Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Max Corona Enggs & Consultants ... vs M/S Mukund Engineers Ltd
2008 Latest Caselaw 1019 Del

Citation : 2008 Latest Caselaw 1019 Del
Judgement Date : 14 July, 2008

Delhi High Court
M/S Max Corona Enggs & Consultants ... vs M/S Mukund Engineers Ltd on 14 July, 2008
Author: Rajiv Sahai Endlaw
*IN THE HIGH COURT OF DELHI AT NEW DELHI

+
                  CS(OS) 27/2004


%                                Date of decision :     14.07.2008


 M/S MAX CORONA ENGGS &                             ......Plaintiff
 CONSULTANTS (P) LTD
                                 Through: Nemo.

                                  Versus


M/S MUKUND ENGINEERS......Defendant/Counter-claimant.
LTD
                            Through : Ms Juma Bose, Advocate



CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
     1. Whether reporters of Local papers may
        be allowed to see the judgment?

     2. To be referred to the reporter or not?

     3. Whether the judgment should be reported
        in the Digest?


RAJIV SAHAI ENDLAW, J (ORAL)


1.              The plaintiff filed a suit for recovery of Rs 12,47,204/-

from the defendant before the court of the Additional District Judge,

Delhi. The defendant filed its written statement alongwith counter

claim before the Additional District Judge before whom the suit was

pending. On 15th September, 2004 none appeared on behalf of the

plaintiff before the learned Additional District Judge where the suit

was initiated by the plaintiff and accordingly the suit of the plaintiff

was dismissed in default and the plaintiff was proceeded ex parte in




cs(os)27/2004                                             page no.1 of 5
 the counter claim of the defendant.        On subsequent date, it was

realized by the learned Additional District Judge that the counter

claim was in excess of the pecuniary jurisdiction of that court and

accordingly the counter claim was ordered to be placed before the

District Judge and the District Judge vide order dated 29th October,

2004 ordered the file to be placed before this court and directed

appearance before this court for the date fixed.


2.              Upon receipt of the file before this court, court notice

was ordered to be issued to the parties.         The defendant/counter

claimant appeared in pursuance to the said court notice. The order

dated 27th April, 2006 records that the counsel for the plaintiff had

been served with the court notice but the plaintiff had remained

unserved. The counsel for the plaintiff on whom the court notice

was reported to have been served, however, did not appear before

the court. Subsequently, the plaintiff was also served by affixation

at the last known address of the plaintiff but still none on behalf of

the plaintiff appeared before the court and the plaintiff was

proceeded ex parte (in the counter claim) again vide order dated

19th September, 2006 of this court. The counter claimant thereafter

led its ex parte evidence by filing the affidavit by way of

examination-in-chief of its Deputy General Manager Shri Ramesh L

Uttamani and by proving the documents Exhibit D1/1 to Exhibit

D1/24.


3.              The counter claimant has proved that the plaintiff had

represented that it was the manufacturer of Flexivinyl (UPVC)

sheets and was a specialist in undertaking water proofing works and

was having enough experience in laying lining of the reservoirs; on




cs(os)27/2004                                            page no.2 of 5
 the said representation of the plaintiff, the counter claimant placed

a work order dated 26th March, 2001 on the plaintiff for supply and

laying lining of 1mm UPVC sheets at the raw water reservoir site of

the counter claimant at M/s Godawari Sugar Mills Limited, Sameer

Wadi, Karnataka on the terms and conditions contained therein.

The said work order has been proved as Exhibit DW1/13.              As per

clause 10 of the said order, 70% of the price was to be released by

the counter claimant to the plaintiff on getting the details regarding

dispatch of materials by the plaintiff and the counter claimant was

to deduct an amount equivalent to 5% from the bills of the plaintiff

and which amount was to be returned to the plaintiff on expiry of

defect liability period of 12 months from the date of completion of

job. It is further a term of this work order that the plaintiff was to

do testing at site and the sheet which the plaintiff was to lay for

water proofing were to be manufactured strictly as per IS-2076-

1961 from Virgin Resins. The said work order further provides that

the plaintiff will give to the counter claimant standard performance

guarantee of 10 years for the sheets supplied and laid by the

plaintiff.


4.              The witness of the counter claimant has further deposed

that the quality of the work executed by the plaintiff was extremely

poor and the plaintiff did not carry out the tests.       It is further in

evidence that heavy leakages occurred throughout the central bund

of reservoir and the counter claimant had to engage consultant for

ascertaining the cause of leakage; it was found that the leakage was

from    the     field   seams   of   PVC liner laid by plaintiff and from

defects in PVC liner supplied by plaintiff and owing to damage




cs(os)27/2004                                             page no.3 of 5
 caused by plaintiff by puncture while laying the liner.             It is the

evidence of the counter claimant that the works of the counter

claimant were adversely affected owing to the aforesaid and the

overall time schedule of the project and commissioning of the plant

was delayed.       It has further been deposed that the plaintiff inspite

of repeated requests and reminders, did not take remedial actions

and ultimately the counter claimant informed the plaintiff that if the

plaintiff failed to carryout the rectification work, the counter

claimant would carry out the same at the costs and risk of the

plaintiff and the plaintiff was further informed that Rs 25-30 lacs

may have to be spent on the rectification work. The witness of the

counter claimant has deposed that the counter claimant has spent

Rs 25 lacs in arresting the leakage and has suffered liquidated

damages in the sum of Rs 2,48,000/-           and thus made the counter

claim of Rs 27,48,000/- together with interest at 18% per annum on

the plaintiff.


5.              I may at this stage notice that the plaintiff had instituted

the suit for recovery of balance amount stated to be due from the

defendant/counter claimant to the plaintiff for the works carried out

by the plaintiff. This suit, as aforesaid, was dismissed in default. It

is the case of the counter claimant that the plaintiff instituted the

suit as a counter blast to the aforesaid claims of counter claimant.


6.              The evidence of the witness of the plaintiff remains

unrebutted.       I have satisfied myself that the counter claim was

instituted within time.      The counter claimant had vide letter dated

15th February, 2002 (Exhibit D1/20) given notice to the plaintiff to

carry out the rectification work and the counter claim was filed on




cs(os)27/2004                                               page no.4 of 5
 9th July, 2004 and is as such within time. Moreover, the work order

placed by the counter claimant on the plaintiff and which was

accepted by the plaintiff, as noticed above, provided for the plaintiff

to guarantee performance for ten years. Yet another clause of work

order provided for 12 months as the defect liability period.


7.              The counter claimant has thus made out a case for

recovery of the sum of Rs 27,48,000/- from the plaintiff. However,

since the plaintiff did not contest the counter claim, the counter

claimant is held and entitled to interest at 6% per annum only from

the date of institution of the counter claim, till realization. The

counter claimant is also entitled to costs limited to court fees paid

on the counter claim. The counter claim is accordingly decreed.




                                          RAJIV SAHAI ENDLAW, J.

July 14, 2008.

cs(os)27/2004 page no.5 of 5

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter