Citation : 2008 Latest Caselaw 1077 Del
Judgement Date : 21 July, 2008
* HIGH COURT OF DELHI
% Date of decision:July 21, 2008
+ FAO(OS) 2/1993
Delhi Development Authority ...Appellant
through
Mr.Bhupesh Narula, Advocate
Versus
M/s Harbans Singh & Sons ...Respondent
through
Mr.B.K.Sood with Mr.K.B.Soni,
Mr.Rajesh Kumar, Advocates
Coram :
Hon'ble Mr.Justice Manmohan Sarin
Hon'ble Mr.Justice Manmohan
(1) Whether reporters of local paper may be
allowed to see the judgment?
(2) To be referred to the reporter or not? Yes
(3) Whether the judgment should be reported Yes
in the Digest ?
Manmohan Sarin, J.
Appellant-DDA has preferred this appeal impugning the judgment
dated 17th September, 1992 passed by the learned Single Judge in Suit
No.2076-A/1990. The learned Single Judge dismissed the objections
filed by the appellant-DDA vide I.A No.11358/1990, against the arbitral
award dated 28th March, 1990. With the dismissal of IA 11358/1990
i.e the objections under sections 30 & 33 of the Arbitration and
Conciliation Act, 1940, the arbitral award dated 28th March, 1990, was
made rule of the court except that the award granting future interest
by the Arbitrator was set aside. The learned Single Judge while making
FAO(OS) 2 of 1993 Page 1 of page 11 the award rule of the court directed payment of interest @ 12% p.a on
the awarded amount in respect of claim nos.1 to 6 from the date of
award till payment. It was further ordered if the awarded amount of
Rs.7,86,245.08 together with interest @ 9% p.a and costs of Rs.5000/-
as awarded by the Arbitrator were paid within two months from 17th
September, 1992, the decree would stand satisfied.
2. Appeal was admitted to hearing on 4th January, 1993. The
Division Bench in CM 2/1993, vide orders dated 15th February, 1993,
directed the appellant-DDA to deposit the decretal amount in the form
of fixed deposit for a period of three years in the name of Registrar,
with interest component to be calculated @ 9% on the award within
eight weeks. The execution of the decree was stayed subject to said
deposit. Appellant accordingly furnished F.D.R in compliance with the
directions given. F.D. was further directed to be renewed for a further
term. On 7th April, 2005, none was present on behalf of the appellant
to press the appeal and the same was dismissed in default and the
amount lying in the Registry was directed to be released to the
respondent. In the event, appellant moved CM 14868/2007 for
restoration of appeal together with an application for condonation of
delay being CM 14869/2007.
3. For the reasons as set out in detail in our order dated 20th
February, 2008, appellant's applications for condonation of delay and
restoration of appeal were allowed and the appeal was restored to its
original number subject to payment of costs of Rs.10000/-.
4. Arguments were heard in appeal on 20th May, 2008 and
judgment reserved. We now proceed to decide the appeal.
FAO(OS) 2 of 1993 Page 2 of page 11 The relevant facts for appreciation of the appellant's contention in
appeal may be noted in brief:-
The offer of the respondent for supply of machine made
door/window, shutters estimated at Rs.50 lacs was accepted vide letter
dated 14th May, 1984 of the Chief Engineer, DDA. An agreement was
entered into between the parties on 16th August, 1984. In terms of the
agreement, shutters were to be supplied to the appellant within eight
weeks from 24th May, 1984 to 23rd January, 1985 at the agreed rates
stipulated in the agreement. The Chief Engineer of the appellant was to
make allocation to its different Divisions. The Executive Engineers of
the concerned Divisions were to confirm the particulars, size and
number of shutters required by them for their respective housing
schemes under the Division. Appellant made nine allocations between
the period from 29th May, 1984 to 18th February, 1986. The second
allocation made on 20th June, 1984 was cancelled on 11th October,
1984. The concerned Executive Engineers of the Division gave
confirmation against eight allocations between 16th June, 1984 to 12th
September, 1986. It was on receiving of confirmation that supplies
had to be made by the respondent. The contract period was to expire
on 23rd January, 1985. The supply on confirmations received on 26th
December, 1984 or thereafter could not be made before the expiry of
the contract on 23rd January, 1985.
