Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Satish Kumar vs Uoi & Others
2008 Latest Caselaw 1160 Del

Citation : 2008 Latest Caselaw 1160 Del
Judgement Date : 28 July, 2008

Delhi High Court
Satish Kumar vs Uoi & Others on 28 July, 2008
Author: Reva Khetrapal
                                        REPORTED
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+     CS(OS) 1829A/1999

                                  DATE OF RESERVE:         May 06, 2008

                                  DATE OF DECISION:        July 28, 2008



      SHRI SATISH KUMAR                           ..... Plaintiff
                                  Through: Mr. Vivekanand, Advocate.



                         versus

      UOI & ORS.                              ..... Defendants
                                  Through: Mr.R.C.Nangia, Advocate



      CORAM:
      HON'BLE MS. JUSTICE REVA KHETRAPAL

1.    Whether reporters of local papers may be allowed
      to see the judgment?
2.    To be referred to the Reporter or not?

3.    Whether judgment should be reported in Digest?



      JUDGMENT

: REVA KHETRAPAL, J.

1. The petitioner was awarded a contract for "Repairs to Passenger Platform

Service with Bitumastic Flooring on Platform No.2 at Saharanpur" vide work

order No.128-W/280/DEN-I/UMB dated 27.02.1992 by the respondent/Union of

India. By a letter dated 15.06.1995, the Union of India, through the General

Manager, Northern Railway, New Delhi appointed Shri Jagdeep Rai, Dy. Chief

Engineer/Const./Works, Northern Railway and Shri A.K.Lal, Dy. F.A. &

CAO/Const., Northern Railway, Delhi as Co-Arbitrators to adjudicate upon the

disputes. The said Co-Arbitrators, as per terms of reference, jointly requested Shri

Raj Kumar Sarkar, Dy. Chief Engineer/Deposit Work, Northern Railway, Patel

Nagar, New Delhi to act as Umpire vide letter No.94/Arb./JR-11 dated 29.6.95

which he agreed to act on 3.7.1995. The Co-Arbitrators entered into the reference

on 23.11.1995, but did not hold any hearing during the period of validity, that is,

four months from the date of entering into the reference. Accordingly, the

petitioner invoked the arbitration clause and requested Shri Raj Kumar Sarkar to

enter into the reference and to act as Umpire vide his letter dated 28.03.1998.

Shri Raj Kumar Sarkar entered into the reference on 5.4.1999 and after having

heard the parties and gone through the material on record, gave his award on

23.7.1999, thereby allowing the claims of the petitioner to the extent of

Rs.60,395/- (Rupees Sixty Thousand Three Hundred Ninety Five only) with

simple interest @ 12% p.a. on Rs.51,690/- (that is, Rs.60,395/- minus Rs.8705/- =

Rs.51690/-) from 1.10.92 till the date of payment. The learned Umpire further

held that if the awarded amount was not paid within a period of 75 days from the

date of publishing of the award, the respondent would be liable to pay interest @

18% to the contractor till the payment of the award amount. The learned Umpire,

however, rejected the counter claim of the Railways to the tune of Rs.15,000/-.

2. The respondent/Union of India has filed the present objections to the

award under Sections 30 and 33 of the Arbitration Act, 1940 on the ground that

the learned Umpire mis-conducted the proceedings, inasmuch as he could not

have awarded the said amount in accordance with the specific clauses of the

agreement and also as per the evidence available with him. The award of the

learned Arbitrator is, therefore, stated to be against the facts on record and bad in

law. The award is also stated to be based on conjectures and surmises. Finally, it

is submitted that by interpreting the clauses of the agreement in a manner

different from the original agreement, the learned Umpire has exceeded the terms

of reference. Thus, according to the Union of India, claims No.1,2,4 & 5 were

wrongly allowed by the arbitrator, while the counter-claim of the Railways was

wrongly dis-allowed and accordingly the award of the learned arbitrator was

liable to be set aside under the provisions of Sections 30 and 33 of the Arbitration

Act, 1940.

3. The petitioner/contractor has filed a detailed reply to the objections

denying the objections in seriatum and praying for the dismissal of the objections

with costs and for making the award the rule of the court with further interest @

18% p.a. from the date of decree till the date of the payment.

4. It is proposed to deal with the objections of the respondent/UOI claim-wise

and the same are accordingly dealt with as follows:-

Claim No.1:

5. The first Objection is with regard to the claim No.1, whereby the learned

arbitrator against the amount claimed of Rs.80,000/-, awarded a sum of

Rs.10,000/- in respect of the work done. It is stated by the Objector that in

accordance with Clause-45 of the General Conditions of Contract, which was part

of the agreement between the parties, the measurement of work recorded between

the parties was final and binding. Any claim in regard to measurement or any

claim for work which was not according to the measurement, being an 'excepted

matter', could not be awarded by the arbitrator. By awarding claim No.1, the

learned arbitrator has given an award contrary to the agreement between the

parties. It is also contended that the reasoning given by the learned arbitrator is

vague and baseless.

6. In reply it is denied that the dispute with regard to claim No.1 was an

'excepted matter'. It is submitted that the respondent took no plea of 'excepted

matter' either before the Court at the time of making of the order of reference by

the Court or before the learned Arbitrator. As per the recorded measurement, the

claimant was entitled to Rs.42,681.72 for work done after deducting the running

payment, the details whereof were filed before the arbitrator. Without issuance of

any show cause notice or intimation in writing, some of the measurements were

later on, behind the back of the claimant, struck off by the respondent on the

allegation of alleged defects. There were letters and material on record to show

that the claimant had rectified the defects. It was also an admitted case of the

respondent that the work as done by the claimant had been put to use and was

being utilized by the respondent without dismantling the same or without further

rectification, either departmentally or otherwise. Thus, the learned arbitrator,

keeping in view all the facts and circumstances, awarded a sum of Rs.10,000/- to

the claimant, though a much larger amount was claimed.

7. A perusal of the counter statement of facts on behalf of the respondent/UOI

filed before the learned arbitrator shows that it was nowhere pleaded by the

respondent that claim No.1 was in the category of 'excepted matters'. The plea of

the learned counsel for the respondent that Claim No.1 fell in the category of

'excepted matters' cannot, therefore, be entertained at this stage. Such a plea is

also not sustainable in view of the judgments of the Hon'ble Supreme court in

J.G.Engineers (P) Ltd. Vs. Calcutta Improvement Trust AIR 2002 S.C 766 and

Narain Prasad Lohia Vs. Nikunj Kumar Lohia 2002(1) Arbitration Law

Reporter (RLR) 493 (Supreme Court), wherein applying the principal of waiver,

it was held by the Hon'ble Supreme Court that the respondent not having taken the

objection with regard to the non-arbitrability of the claim before the arbitrator or

any objection that the said claims were 'excepted matters' and having contested

the claims on merits, is estopped from raising such an objection after having

suffered the award.

8. The learned arbitrator's finding that during discussion the respondent

agreed that defects of some portions were removed by the claimant and, therefore,

the claim was being partly allowed to the extent of Rs.10,000/- as against the

claim of Rs.80,000/-, cannot, therefore, be faulted, more so, as the learned

arbitrator has reasoned that though the respondent had entered the measurement of

the whole work done by the claimant in the measurement book, later some of the

measurements had been scored out on account of defects noticed. There is also

nothing on record to suggest that this scoring out in the measurement book was

done after issuance of notice to the claimant, in his presence. The amount has

been awarded on the basis of the measurement book and it is not the case of the

respondent that no measurement was recorded. The record also shows that by

letter dated 28.9.1992, the claimant had written to the respondent that the defects

had been rectified and that there was no rebuttal of this fact from the side of the

respondent.

Claim No.2:

8. Claim No.2 is towards idling of labour, staff, tools, plants and equipment

and additional expenses due to faults and failures of the respondent. Against the

claimed amount of Rs.4,15,000/- (Rupees Four Lacs and Fifteen Thousand only),

a sum of Rs.41,690/- only (Rupees Forty One Thousand Six Hundred Ninety

only) has been awarded by the arbitrator to the claimant with the following break

up:-

 Claim No.              Description of claims             Amount claimed     Amount
                                                              (Rs.)        awarded (Rs.)

2.            Idling of labour, staff , tools, plants and 4,15,000/-       41,690/-
              equipments and additional expenses
              due to faults and failures of respondent.

(i)           Double wages of 10 workmen                 72000/-           14400/-
              @ Rs.40 per day for 6 months.

(ii)          Salary of supervisor                       24000/-           4645/-
(iii)         Hire charges for T &P                      90000/-           18000/-
(iv)          Salary of watch & ward                     24000/-           4645/-
(v)           conveyance, rent, lodging, boarding        33000/-           Nil
              etc. for six months.                                         ________
                                                                           41690/-
                                                                           ________
              Reasons of the amount awarded

              After hearing the arguments of both
              claimant and the respondent and going
              through the records presented, the
              claim is partly awarded as shown
              against each item above due to non-
              removal of hindrances and non-
              availability of site during the day time
              which resulted in hindrances and
              labour output at site as also agreed by
              respondent.



9. The reasons recorded by the arbitrator for award of this claim are that due

to non-removal of hindrances and non-availability of site during the day time

which resulted in hindrances and labour output at site, "as also agreed by the

respondent", the claim was being partly awarded. The basis of this claim thus

appears to be that the site and the electricity were not provided to the contractor

within the stipulated period. In this context, apart from the fact that the learned

arbitrator has recorded that, the non-removal of hindrances and non-availability of

site during the day time was admitted by the respondent, the learned counsel for

the claimant has drawn my attention to an intimation sent by the Assistant

Engineer, Northern Railway, Saharanpur to the S.H.O/GRP/Police, Saharanpur

dated 27.04.1992 which is to the following effect:-

"Northern Railway

Office of the Assistant Engineer/N.Rly Saharanpur.

No.18-A/16/535 Dated 27/4/92

Sub: Repairs to pass, platform surface with bitumastic flooring of P F No.2 at SRE.

The above work is being carried out by Shri Satish Kumar, Contractor Saharanpur. Due to power cut in day time, the work is being done during night time.

Please allow contractor's labour (about 10 men) to work on the platform No.2 & 3 during night time so that the work may be completed well in time i.e. within target date.

sd/-

Assistant Engineer Northern Rly., Saharanpur."

10. The learned counsel for the claimant submits that in view of the fact that

the respondent was squarely to blame for the non-availability of the site during the

day time resulting in hindrances and increased labour output at the site, the

learned arbitrator was justified in granting claim No.2 in respect of idling

charges. He also points out that though the aforesaid charges were claimed for a

period of six months, the learned arbitrator has awarded the same for a period of

one and half month only.

11. The learned counsel for the respondent/UOI does not dispute the letter

dated 27.04.1992 or the fact that it was agreed to by the respondent before the

arbitrator that there was non-availability of site during the day time. This being so,

it is not understandable as to how the award of one and half month idling charges

on account of non-availability of the site to the claimant can be objected to by the

respondent. The contention of the respondent that the award of claim No.2 for idle

labour, staff, tools, etc. in the sum of Rs.41,690/- by the learned arbitrator is not

only contrary to the pleadings, but also against the record of the proceedings is,

therefore, clearly mis-placed.

Claim No.4:

12. In the context of claim No.4, the findings of the learned arbitration are as

follows:

 Claim No.               Description of claims                Amount       Amount
                                                              claimed      awarded
4.           Refund of earnest money/security deposit     Rs.2500/-
             (Earnest money deposited Rs.2500/-. Security
             deposit Rs.6383/-. Deduct electric bill for
             Rs.2678/-. Net amount payable Rs.8705/-).





  Claim No.                Description of claims                    Amount     Amount
                                                                   claimed    awarded
             Reasons of amount awarded.                                      Rs.8705/-
             As per the final bill prepared and entered in
             measurement book No.D-571/UMB/90 Page-99

by the respondent, security deposit of Rs.6383/-

has been deducted from the Ist running on account bill and out of E/money of Rs.5000/-, the respondent has adjusted Rs.2400/- as security deposit and an amount of Rs.2678/- is to be deducted for electricity as per electric bill from claimant. Thus, the respondent will pay Rs.8705/- to the claimant (i.e. Rs.6383/- + Rs.5000/- = Rs.11383/- minus Rs.2678/- = Rs.8705/-). This has already been accepted by the respondent during the arguments.

13. At the outset, the learned counsel for the claimant explained that though the

claim under this head was made for earnest money deposited in the sum of

Rs.2,500/-, the learned arbitrator has also dealt with the security deposit under this

head. It was elaborated by him that it was not that the security deposit was not

claimed before the arbitrator, but that the arbitrator instead of dealing with it in

claim No.1, has dealt with it in claim No.4.

14. A somewhat feeble attempt was made by the learned counsel for the

respondent to urge that the learned arbitrator was not justified in awarding the

aforesaid claim. The learned counsel for the petitioner, on the other hand, has

drawn my attention to page 171 of the records, which contains handwritten notes

with regard to the payment due to the contractor. The said handwritten records are

on the letter-head of the Northern Railway and read as follows:

"NORTHERN RAILWAY

Dy. Chief Engineer/Const.

N.rly, Tilak Bridge Sh.R.K.Sarkar

Payment due to the contractor for "Repair to Passenger Platform service with bitumastic flooring of Platform No.2 at Saharanpur.

        (i)    Security 10%               Rs.6383.00 (against
                                                     CCI for Rs.63831)
        (ii)   Earnest money              Rs.5000.00
               (which was later on
               adjusted as security
                deposited for Rs.2400/-) __________
                              Total =    Rs.11383.00
                                         __________

        Deduction for Electric
        Bill charges                      Rs.2678.00
                                          __________
               Net Amount Payable =       Rs.8705.00
                                          __________
                                          (Eight Thousands Seven
                                                 Hundred & Five only)"

15. Clearly, the findings of the learned arbitrator are based on this document

which emanates from the Northern Railway itself and was not disputed by the

counsel for the respondent before the lelarned arbitrator. The award of the claim

is, therefore, to my mind, being challenged for the sake of challenge.

Claim No.5:

16. The learned counsel for the respondent submits that interest @ 12% from

01.10.1992 till the date of payment could not have been awarded by the arbitrator

on the amounts awarded for claim No.1,2 & 3, as no interest as per Clause 16(2)

of the General Conditions of the Contract was payable to the contractor and on

this ground also the award of the learned arbitrator is liable to be set aside. This is

disputed by the counsel for the petitioner, who states that in terms of the award,

the claimant is now entitled for the enhanced rate of 18% p.a. According to him,

the alleged clause in any case is not a bar on the power and jurisdiction of the

court to award interest, and the legal position is well settled that the arbitrator has

the power, authority and discretion to award interest for all the periods on the

amounts found due and payable by the arbitrator. Further, the respondent before

the learned arbitrator had placed no reliance on clause 16(2) and could not,

therefore, do so at this stage.

17. There is, in my view, no merit in this objection either. The Hon'ble

Supreme Court in the case of State of U.P. Vs. Harish Chandra and Co. reported

in 1999 1 SCC 63 has laid down that any bar provided in the contract on payment

of interest, is not a prohibition against the contractor to raise a claim for interest

before the arbitrator on claimed amounts and cannot operate as a bar on the power

of the arbitrator to award interest to the claimant on the amounts awarded in his

favour.

Counter-Claim:

18. Finally, the award was assailed by the respondent's counsel on the ground

that the counter-claim of the Railways for expenditure of Rs.15,000/- incurred

before the various fora was wrongly rejected. It was submitted that there was

delay on the part of the claimant and in fact there were lots of defects in the works

done by the contractors, on account of which the respondent had to incur expenses

for rectifying the same and the rejection of the claim of Rs.15,000/- of the

Railways was accordingly unjustified. The learned counsel for the petitioner, on

the other, denied that the respondent incurred any expenses in rectifying the

defects as alleged, and pointed out that no evidence had been adduced before the

arbitrator in this regard nor any amount was ever demanded by the respondent

from the petitioner on account of alleged rectification of defects, and that the

counter claim of the Railways before the arbitrator was, therefore, an after-

thought and was rightly rejected by the learned arbitrator as such.

19. A glance at the award shows that the counter claim of Rs.15,000/- was

rejected by the learned arbitrator on the ground that no termination of contract

was done nor the defects were got rectified by the Railways, either departmentally

or through any other agencies by the respondent and the respondent had failed to

produce any record for the amount claimed. This being the position, the rejection

of the claim of the respondent which was without particulars and in support of

which there is not even a scrap of paper, in my view, was wholly justified.

20. To conclude, in the present case, in my considered opinion, the arbitrator

cannot be said to have taken into consideration any matter outside the scope of

reference. The appellant has also failed to prove that the findings of the learned

arbitrator were without any basis or that such findings were patently unjust or

perverse. In the case of State of Rajasthan Vs. Puri Construction Co. Ltd. And

Another (1994) 6 Supreme Court Cases 485, relying upon its earlier judgments

in Sudarsan Trading Co. V. Govt. of Kerala (1989) 2 SCC 38; Municipal

Corporation of Delhi Vs. Jagan Nath Ashok Kumar (1987) 4 SCC 497; Alopi

Parshad & Sons Ltd. Vs. Union of India (1960) 2 SCR 793 : AIR 1960 SC 588;

Kapoor Nilokheri Coop. Dairy Farm Society Ltd. Vs. Union of India (1973) 1

SCC 708; India Oil Corpn. Ltd. Vs. IndianCarbon Ltd. (1988) 3 SCC 36; State

of Orissa Vs. Lall Bros. (1988) 4 SCC 153; Firm Madanlal Roshanlal Mahajan

V. Hukumchand Mills Ltd. (1967) 1 SCR 105: AIR 1967 SC 1030, it has been

held by the Hon' ble Supreme Court as under:-

"Even if it is assumed that on the materials on record, a different view could have been taken and the learned arbitrator has failed to consider the documents and the materials on record in their proper perspective, the award is not liable to be struck down in view of the plethora of case law to the effect that in the anxiety to render justice to the parties to the arbitration, the court should not re-appraise the evidence intrinsically with the close scrutiny for finding out the conclusions drawn from such facts by the arbitrator is, according to the understanding of the court, erroneous. Such exercise of power, it is well settled, is alien to the scope and ambit of challenge of award under the Arbitration act. Error apparent on the face of the record does not mean that on closer scrutiny of the import of documents and materials on record, the finding made by the arbitrator may be held to be erroneous. An error of law or fact committed by an arbitrator by itself does not constitute misconduct warranting interference with the award."

21. In view of the aforesaid legal and factual position, the petition is without

merit and is dismissed as such. The award is made rule of the Court. There will be

no order as to costs.

REVA KHETRAPAL, J

JULY 28, 2008 dc

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter