal,
facts may be noted briefly.
(i) A contract was executed on 29.8.1996, between
the parties for supply of 10,000 nos. 22.9T BG
BOX‟N‟ wheel sets. The contract specified detailed
terms including a supply schedule. As per the
schedule, within 90 days from the execution of the
contract, 1500-2000 units were to be supplied. The
balance was to be offered in six monthly
instalments. Provisions were made for inspection
by appellant‟s representatives and for opening
Letter of Credit. Clause 17 of the contract provided
for levy of liquidated damages in the event of non-
compliance of seller‟s (respondent‟s) obligations
including timely supply of the material.
(ii) The quantity of 10,000 was subsequently reduced
to 5,297 and the respondent shipped the material
in three lots of 1936 nos., 367 nos. and 3,000 nos.
on 30.5.1997, 29.6.1997 and 4.3.1999 respectively.
Delivery period was extended with token liquidated
damages with denial clause for the first and second
lot. For the balance 3000 nos., delivery period was
extended with liquidated damages and denial
clauses to cover foreign exchange and customs
duty variation etc., limiting the total damages to
10% of value of the stores besides expenditure of
„Letter of Credit‟ extension.
(iii) Arbitration notice was served by the respondent
Firm on 24.5.2000, claiming refund of liquidated
damages and other charges totaling to US $
10,62,444.16. Shri Ranganath Mishra, former Chief
Justice of India, Shri M.V. Ramani, the then COS,
Southern Railway and Shri V.S. Malimath, retired
Chief Justice Karnataka and Kerala High Court, were
appointed as Arbitrators. Petitioner filed their
reply to the claims and made counter claims on
account of delay in supplies, cost of arbitration
proceedings etc.
(iv) Learned Tribunal in the hearing dated 27.4.2003,
came to certain conclusions and passed the order
as follows
"After discussing the claims at length with reference to the entire material on record, we have come to following conclusions :
The claim of liquidated damages raised by the respondent (UOI) shall be confined to 1 % uniformly for the entire supply in respect of all the three consignments
The claimant shall be entitled to the price of the material supplied at the stipulated rate for which no payment has been made
The costs actually incurred by the claimant for the LC charges shall be confined to 50%.
In respect of amount in excess of 1% which will now become refundable to the claimant, interest shall be payable at 6% only".
Costs of the proceedings at USD 10,000 payable to the claimant.
Arbitral Tribunal called upon the parties to clearly
indicate within 4 weeks from the date of the above
order, the exact amounts under each of the above
heads, and on the basis thereof claimant‟s dues
were to be quantified to determine the stamp duty
for the award. It was further held by the Tribunal
that other claims of the claimant and all claims
raised by the respondent (appellant herein) are
negated.
(v) In pursuance to quantification sought by the
Tribunal, appellant submitted computation on
26.5.2003 followed by hearing on 30th May, 2003.
The impugned award records "From the
submissions, we are satisfied that the parties
wanted their dispute to be settled on the basis of
the conclusions set out by us on 27.4.2003 subject
to the modifications which were suggested to us at
the hearing on 30.5.2003 and were agreed".
(vi) The award challenged by the appellant in OMP
381/2003, was dismissed on the ground that it was
consensual. The said judgment is impugned before
us.
3. It is the petitioners case that arbitral Tribunal is bound to
decide the dispute in accordance with the terms of the contract.
Appellant contended as per the terms of contract, liquidated
damages could be levied for the delayed period, upto 10%.
When the claimants failed to perform the contract, extension of
time was given to the claimant only subject to levy of liquidated
damages at the rate of 10%. Appellant submitted that the
Tribunal acted contrary to the provisions of the contract and the
Act and did not encourage parties to a settlement in accordance
with section 30 of Arbitration and Conciliation Act, 1996. Instead,
after recording five issues, arbitral Tribunal asked the parties to
calculate the exact amount arising out of such 5 issues so that
necessary stamp duties could be purchased for the award.
Counsel contended that such calculation for the purpose of stamp
paper cannot amount to any kind of consent, nor any kind of
encouragement for the parties for settlement. He submitted that
no settlement between the parties was ever arrived at and that
the computations were submitted without prejudice to their
rights.
4. Appellant‟s counsel submitted that he had paid/remitted to
the respondent a sum of US $ 3,37,500 towards the liquidated
damages and a sum of US $ 16,856 towards 50% LC charges as
per the award without prejudice to the right of the appellant in
order to save the penal interest of 18% per annum. Counsel
further submits that the interest as levied is harsh, arbitrary and
on the higher side in comparison to the prevailing bank interest.
5. We have heard counsels of both parties and perused the
arbitral award along with other documents available on record.