5. It has come on record that appellant withheld certain payments
in the absence of extension of time and the respondent, therefore,
applied for grant of provisional extension of time under duress.
Respondent claimed to be entitled to enhanced rate for supplies made
FAO(OS) 2 of 1993 Page 3 of page 11 after the contractual period i.e 23rd January, 1985, claiming that they
were not bound to supply at the contract rate. The claims of the
respondent were disputed by the appellant, resulting in arbitration
clause being invoked. Mr.M.S.Telang was appointed as the sole
arbitrator to adjudicate upon the disputes/claims raised by the
respondent. Respondent raised six claims all on account of escalation
of timber price, seasoning costs and also claiming future interest and
cost of arbitration proceedings. The Arbitrator after perusal of the
pleadings and the evidence produced before him and hearing the
parties, awarded Rs.7,86,245.08 together with future interest @ 12%
and costs of Rs.5000/-. As noted earlier, objections filed were dismissed
by the learned Single Judge vide impugned judgment and the said
judgment is assailed in this appeal.
6. The main contention of Mr.Bhupesh Narula, learned counsel
appearing for the appellant is that as per the arbitration agreement, the
arbitrator was required to give his reasons in respect of the award for
any claim/dispute over Rs.50,000/-. The Arbitrator has singularly
failed to give his reasons for the amounts awarded. Counsel submits
that the Arbitrator has simply given his conclusions without reasons.
There is no reason justifying the quantum of award or indication in the
award as to how the amount awarded had been arrived at. Learned
counsel further contends that respondent has failed to lead any
evidence of the escalated costs or higher amounts being expended by
them in the acquisition of the material and in execution of the contract.
Learned counsel for the appellant referred to the letter dated 18 th
September, 1985, written by the respondent to the appellant wherein
FAO(OS) 2 of 1993 Page 4 of page 11 while noting that due to placement of orders and confirmation of sizes
after the expiry of contract period, delay had occurred. The respondent
was still cooperating with the Department in execution of balance
orders when the market rates had gone up by 25%. Respondent also
sought six months' time as 55% of the work was ordered six to eight
months after the expiry of contract. Respondent also protested against
payment being stopped because of extension of time not having been
applied for. Respondent sought issue of provisional time extension in
the interest of work so that they could resume supply. Learned
counsel for the appellant urges that use of expression by the
respondent that they were cooperating with the respondent, indicated
that they were willing to make the supply on the contracted rates and
were only seeking extension of time. The claim for enhanced rate was
thus an afterthought. Counsel further submitted that the Arbitrator
had erred in ignoring letters of the respondent dated 26.1.1985,
24.2.1986 and 15.12.1986 which showed that due to an accident
having occurred in the factory of the respondent and the non availability
of timber etc., work remained closed Appellant urged that these were
delays attributable to the respondent which were ignored.
7. On the first submission that the basis of amounts awarded not
having been disclosed the award suffered from vice of non giving of
reasons and simply conclusions being given, the appellant places
reliance on Gora Lal Vs. Union of India (2003) 12 SCC 459, College of
Vocational Studies Vs. S.S.Jaitley AIR 1987 Delhi 134. Regarding
ignoring of material documents and resultant misconduct, counsel relied
on Seth Mohanlal Hiralal Vs. State of M.P (2003) 12 SCC 144, Union
FAO(OS) 2 of 1993 Page 5 of page 11 of India Vs. Banwari Lal & Sons (P) Ltd (2004) 5 SCC 304, Ms.Bombay
Ammonia Pvt. Ltd Vs. Union of India AIR 1987 Delhi 148 to urge that
award suffered from non application of mind. Reliance was also placed
on Sathyanarayana Brothers (P) Ltd Vs. T.N.Water Supply & Drainage
Board (2004) 5 SCC 314 to urge that non consideration of relevant
writings and documents deprived a just and fair decision and vitiated
the award.
