Citation : 2008 Latest Caselaw 916 Del
Judgement Date : 3 July, 2008
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 03.07.2008
+ OMP 415/2005
UPPAL ENGINEERING COMPANY PVT LTD ... Petitioner
- versus -
ABHINAV COOPERATIVE GROUP HOUSING
SOCIETY LIMITED AND OTHERS ... Respondents
Advocates who appeared in this case:
For the Petitioner : Mr Raju Ramachandran, Sr Advocate with Mr Mandeep Singh Vinaik and Mr Rishad Chowdhury For the Respondents : Mr Dayan Krishnan with Mr Amit Gupta and Mr Gautam Nayaran
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
1. Whether Reporters of local papers may be allowed to see the judgment ? YES
2. To be referred to the Reporter or not ? YES
3. Whether the judgment should be reported in Digest ? YES
BADAR DURREZ AHMED, J
1. This is a petition under Section 34 of the Arbitration and
Conciliation Act, 1996 seeking the setting aside of the award dated
30.06.2005 made by an arbitral tribunal comprising of three arbitrators.
The challenge is essentially to the question of arbitrability of claim
No.1 which has been decided by the arbitral tribunal in favour of the
claimant (respondent No.1) herein. The petitioner has also raised
issues with regard to limitation and has urged that part of the claim was
time barred. It was also contended that the payments which had been
made to the petitioner upon certificates issued by the architect cannot
be overturned inasmuch as the architect has acted as an agent of the
respondent No.1. Lastly, it was contended that the decision making
process of the arbitrators turned out to be a travesty of justice inasmuch
as the majority view on the question of arbitrability decided as per the
order dated 09.09.2004 had been notified only by the presiding
arbitrator and such an order would be illegal in the absence of the
signatures of the other arbitrators.
2. The respondent No.1, who was the claimant before the
arbitral tribunal, made submissions to the contrary. It was urged on
behalf of the respondent No.1 that claim No.1 was an arbitrable dispute
particularly in view of the novation of the agreement between the
parties recorded in the consent order dated 28.05.1998 passed by a
learned single Judge of this court while disposing of an application
filed by the respondent No.1 under Section 11 of the said Act for the
appointment of an arbitrator / arbitral tribunal. It was also contended
that the question of limitation must be pleaded specifically. This has
not been done either before the arbitral tribunal or before this court and
unless and until specific pleas with regard to limitation are taken, in
view of the decision of the Supreme Court in the case of Oil & Natural
Gas Commission v. M.C. Clelland Engineers S.A.: 1999 (4) SCC 327,
the petitioner would not be permitted to raise such pleas in the course
of oral arguments. With regard to the question of agency, it was
submitted that in building and engineering contracts, the architect as
certifier does not act as an agent of the employer, but acts as a quasi-
judicial authority between the owner and the contractor. A reference
was made to Law Relating to Building & Engineering Contracts in
India, Fourth Edition by Kishore Gajaria. Moreover, the petitioner in
its reply to the claims before the arbitral tribunal had taken the stand
that the architect is not the agent of the respondent No.1 and a
unilateral decision to terminate the services of the architect could not
have been taken by the respondent No.1. It was submitted that the
petitioner having stated before the arbitral tribunal that the architect
was not an agent of the respondent No.1, cannot be permitted to
approbate and reprobate, by now taking the stand that the architect was
an agent of the respondent No.1.
3. With regard to the notification of the majority view of the
order dated 09.09.2004 being signed by only the presiding arbitrator, it
was contended on behalf of the respondent No.1 that this issue no
longer survives inasmuch as the question of arbitrability of claim No.1
has been considered in the award itself and the award has been signed
by all the arbitrators. Thus, even if the earlier incident could be
regarded as an irregularity, the same stood cured by the signing of the
award.