Firstly it is seen that as per the arbitral award US $ 4,64,128.60
inclusive of arbitration cost, 50% LC charges, 6% interest on
liquidated damages and liquidated damages in excess of 1% to
be returned to the respondent, a total of US $ 3,54,356 on
account of liquidated damages refunded and 50% of LC charges
has been paid by the appellant to the respondent without
prejudice to the appellants rights under the contract to avoid
penal costs on delay of payment @ 18% per annum as per the
award.
6. The learned Single Judge has not dealt with the objections
raised by the appellant on merits under section 34 of the
Arbitration and Conciliation Act, 1996 and dismissed the same on
the short ground that it was a consensual award and accordingly,
the objections were not maintainable. The appellant has
questioned the very basis or existence of consent. The genesis of
consensual award lies in the proceedings/order passed on 27 th
April, 2003 which had also been the basis on which the learned
Single Judge has proceeded and dealt with. Reference is required
to be made to the proceedings of 27th April, 2003 which are
reproduced for facility of reference:-
"PROCEEDINGS
After discussing the claims at length with reference to the entire material on record, we have come to the following conclusions:
(i) The claim of liquidated damages raised by the respondent shall be confined to 1% uniformly for the entire supply in respect of all the three consignments.
(ii) The claimant shall be entitled to the price of the material supplied at the stipulated rate (5297) for which no payment has been made.
(iii) The costs actually incurred by the claimant for the LC charges shall be confined to 50%.
(iv) In respect of the amount in excess of 1% which will now become refundable to the claimant, interest shall be payable at 6% only.
(v) We assess the costs of the proceeding at ten thousand US $ payable to the claimant.
Parties shall now be called upon to clearly indicate within four weeks‟ from today the exact amounts under each head, and on the basis thereof claimant‟s due shall be quantified to determine the stamp duty for the award.
Other claims of the claimant and all the claims raised by the respondents are negated.
We are of the unanimous view that if the dues of the claimant to be stated in the award are paid within ninety days from the date of award, no interest shall be payable, otherwise interest @ 18% shall be payable from the date of the award till recovery.
Notify parties and call upon them to appear on 31st May, 2003 with the requisite details at 10 a.m. at the same place."
7. The parties in compliance with the directions given and the
appellant particularly vide its letter of 26th May, 2003 furnished
the information to the Arbitral Board in respect of each of the
conclusions recorded in the proceedings of 27th April, 2003. It is
significant to notice that the said letter begins with "The
respondent is submitting the exact amount as directed vide
proceedings dated 27.4.2003 by Hon‟ble Arbitrators without
prejudice to the rights of the respondent." (UOI-appellant herein).
The letter ends with last two lines as "It is mentioned that the
above details as sought by the Hon‟ble arbitrators is furnished by
the respondents without prejudice to their rights."
8. The Arbitrators, after the parties complied with the
directions given on 27th April, 2003, stated to have taken up the
matter for hearing on 30th May, 2003. The original record as
produced by the Arbitrators does not carry any recorded
proceedings of 30th May, 2008. Counsel for the appellant during
the course of hearing sought to hand over an internal noting of
their‟s titled Sr.No.138 reference : arbitration proceedings held
on 30th May, 2003 which recorded directions with regard to
payment of fees to the Arbitrators, travel expenses, secretarial
expenses etc having been given in the said hearing. However,
there is another purported record of proceedings which are
erroneously dated 30th June, 2008 which the appellant claims
should be 30th May, 2008 which also refers to travel expenses,
payment of fees of the Arbitrators and the directions to furnish
non judicial stamp paper.
Be that as it may, in the original record, as furnished by the
Arbitrators, there is no record of proceedings for 30th May, 2003.
It is only in the arbitral award that a reference is made to the
matter having been taken place for further hearing after the order
of 27th April, 2007 in the following words:-
"Both the parties have complied with the direction and the matter thus has been taken up for further hearing on 30.5.2003."
The Arbitrators go on to further record in the award:-
"From the submissions we are satisfied that the parties wanted their dispute to be settled on the basis of the conclusions set out by us on 27.4.2003 subject to the following modifications which were suggested to us at the hearing on the 30.5.2003 and were agreed."
9. As noted earlier, there is no record of proceedings of 30 th
May, 2003. It is the appellant‟s case that no such agreement was
reached or recorded in the hearing. Rather the appellant had even
in their letter dated 26th May, 2003 furnished the said information
without prejudice to their rights and in compliance with the
directions given on 27th April, 2003 which is indicative that there
was no consent. The learned Single Judge dismissed the
objections by holding the award to be consensual and had also
relied on the above quoted portion of the award. The learned
Single Judge has also noted that at the end of the award, the
Arbitrators have noted "We are thankful to the parties and their
counsel for cooperating final disposal of the dispute on terms
which are beneficial to the interest of both" and the same again
been suggestive of there being consent and agreement. The
learned Single Judge, therefore, held that the Arbitral Tribunal had
indicated its mind by recording certain conclusions in the
proceedings of 27.4.2003 and the parties agreed to settle the
disputes on the basis of said terms. However, certain modifications
suggested by the respondent in respect of interest, cost of
arbitration and future interest payable etc were discussed on 30 th
May, 2003 and even those modifications were agreed. The
learned Single Judge proceeds to hold that if the appellant had any
genuine grievance with regard to the award, it should have
addressed a letter or communication to the Arbitral Tribunal
disputing the averments made in the said award.
10. Reliance was placed on Shankar K Mondal and others Vs.
State of Bihar and others (2003) 9 SCC 519 wherein it was held
that "If a party thinks that the happenings in court have been
wrongly recorded in a judgment, it is incumbent upon the party,
while the matter is still fresh in the minds of the Judges, to call
upon the attention of the very Judges who have made the record.
That is the only way to have the record corrected. If no such
step is taken, the matter must necessarily end there. It is not
open to the appellant to contend before this court to to the
contrary." The learned Single Judge observed that as to what
applied to court proceedings, same analogy would be applicable
to arbitral proceedings.
11. Reliance is also placed on Daman Singh Vs State of
Punjab (1985) 2 SCC 670 wherein it was observed that where
several grounds are taken but later the parties during the course
of arguments confined to few of those grounds, then no grievance
can be made that grounds taken have not been considered.
12. We have given due consideration to the findings and
reasoning given by the learned Single Judge. We are also
conscious of the fact that the Arbitral Tribunal comprised eminent
Judges and a high functionary and officer of the Railways and the
findings recorded by them deserved the most respectful
consideration and should not be lightly disturbed. However, for
the reasons stated hereinafter, we hold that finding of the learned
Single Judge that award was a consensual award, is not
sustainable. The objections to the award as filed, in our view,
are, therefore, liable to the disposed of on merits. The reasons
are:-
(i) By furnishing of the information in respect of the conclusions
recorded by the Arbitrators in their proceedings of 27th April, 2003,
an inference of the appellant‟s having consented to the same,
cannot be drawn and more so consent cannot be made the basis
of the award. This is especially so in the light of the objections
filed and the information being furnished categorically as without
prejudice to their rights and contentions. The entire basis of the
award being `consensual‟ is said to be the deliberations in the
hearing held on 30th May, 2003. As observed earlier, there is no
record of the said hearing or of the respective submissions made.
This is especially so even where the conclusions in respect of
which appellant had expressed its reservations by furnishing
information as without prejudice to their rights were modified to
the disadvantage of the appellant, without there being a
recording of consent in respect thereof. As noted, the only
semblance of the recording that is available is with regard to the
administrative matters regarding payment of Arbitrators‟ fees,
traveling expenses, secretarial expenses etc. in relation to 30th
May, 2003. In the award which was published on 27th June, 2003,
a bald recording appears with regard to Arbitrators having been
satisfied that parties wanted their disputes to be settled on the
basis of conclusions of 27th April, 2003, subject to modifications
which were suggested in the hearing on 30th May, 2003 and were
agreed. Appellant disputes such an agreement or consent.
(ii) Appellant has also urged that award is vitiated by non giving
of the reasons and only conclusions having been given on 27 th
April, 2003. Reference may usefully be made to Sections 30 and
31 of the Arbitration and Conciliation Act, 1996 giving the
procedure with regard to settlement of the disputes through
arbitration and the form and contents of arbitral award. There
was termination of proceedings as required to be noted in terms of
section 30 and recording of agreed terms on the said date. The
most natural and normal course of events of 30th May, 2003,
when modifications based on settlement and agreement to the
earlier conclusions of 27th April, 2003 were allegedly being made,
was to have the same recorded and signed by the parties. The
absence of the proceedings of 30th May, 2003 coupled with the
information having been supplied by the appellant, without
prejudice to its rights and contentions and its denial of any
consent raise and cast a serious doubt on the award being
consensual.
(iii) In these circumstances, in our view, it is a fit case, where
the award cannot be sustained on the basis of consent and would
have to be sustained otherwise with objections being disposed of
on merits in accordance with law. In our view, appellant‟s
occasion to raise a protest against the award being consensual
would arise only after the award was made and published and this
being made known to it. In the instant case, objection petition
was filed on 23rd September, 2003 without any loss of time and as
such not writing any letter of protest in these facts was hardly of
any consequence considering the proximity of the date of filing of
objection petition.
In view of the foregoing discussion, we allow the appeal
and set aside the judgment of the learned Single Judge and
remand the matter for objections to be considered on merits
without proceeding on the assumption of award being a
consensual award.
Manmohan Sarin, J.
Manmohan, J.
July 4th, 2008 ssb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!