8. We have heard learned counsel for the parties, carefully perused
the arbitral award, the objections thereto, the impugned judgment and
the grounds of appeal and the submissions made before us. The
learned Single Judge in his judgment and the Arbitrator in the award
have clearly set out the facts which bring out that there was failure on
the part of the appellant to make allocation for the orders to be
executed in time and also delayed confirmation by the concerned
Executive Engineers of the Divisions, who were to confirm their
requirement of particular sizes of doors/window shutters in respect of
different Divisions. The Arbitrator has found that confirmation in
respect of housing scheme of 288 LIG houses was well within
reasonable time. However, confirmation in relation to 160 SFS houses
was sent on 26th December, 1984 which hardly gave one month time
to manufacture and supply thereof. The Arbitrator has found that
effectively only four allocations out of nine were made before 23rd
January, 1985 and confirmation in respect of one and a half of them
was made before the said date. All other allocations and the
confirmations were made in the extended period of contract. In view of
these clear and categorical findings of facts in the award which are
FAO(OS) 2 of 1993 Page 6 of page 11 based and supported by records, it is idle for the appellant to contend
that delay had occasioned on account of respondent, based on two or
three letters written wherein they had intimated the factum of an
accident in their factory and temporary closure flowing therefrom. The
said intimation may have explained the delay that was taking place in
manufacture and supply of the particular consignment in question. The
said letters do not dilute or negate the findings of breach or delay
having been occasioned in the execution of contract on account of
appellant. Moreover, the Arbitrator is the master of facts and law. He
has given clear findings of breach by appellant which cannot be assailed
in these proceedings. The judgments cited by the appellant regarding
non consideration of material documents would not be attracted and do
not advance the appellant's case in these circumstances.
9. This takes us to the second submission regarding the claim of the
respondent for payment at enhanced rates being not admissible under
the agreement and in view of the respondent having themselves applied
for extension of time which was granted without levy of compensation
or damages. The Arbitrator had found on examination of evidence that
the costs of machine made shutters were rising after the agreement
had been entered into. He also found that claimant/respondent applied
for extension of time not under free consent but only under duress and
the threats of withholding of eligible and due payments by the
appellant. Letter dated 18th September, 1985 on which reliance was
placed by the appellant and where the respondent mentioned the
factum of cooperating with the Department in executing the balance
orders, respondent had significantly pointed out that market rates had
FAO(OS) 2 of 1993 Page 7 of page 11 gone up by 25%. Respondent had also protested and described the
appellant's action unjustified in directing the Executive Engineer to stop
payment because extension of time had not been applied for. It was,
in these circumstances, that provisional extension of time was sought
for to resume supplies. The findings of the learned Arbitrator is in
consonance with the basis as unfolded and as noted by us it is a
finding of fact, which is not assailable. Similar is the position with
regard to finding reached by the Arbitrator that appellant committed
breach of the agreement as they failed to make allocations and
confirmation in sizes before the stipulated date and the respondent was
thus entitled to receive suitable compensation.
10. Let us now consider the last contention of the appellant with
regard to award being vitiated by non giving of reasons and only the
conclusions having been given. The learned Single Judge has duly
discussed and noted the decision as in College of Vocational Studies Vs.
S.S.Jaitley (supra). The learned Single Judge has held that the
Arbitrator has given ample reasons for the award of higher rates to the
respondent for the supplies made after the expiry of the stipulated
date of supply i.e 23rd January, 1985. The learned Single observed
that the Arbitrator had not explicitly stated as to how he worked out the
figure awarded by him against each claim. In other words, he had not
given the computation or quantification of the amount awarded. The
learned Single Judge with a view to satisfy his judicial conscience that
Arbitrator had applied his mind in making the award and findings and
conclusions were not arbitrary even went through the exercise to find
out as to how the amount against each of the claims on account of
FAO(OS) 2 of 1993 Page 8 of page 11 price rise of timber, rise in seasoning cost etc had been arrived at by
the Arbitrator. It was demonstrated before the learned Single Judge
that the amounts have been worked out on the basis of rates at which
the appellant had awarded tender on or about the dates of supply made
by the respondent. The Arbitrator's minutes of proceedings dated 8th
November, 1989, 9th January, 1990 and 16th January, 1990 and the
calculation sheets on pages 44 to 50 of the award file were perused by
the learned Single Judge to satisfy himself as to the basis of the award.
This exercise had been duly gone into. The learned Single Judge has
also noted that counsel for the appellant was confronted with this
position who did not dispute the explanation given by the counsel for
the respondent but only insisted that this basis of arriving at the
amount should have been mentioned in the award itself. Perusal of
the award as also the judgment of the learned Single Judge and the
proceedings sheet referred to him, have also been seen by us. We
have no reasons to reach a different conclusion than the one reached
by the learned Single Judge.
11. We may observe that the Arbitrator is required only to indicate his
thought process. As held out in Delhi Development Authority, New
Delhi Vs. M/s Alkaram, New Delhi AIR 1982 Delhi 365 and College of
Vocational Studies Vs. S.S.Jaitely (supra), an Arbitrator is not required
to give the details of his computation and give his mental meanderings.
It is sufficient if his thought process is indicated and the basis for
awarding the amount is disclosed. Reference may also be made to the
judgment of the Supreme Court in Indian Oil Corporation Ltd Vs. Indian
Carbon Ltd AIR 1988 SC 1340 where the court has considered the
FAO(OS) 2 of 1993 Page 9 of page 11 requirement of reasons being given for the award and the nature and
extent of such reasons. The court observed that "Arbitration process
should be quick and that quickness of the decision can always be
ensured by insisting that short intelligible indications of the grounds
should be available to find out the mind of the arbitrator for his action."
The award in the present case meets the said requirements. It would
perhaps help had the learned Arbitrator explicitly stated that the
computations were based on the rates at which the appellant itself had
awarded contracts to others at the relevant period. It would have
obviated the exercise which the learned Single Judge went through to
satisfy his judicial conscience with regard to the basis of computation
for the amount awarded. However, the absence did not introduce any
fatality in the award.
12. This is not a case where the findings of the Arbitrator is not
based on evidence. The purpose of arbitration is to provide a speedy
and economical remedy for commercial disputes. The Arbitrator is not
required to give detailed judgment or detailed reasons. Courts are not
required to go into the reasonableness of the reasons or sufficiency of
the reasons. The court is not required to reappraise the evidence and
sit as a court of appeal. In this case, it would be seen that award is
dated 19th March, 1990 and a period of nearly 18 years has elapsed
since then, such objections and pleas do not deserve to be
countenanced.
13. We may observe in addition that the Arbitrator has carefully
considered each item of claims and wherever required had not granted
or reduce the claim where the allocation was made before the stipulated
FAO(OS) 2 of 1993 Page 10 of page 11 date i.e 23rd January, 1985. It is only in cases where allocation or
confirmation of sizes was given by appellant belatedly which made the
execution impossible, before the stipulated date that compensation has
been awarded taking into account the rise in price of timber, rise in
seasoning cost, rise in fabrication cost and rise in truck freight.
Moreover adopting the rates at which the appellant itself had awarded
the work in competitive bidding to other parties during the
contemporaneous period was a rational method adopted for assessing
the enhancement in rates.
We, therefore, find no error or infirmity in the award or in
the impugned order. Needless to mention that none of the judgments
referred to in view of the discussion aforesaid and the facts as noted
would apply and advance the appellant's case.
Appeal has no merit and is liable to be dismissed. However,
on the question of award of interest, considering the prevalent rate of
interest and the rate as admissible for F.D's, counsel for the
respondent on behalf of the respondent has consented that post award
interest may be reduced to 8.25% p.a. We, accordingly, dismiss the
appeal subject to the modification in the decree that the interest shall
be @ 8.25% p.a from the date of award.
Manmohan Sarin, J.
Manmohan, J.
July 21, 2008 ssb FAO(OS) 2 of 1993 Page 11 of page 11
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!