4. Before I consider the rival contentions of the parties, it
would be appropriate to note a few facts with regard to the background
of the case. The respondent No.1 is a group housing society. In 1989,
it invited tenders for the construction of 149 dwelling units at Chilla,
Dallupura (now known as Vasundhara Enclave) through its architect
M/s Govardhan Kundi and Associates (hereinafter referred to as „the
said architect‟). The petitioner‟s tender was found to be the most
suitable and the work of constructing the dwelling units was awarded
to the petitioner. A contract dated 14.09.1989 was signed and executed
by and between the parties for this purpose. Clause 44 of the special
conditions of contract provided for arbitration. The same reads as
under:-
"Clause 44 Settlement of Dispute Arbitration: „All disputes and differences of any kind whether arising out of or in connection with the contract or the carrying out of the works (whether during the progress of the works or after their completion, and whether before or after the determination, abandonment or breach of the contract) shall be referred to and settled by the Architects who shall state their decision in writing. Such decision may be in the form of a final certificate or otherwise. The decision of the Architects with respect to any of the excepted matters shall be final and without appeal as stated in Clause 34. But if either the Employer or the Contractor be dissatisfied with the decision of the Architects or any matter, question or the disputes of any kind (except any of the excepted matters) or as to the withholding by the Architects of any certificate to which the contractor may claim to be entitled, then and in any such case either party (the Employer or the Contractor) may within twenty eight days after receiving notice to such decision, give a written notice to the other party through the Architects requiring that such matters in disputes be
arbitrated upon. Such written notice shall specify the matters which are in dispute and such dispute or difference of which such written notice has been given and no other claim shall be and is hereby referred to the arbitration and final decision of a single Arbitrator being a fellow of the Indian Institute of Architects to be agreed upon and appointed by both parties or in case of disagreement to the appointment of a single Arbitrator, two Arbitrators being both fellow of the Indian Institute of Architects, shall before taking upon themselves the burden of Reference appoint an Umpire.
The Arbitrators, and the Umpire shall have power to open up, review and revise any certificate, opinion, decision, requisition or notice save in regard to the excepted matters referred to in clause 34 and to determine all matters in dispute which shall be submitted to him or them and of which notice shall have been given as aforesaid. Upon every or any such reference the cost of and incidental to the reference and award respectively shall be in the discretion of the Arbitrator or Arbitrators or the Umpire who may determine the amount thereof or direct the same to be taxed as between Attorney and Client or Clients or as between party and party, and shall direct by whom and to whom and in what manner the same shall be borne and paid. The submission shall be deemed to be a submission to Arbitration within the meaning of the Indian Arbitration Act 1940 or any modification thereof, the award of the Arbitrators or Arbitrator or the Umpire shall be final and binding on the parties. Such reference except as to the withholding by the Architects of any certificate under Clause No.32 to which the Contractor claims to be entitled, shall not be opened or entered upon until after the completion or the alleged completion of the works or until after practical cessation of the works arising from any cause unless with the written consent of the Employer and the Contractor. Provided always that the Employer shall not withhold the payment of the interim Certificate nor the Contractor except with the consent in writing of the Architects in any way delay the carrying out of the works by reason of any such matter, question or disputes all due to diligence and shall until the decision of the Arbitrator or Arbitrators or the Umpire be given, abide by the decision of the Architects and no award of the Arbitrator or the Arbitrators or the Umpire shall relieve the Contractor of his obligations to adhere strictly to the Architect‟s Instructions
with regard to the actual carrying out of the works. The Employer and the Contractor hereby also agree that Arbitration under this clause shall be a condition precedent to any right of action under the contract‟."
5. Though the aforesaid arbitration clause is rather lengthy,
what is essential for the purpose of this petition is that there are two
categories of matters - ordinary matters and excepted matters. Insofar
as ordinary matters are concerned, a two-tier system for dispute
resolution was provided. In the first instance, a dispute with regard to
ordinary matters was to be resolved by the architect. In case either of
the parties was dissatisfied with the conclusion of the architect, they
had a further opportunity to have the dispute or disputes referred to
arbitration. On the other hand, in the case of excepted matters, this
two-tier system was not available and the decision of the architect was
final and binding without either party having recourse to any further
appeal or arbitration. The result of this is that excepted matters are not
arbitrable. It is an admitted position that claim No.1, which is the bone
of contention in the present petition, fell within the area of excepted
matters. As such, in terms of contract between the parties, claim No.1
was not arbitrable. But, the matter does not rest here.
6. The respondent No.1 had alleged that in connivance with the
said architect, the petitioner procured incorrect certification from him
on the strength of which the petitioner claimed payments against jobs
even though the same had not been executed at all. Consequently, as a
result of such illegal and fraudulent act on the part of the petitioner, in
collusion with the said architect, the respondent No.1 was put to great
financial loss running into several lakhs of rupees. Faced with such a
situation, the respondent No.1 terminated the services of the said
architect on 29.06.1997 which was conveyed to the said architect on
22.07.1997. Shortly thereafter, on 18.08.1997, the respondent No.1
also terminated the agreement dated 14.04.1989 which had been
entered into with the petitioner.
7. Since there were disputes which required resolution, the
respondent No.1 was of the view that, as the services of the said
architect had been terminated in the circumstances indicated above, and
there was no architect in place to take a decision either as to the
excepted matters or the other matters as provided under the contract,
the proper course would be to file a petition under Section 11 of the
said Act and seek the appointment of an independent arbitrator in
respect of all the matters, including those which were otherwise
excepted. On 16.09.1997, the respondent No.1, therefore, filed AA
228/1997 under Section 11 of the said Act for the appointment of an
arbitrator.
8. In the said petition, the respondent No.1 had, inter alia,
stated that one of the disputes which required resolution was with
regard to "the respondent (petitioner herein) failing to execute specific
jobs against which they fraudulently received payments in connivance
with the architect, M/s Govardhan Kundi and Associates, the value of
the same as on date is nearly - Rs 15 lacs". In the said petition, the
respondent No.1 also stated that it had already terminated the contract
of the said architect for his failure to honestly perform his part under
the contract. It was, therefore, submitted that as the said architect
would himself be an aggrieved party, he would not be in a position to
function as an honest, unbiased adjudicator of the disputes between the
parties. It was contended that since there is a named arbitrator, i.e., M/s
Govardhan Kundi and Associates in the contract between the parties
and that as the said arbitrator cannot function in an unbiased manner, it
was a fit case for the appointment of an arbitrator under Section 11 of
the said Act. It was, therefore, prayed that an order of reference be
made to the arbitrator after appointing him and all disputes and
differences between the parties arising out of the contract be referred to
such arbitrator.
9. During the pendency of the said petition under Section 11 of
the said Act, on 15.10.1997, the respondent No.1 filed an application
under Section 9 of the said Act seeking the appointment of a Local
Commissioner to take measurements because the petitioner was not
coming forward for joint measurements. It was contended that the
measurements were necessary because the entire case revolved around
fraudulent and false certification with regard to the extent of the works
done by the petitioner. By an order dated 27.10.1997, a learned single
Judge of this court passed an order appointing a Local Commissioner
for the purposes of taking measurements and the Local Commissioner
submitted his report on 24.03.1998. The petitioner filed its reply to the
respondent No.1‟s said petition under Section 11 on 08.04.1998. The
petitioner had specifically taken the plea that reference to arbitration
should be limited to only those matters which are covered by the
arbitration clause 44.
10. However, by a consent order dated 28.05.1998, the said
petition under Section 11 of the said Act was disposed of in, inter alia,
the following manner:-
"This petition can be disposed of at this stage itself. It has been agreed between the parties that all the disputes and differences arising out between the parties shall be referred for the arbitration. It has also been agreed that the dispute regarding steel not mentioned in the petition by the petitioner shall also be referred for the adjudication of the Arbitrators. It has also been agreed that the respondent shall also be entitled to raise any dispute before the Arbitrators including the objections to the report of the Local Commissioner appointed by this Court. ..."
xxxx xxxx xxxx xxxx xxxx
"Counsel for the respondent has suggested the name of Brig. Mr M.M.S. Parihar, retired Chief Engineer, MES as the Arbitrator on their behalf. Mr Chatterjee prays for some time to supply the vacancy on their behalf. Let vacancy be supplied on their behalf within two weeks.
I appoint Mr. R.S. Jindal, retired Chief Engineer of DDA as the Umpire. Let notice be sent to the Umpire by the Registry. Fees shall be decided by the Arbitrators/Umpire themselves. ..."
11. On 19.06.1998, a joint letter was issued to the presiding
arbitrator by the petitioner and the respondent No.1. The said letter
reads as under:-
"Subject: Arbitration of the Disputes between M/s Abhinav Co-op. Group Housing Society Ltd. And M/s Uppal Engineering Co. Pvt. Ltd.
Sir, The Hon‟ble High Court vide its order dt. 28.5.98 has appointed you as the Umpire in arbitration proceedings in the above noted case and has also recorded that Brig. (Rtd.) M.M.S. Parihar, Chief Engineer (Rtd.) (M.E.S.) has been nominated as the Arbitrator by the respondent M/s. Uppal Engineering Co. Pvt. Ltd. The Abhinav Co-op. Group Housing Society Ltd. has been allowed to supply the vacancy of the Arbitrator on their behalf within 2 weeks.
The Contract clause on Arbitration in the case envisages appointment of Architects, who should be Fellow of the Institution of Architects, as Arbitrators by the parties. However, we have agreed to the appointment of Engineers in place of Architects by the Society as well as by the Contractor. Therefore, the appointments of Brig. (Rtd.) M.M.S. Parihar as Arbitrator by the Contractor i.e. M/s. Uppal Engineering Co. Pvt. Ltd. and that of Shri C.S.P. Sastri, Director of Works (Rtd.), CPWD as Arbitrator by the Abhinave Co-op. Group Housing Society Ltd. are acceptable to both the parties and we agree to the proceedings conducted by the Arbitrators and the Umpire, who has been appointed by the Hon‟ble High Court.
Thus, we agree that the arbitration tribunal shall consist of the following:-
1) Shri R.S. Jindal, Presiding Arbitrator
2) Brig. (Rtd.) M.M.S. Parihar, Arbitrator
3) Sh. C.S.P. Sastri, Arbitrator.
The arbitration shall be under Arbitration and Conciliation Act, 1996."
12. Claim No.1, as submitted by the respondent No.1 before the
arbitral tribunal, was the final statement of accounts after the contract
was terminated on 18.08.1997 for the work done by the petitioner
allegedly based upon the measurement of the works done and the rates
payable under the terms and conditions of the contract. Under this
claim, the respondent No.1 stated that an excess amount of Rs
3,80,40,473 was claimed and received by the petitioner on the basis of
false and incorrect certificates allegedly procured by the respondent
from the said architect. It was alleged on behalf of the respondent that
the payments had been made to the petitioner on the basis of the said
architect‟s certificates which were contrary to the terms of the contract
and were in respect of the works which had not been executed at all or
which were of substandard and inferior quality. It was also stated that
the petitioner had not cooperated with the respondent No.1 by coming
forward for taking joint measurements of the work existing at the site.
By virtue of the impugned award, the arbitral tribunal by majority (R.S.
Jindal, Presiding Arbitrator and C.P.S. Sastri, Arbitrator) came to the
conclusion that claim No.1 was arbitrable in the facts and
circumstances narrated above and that the respondent No.1 was entitled
to a sum of Rs 1,71,23,246/- under claim No.1. It was, inter alia, noted
in the award:-
"6. Broadly the above award of Rs 1,71,23,246/- is on account of the following excess payments made to the respondent on the basis of the claims made by the respondent to this effect and wrongly certified for payments by the then Architect M/s Goverdhan Kundi & Associates.
i) Rs 23,47,221/- Work claimed by the respondents certified for payment by the Architect M/s Goverdhan Kundi & Associates, paid to the respondent but not existing at site.
ii) Rs 79,14,698/- Excess payment claimed by the respondent for escalation under contract condition (CPWD Clause 10CC-Annexure XVI) wrongly certified for payment by the Architect and paid to the respondent.
The total amount paid to the respondent as escalation Rs 1,70,08,934/- and that payable under CPWD Clause 10 (CC) is 90.51.086/- i.e. Rs 86,70,184/- for the agreement items Rs 4,24,052/-
for Extra items 10 to 15 90,94,236/-
iii) 18,64,135 Less Recoveries for the materials
issued by claimant for respondent
Cement 4,58,100/-
Steel 13,05,331/-
Bricks 1,00,704/-
18,64,135/-
iv) 45,800/- Electricity Bill liable to be
recovered from respondent
v) 49,51,392 Excess cheque payments received
1,71,23,246 by respondent by way of advances
etc."
13. The petitioner has challenged this finding of the arbitral
tribunal on the grounds mentioned above. The order dated 28.05.1998
is admittedly a consent order. The parties had agreed that all the
disputes and differences between the parties be referred for arbitration.
It must be recalled that the respondent No.1 sought arbitration even in
respect of the excepted matters in view of the exceptional circumstance
of the services of the architect having been terminated for having
allegedly colluded with the petitioner. In response to this, the
petitioner had contended that only those matters which were arbitrable
under the contract be referred to arbitration. Despite these rival
contentions, the petition was disposed of by the consent order that all
the disputes and differences between the parties be referred for
arbitration. I my view, the petitioner cannot be permitted to resile from
this position by now contending that the expression "all the disputes
and differences" has reference only to disputes and differences which
were arbitrable under the contract between the parties. It must also be
noted that the order dated 28.05.1998 also indicated that the parties had
agreed that the dispute regarding steel which was not mentioned in the
petition by the petitioner shall also be referred for adjudication of the
arbitrators. This part of the order read with the earlier part leaves no
manner of doubt that all disputes and differences which found mention
in the petition had been agreed to be referred to arbitration. This
conclusion is further supported by the fact that the order also records
that the parties had agreed that the petitioner would be entitled to raise
any dispute before the arbitrators, including the objections to the report
of the Local Commissioner appointed by the court. It will be recalled
that the Local Commissioner had been appointed by virtue of an order
dated 27.10.1997 in an application filed by the respondent No.1 under
Section 9 of the said Act for the purposes of taking measurements. The
object of which, was specifically for the purposes of noting the actual
extent of work executed by the petitioner and fell entirely within the
scope of claim No.1. Clearly, it was within the contemplation of the
parties that claim No.1 would be adjudicated upon by the arbitrators.
In Milkfood Limited v. M/s GMC Ice Cream Pvt. Ltd & Others:
83(2000) DLT 130, it was observed that where both the parties gave a
clear consent to refer the matter to arbitration before the High Court,
"the parties by agreement gave a good-bye to all other proceedings
and ... agreed for reference of the disputes to the arbitrator. The
sanctity of the undertaking given to the court by the parties has to be
maintained. No one can be permitted to breach or flout the
undertaking in this manner".
14. The joint letter issued on 19.06.1998 further constitutes a
written agreement for reference to arbitration in terms of the order
dated 28.05.1998. If there was any doubt as to whether there was an
arbitration agreement of the kind required by Section 7 of the said Act,
the said letter dated 19.06.1998 removes any such doubt. In these
circumstances, I am of the view that the submission of the learned
counsel for the petitioner that claim No.1 was not an arbitrable dispute,
is untenable.
15. An alternative plea had been raised by the learned counsel
for the petitioner that even if it were held that the parties had consented
for arbitration of claim No.1, such a consent was clearly based on a
misrepresentation. This argument was advanced in the context of the
respondent No.1‟s claim in the Section 11 petition being limited to Rs
15 lakhs, whereas in the claim filed by the respondent No.1 before the
arbitral tribunal, a sum claimed was Rs 3,80,40,473/- (which was later
on amended to Rs 2,92,58,702/-). This submission cannot be accepted.
The sum of Rs 15 lakhs was claimed by the petitioner, "as on date".
The measurements had not been done at that point of time and it is only
upon the Local Commissioner‟s report that the respondent No.1 came
to learn of the extent of the excess payments made by it on account of
the false certificates given by the said architect. In any event, no such
plea was raised by the petitioner before the arbitral tribunal and,
therefore, it cannot be permitted to agitate this issue before this court.
It must also be pointed out that this alternative plea of consent by
misrepresentation was raised by the learned counsel for the petitioner
in the course of arguments. This has not been pleaded either before the
arbitral tribunal or even in the present petition.
16. On the question of limitation, the learned counsel appearing
for the respondent No.1 had, as noted above, placed reliance on the
decision of the Supreme Court in the case of ONGC v. M.C. Clelland
Engineers S.A. (supra). In that case, the plea of limitation had been
taken in the following manner:-
"The present arbitration itself is barred by limitation as the alleged claims are relating to the work done in 1981-92".
The Supreme Court considered such a statement to be a bald statement
without any details and observed as under:-
"This is a very bald statement without setting out the details as to how the claim made by the respondent before the Arbitrators have become barred by the limitation particularly when the stand of the respondent is that they had running bills and payments were made from time to time and an account has to be taken as to what amount became due and when; the same has to be worked out. Whether all such details have to be worked out and whether the transactions between the appellant and the respondent did not become complete until the payment of final amount are matters for adjudication. Thus, it becomes very difficult to appreciate that the plea raised before the Arbitrators was sufficient to meet the situation to defeat the claim
on the bar of limitation. Therefore, we do not think that we can examine the matter in the light suggested now by the learned senior counsel for the appellant when no foundation has been laid in the course of the proceedings before the Arbitrators either in the pleadings or in the evidence. We are, therefore, of the view that the High Court was justified in dismissing the appeal against the decree passed in terms of the award."
17. The plea of limitation taken by the learned counsel for the
petitioner is that a total amount of approximately Rs. 8.23 crores was
the value of the work done as per the respondent‟s case. It is submitted
that out of this amount, the value of the work done upto 16.09.1994 (a
date, three years prior to the date of filing of the respondent No.1‟s
Section 11 application on 16.09.1997) in respect of which payments
were made before that date, was Rs 5.63 crores. Therefore, according
to the petitioner, the value of the work in respect of which the claim
could at all have been made would be approximately Rs 2.60 crores (Rs
8.23 crores - Rs 5.63 crores = Rs 2.60 crores). Consequently, it was
contended on behalf of the petitioner that if the alleged excess payment
in respect of Rs 8.23 crores has been computed at approximately Rs
1.71 crores, then, proportionately, even if the award were to be
sustained on merits, the only amount which could be awarded keeping
in view the law of limitation would be approximately Rs 50 lakhs.
Such a viewpoint cannot be accepted. When a party takes up the plea
of limitation and / or time barred claims, it must do so with precision.
The court, also, before it can come to the conclusion as to whether a
claim is time barred has to know the exact extent of the claim which
falls within the zone of limitation and that which falls outside such
zone. Specific pleas have to be taken and the issue of time barred
claims cannot be decided on assumptions and on applying principles of
proportionality. Thus, even de hors the question that in an arbitration
by consent, the plea of limitation cannot be raised (See: National
Building Construction Corporation Limited v. Decor India Pvt Ltd:
2004 (74) DRJ 159), the petitioner‟s arguments on the issue of time
barred claims cannot be accepted.
18. On the issue of agency, I find that this impinges upon the
merits of claim No.1. The arbitral tribunal has considered the evidence
on record and has returned the finding thereon. The question as to
whether the said architect acted as an agent of the respondent or not is
not relevant at this stage. The arbitral tribunal has concluded that the
certification was false and that on account of this, the respondent was
entitled to the sum of Rs 1,71,23,246/- which had been paid in excess
by it to the petitioner. Such findings cannot be challenged in a petition
under Section 34 of the said Act inasmuch as that would entail this
court sitting as a court of appeal. In any event, as pointed out earlier,
the petitioner itself in its reply to the respondent No.1‟s claim before
the arbitral tribunal had taken the stand that the said architect was not
an agent of the respondent. It cannot be permitted to submit to the
contrary at this stage.
19. Finally, on the question of the decision making process of
the arbitrators, it is apparent that one of the arbitrators did not agree
with the other two. The so-called notification which has purportedly
been signed only by the presiding arbitrator is now of no consequence
inasmuch as the entire issue with regard to arbitrability of claim No.1
has been discussed and decided in the award itself which has been
signed by the arbitrators. This objection on the part of the petitioner is
also unacceptable.
20. In view of the foregoing, no ground for interference with the
impugned award is made out. The petition is dismissed. No costs.
BADAR DURREZ AHMED (JUDGE) July 03, 2008 dutt
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!