Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gmr Infrastructure Ltd. & Anr. vs National Highways Authority Of ...
2008 Latest Caselaw 2257 Del

Citation : 2008 Latest Caselaw 2257 Del
Judgement Date : 16 December, 2008

Delhi High Court
Gmr Infrastructure Ltd. & Anr. vs National Highways Authority Of ... on 16 December, 2008
Author: Mukul Mudgal
*              IN THE HIGH COURT OF DELHI AT NEW DELHI

+                         W.P.(C) NO. 6792/2008

             Reserved on: 20th November, 2008

    Date of Decision: 16th December, 2008

GMR INFRASTRUCTURE LTD. & ANR.                         .....Petitioners

                        Through:     Mr. Arun Jaitley, Sr. Adv. with
                                    Mr. Atul Sharma and
                        Mr. Milanka Chaudhury, Advs.
Versus

NATIONAL HIGHWAYS AUTHORITY OF INDIA & ORS.            .....Respondents

Through:   Mr. Dushyant Dave and      Mr. Ramji Srinivasan, Sr. Advs. with Mr.
Ravi Kini,  Mr. Krishan Kumar,       Mr. Sumit Gupta, Mr. Mukesh Kumar, Ms.
Madhuri Diwan and Ms. Padma Priya, Advs. for respondent No. 1/NHAI.

         Mr. Gopal Subramanium, ASG with Mr. Gaurav Duggal and Mr. Chetan
Chawla, Adv. for respondent No.2/UOI.

With

+                        W.P.(C) NO. 6419/2008

MADHUCON PROJECTS PVT. LTD. & ANR.                     .....Petitioners

                                            Through:   Mr. C.A. Sundaram, Sr. Adv.
                                            with Mr. Amitabh Chaturvedy, Mr.
                                            Jeevesh Nagrath and        Mr. Mohit
                                            Chadha, Advocates.
Versus

UNION OF INDIA & ORS.                                  .....Respondents

Through:   Mr. Gopal Subramanium, ASG with Mr. Gaurav Duggal and Mr. Chetan
Chawla, Adv. for respondent No.1/UOI.

Mr. Dushyant Dave and      Mr. Ramji Srinivasan, Sr. Advs. with Mr. Ravi Kini,
Mr. Krishan Kumar,      Mr. Sumit Gupta, Mr. Mukesh Kumar, Ms. Madhuri Diwan
and Ms. Padma Priya, Advs. for respondent No. 2/NHAI.



CORAM:

HON'BLE MR. JUSTICE MUKUL MUDGAL
 HON'BLE MR. JUSTICE MANMOHAN
1.    Whether the Reporters of local papers may be allowed to see the
judgment?
2.  To be referred to the Reporter or not?
3.  Whether the judgment should be reported in the Digest?
%                         JUDGMENT
MUKUL MUDGAL, J.

1. The present petition challenges the letter No. NHAI/BOT/11012/66/2005/3940

dated 26th August, 2008 issued by the respondent no.1 National Highways

Authority of India (hereinafter referred to as 'NHAI') to the petitioner consortium

intimating the petitioner that it is not eligible to participate in the second stage of

the bidding process (the bid stage) in supercession of its earlier letter dated June

27, 2008 pursuant to which the consortium had been declared pre-qualified for

the project in question i.e. Design, engineering, construction, development,

finance, operation and maintenance of Hyderabad-Vijayawada section of the

National Highway 9 (hereinafter referred to as NH9) from KM 40.000 to KM

221.500 of NH 9 in the state of Andhra Pradesh under National Highways

Development Programme Phase IIIA on Build Operate and Transfer-toll Basis. The

petitioner No.1 GMR Infrastructure Ltd. had applied pursuant to the Request For

Qualification (RFQ), issued by the respondent No. 1 NHAI in December, 2007. It is

not in dispute that pursuant to the process of evaluation and after compliance of

the terms of the tender, and in particular Clause 3.5.2, the petitioner was short

listed as one of the six successful tenderers, entitled to be further considered.

2. A number of writ petitions have been filed challenging the tender issued by

the National Highways Authority of India, which can be broadly classified into

three parts. The first challenge through writ petitions relates to the petitioners,

i.e., those bidders, who were initially shortlisted but subsequently declared to be not eligible to participate in the second stage of the bidding process after the

revaluation. The second challenge relates to those bidders, who were initially not

shortlisted but subsequently allowed to participate in the second stage of the

bidding process. The third challenge through the writ petitions relates to the

petitioners Reliance Infrastructure Ltd. and DLF-Gayatri-Lor Joint Venture, i.e.,

those bidders, who did not qualify either through the initial evaluation at the

qualification stage and who also did not qualify after the revaluation was done.

The present writ petitions correspond to those bidders, i.e., WP(C) 6792/08 titled

as GMR Infrastructure Pvt. Ltd. & Anr. Vs. NHAI & Anr. and WP(C) 6419/08 titled as

Madhucon Project Pvt. Ltd. & Anr. Vs. UOI & Anr., who were declared qualified at

the initial stage i.e. the qualification stage but subsequently declared to be not

eligible to participate in the second stage of the bidding process after the

revaluation. In the present petition, the bidders who were initially not shortlisted

but subsequently allowed to participate in the second stage of the bidding process

namely M/s Cintra Concessions De In Infraestruras De Tranporte S.A. and M/s

Isolux-Soma-Omaxe Consortium were impleaded as respondents and Mr. Rajiv

Nayar, who appeared for M/s Isolux-Soma-Omaxe Consortium was also heard.

3. Since common issues of law arise in the present writ petition and the Writ

Petition(C) 6419/2008 titled as M/s Madhucon Projects Pvt. Ltd. & Anr. Vs. Union of

India and Anr. we are taking into account only the facts of the present petition,

which are as follows:-

(a) The Petitioner No.1 GMR Infrastructure Ltd. and its group companies together

are one of the fastest growing infrastructure organizations in the country with

interests in airports, energy, highways and urban infrastructure (including special economic zones).

(b) The Petitioner no. 2 Punj Lloyd Ltd. is in the business of Engineering,

Procurement, Construction /Developer. The various areas of operation of the

Petitioner No. 2 include Road/Highway and Bridge Construction, Industrial

Construction, Laying of Cross Country Pipelines, Tankage and Composite

Construction, EPC Contracts and Telecom Contracts.

(c) The Respondent No. 1 National Highways Authority of India is engaged in the

development of highways and as a part of this endeavor, the Respondent No. 1

decided to undertake development of four/six laning of Hyderabad - Vijayawada

section in the state of Andhra Pradesh from KM 40.000 to KM 221.500 of NH 9

through private participation on BOT basis and as such issued the RFQ in

December 2007 for selection of the preferred bidder/sponsor. By issuing the RFQ,

the Respondent No. 1 intended to pre-qualify suitable applicants who will be

eligible for participation in the bid stage for awarding the Project through open

competitive bidding process in accordance with the procedure set out in the RFQ.

(d) The Petitioner No. 1 and Petitioner No. 2 formed a consortium and entered into

a Joint Bidding Agreement dated 14th January, 2008 to participate in the bidding

process for the Project.

(e) As per the RFQ, the successful bidder shall be responsible for designing,

engineering, financing, procurement, construction, operation and maintenance of

the Project under and in accordance with the concession agreement to be entered

into between the successful bidder and the Respondent no. 1. The scope of work as indicated in the RFP would include rehabilitation, upgradation and widening of

the existing carriageway to four/six lane standards with construction of the new

pavement, rehabilitation of the existing pavements, construction of major and

minor bridges, culverts, intersections, interchanges, underpasses, drains etc.

(f) As per the RFQ, the Respondent No. 1 intended to follow a two stage process

for the selection of the preferred bidder for the Project which is as under:-

i. At the first stage (the Qualification

Stage) the interested parties are invited to furnish the

information specified in the RFQ document. Upon submission of

the documents and information of the document as contained in

the RFQ, Respondent No. 1 announces/shortlists a list of bidders

for the next stage (the Proposal stage) who are then invited to

submit detailed proposals in respect of the project in

accordance with the Request for Proposal (RFP) document.

ii. In the second stage (the proposal

stage) the shortlisted applicants are requested to examine the

project in further detail and submit Proposals along with a bid

security. The pre-qualified applicants in the second stage

submitting a Proposal in accordance with the RFP document,

would then be evaluated on the basis of technical, other

submissions and financial bids as detailed in the RFP

documents. As part of the RFP documents, the Respondent No.

1 shall provide detailed instructions for applicants relating to submission of the Proposals, a draft Concession Agreement and

project report/feasibility report containing other information

pertaining/relevant to the Project. The award of Project is based

on the lowest amount of grant sought from the Authority or the

highest premium/revenue share offered, as the case may be.

(g) Pursuant to the RFQ, the Petitioners, as a consortium, submitted a request for

qualification application dated January 19, 2008 to NHAI.

(h) Post evaluations of the RFQ Application, Respondent No. 1, vide its letter No.

NHAI/BOT/11012/66/2005/3349 dated June 27, 2008, conveyed to the Petitioners'

Consortium that the Consortium had been pre-qualified for the bid stage against

the RFQ Application submitted by the Consortium. In the very same letter, the

Petitioners' Consortium was called upon by the Respondent No. 1 to collect the

bid documents from July 2, 2008, onwards.

(i) Upon receipt of the above letter, the Petitioners' Consortium vide its letter

dated June 30, 2008 approached Respondent No.1 for issue of the RFP documents

but despite the Petitioners' Consortium tendering the requisite fee of Rs. 50,000/-

in the form of Bank Draft, the Respondent No. 1 failed/refused to accept the same

and also refused to issue the RFP documents.

(j) Thereafter, the Petitioners' Consortium received a letter from Respondent No. 1

bearing letter no. NHAI/BOT/11012/66/2005/3712 dated August 8, 2008, in terms

of which it was conveyed to the Petitioners' Consortium that in view of certain

representations in regard to the evaluation done by the Respondent No. 1,

although having been pre-qualified, the process of Petitioners' Consortium's pre-

qualification was being kept in abeyance and certain clarifications were sought from the Petitioners' Consortium in relation to their RFQ Application.

(k) In response to the same, Petitioners' Consortium vide their letter No.

GIL/BD/SV/08-09 dated August 13, 2008, inquired if Consortium's pre-qualification

was being reviewed due to representations received and also whether the criteria

for pre-qualification remain unaltered. Alongwith the letter of the Petitioners'

Consortium, the Consortium also furnished to the Respondent No. 1 the

clarification asked for them vide letter dated August 8, 2008.

(l) Another letter was received by Petitioner bearing letter No,

NHAI/BOT/11012/66/2005/3940 dated August 26, 2008, impugned in this petition,

conveying to the Petitioners' Consortium that based on the clarifications

submitted by the applicants, the Respondent No. 1 has re-evaluated/reviewed the

submitted applications for the RFQ and as a result of the same the Petitioner has

not been short listed for the Project and that it is not eligible to participate in the

second stage of the bidding process .

4. The main grievance of the petitioner as articulated by Mr. Arun Jaitley, the

learned Senior Counsel in the present writ petition is as follows:

(a) The process of evaluation has been done on the basis of the representations

made by unsuccessful applicants and the said representations were forbidden by

Clause 2.21 of the RFQ:

Clause 2.21 reads as follows:

"2.21 Short listing and notification-

After the evaluation of Applications, the Authority

would announce a list of short-listed pre-qualified

Applicants (Bidders) who will be eligible for participation in the Bid Stage. At the same time, the

Authority would notify the other applicants that they

have not been short-listed. The Authority will not

entertain any query or clarification from Applicants who

fail to qualify. (emphasis supplied)"

(b) Not only the representations from M/s Inolux Soma Omana Consortium, M/s

Reliance Infrastructure Ltd. and M/s Macquarie were entertained but also pursuant

to the said representations the petitioner was knocked out from the first six

names where he was placed subsequent to the initial evaluation in accordance

with Clause 3.5.2. The learned counsel for the petitioner has submitted that the

said representations and any action pursuant thereto are contrary to the mandate

of Clause 2.21.

(c) It has also been submitted that the receiving of the said representations from

the unsuccessful applicants amounted to 'an undesirable practice' as it clear from

Clause 4.2(d) of the RFQ:

Clause 4.2(d) reads as follows:

"(d) "Undesirable practice" means establishing contact with any person connected with or employed by the

Authority with the objective of canvassing, lobbying or

in any manner influencing or attempting to influence the

Bidding Process."

(d) It has also been submitted that Clause 2.18 of the RFQ mandates that all the

information submitted to the respondent no.1 shall be treated in confidence. The

representations made by the unsuccessful applicants, however, clearly indicate the breach of confidence, as the information qua the petitioner's tender is

available to the unsuccessful applicants.

(e) It is submitted that the petitioner's i.e. GMR Infrastructure Pvt. Ltd. project and

the construction work commissioned was not taken into account in order to

disqualify the petitioner. It has been submitted that the requirement of Clause

3.2.3(d) of the RFQ only required the commissioning of the constructed work and

payment there for. The commissioned project of the petitioner has not been

considered by the respondent on the ground that the project was not

commissioned.

(f) Even though the respondent no.1 sought the explanation which was

satisfactorily given by the petitioner, the marks for the projects in respect of

which clarification was given was not given including scores claimed by M/s

Sembawang Engineers and Constructors Pvt. Ltd., were not awarded. The

relationship between M/s Sembawang Engineers & Constructors Pvt. Ltd. pursuant

to the clarification sought by the respondent no.1 was given by the letter dated

13th August 2008 and that explanation was not taken into account. It is lastly

submitted that even if it is assumed that the Two Member Committee Report

could have been taken into account, the said recommendations have not been

fully implemented.

The said recommendations read as follows:

"(iii) As a result of above exercise there is likelihood of change in the shortlist of top six bidders. In case it is

decided to issue RFPs on the changed list of six

shortlisted bidders, this may lead to further representation and possible litigation. Under the

circumstances there could be two options for carrying

the project further:-

(a) NHAI Board may consider one time relaxation for

this particular package and may increase the number

of bidders in the shortlist to accommodate those who

qualify in the review exercise and whose experience

score in higher than the final score(after review) of the

present lowest scorer (M/s Madhucon-Galfar-SREI) in

the already declared shortlist. However, its implication

on other seven project packages where evaluation is

going on will also need to be kept in view as also the

legal implications.

(b) NHAI Board may consider annulling the whole

exercise and direct re-invitation of RFQ for this package

(Hyderabad-Vijayawada). This would also meet the

ends of justice as all prospective bidders would have an

opportunity to apply and be evaluated as per the

present evaluation procedure."

(g) The respondent accepted the first recommendation while brushing aside the

second recommendation and this could not been done. It is finally submitted that

there is a gross disparity of the marks awarded by the respondent no.1 for

different projects for almost same experience.

(h) The documents filed by the respondent No. 3 Cintra Concessions De In

Infraestruras De Tranporte S.A. and Shapoorji Pallonji & Co. Ltd. in reply to the

clarification sought on 8th August, 2008 clearly shows that the said documents

specifically the certificate issued by the Statutory Auditors were ready much before 8th August, 2008, i.e. on 24th July, 2008 and 28th July, 2008. The

respondent No. 3, therefore, had prior knowledge of the fact that clarification was

to be sought by the respondent No. 1.

5. The main grievances of the petitioner in WP(C) No.6419/2008 titled as M/s

Madhucon Projects Pvt. Ltd. & Anr. Vs. Union of India & Anr. as articulated by Mr.

C.A. Sundram, the learned senior counsel is as follows:

(a) The Government could not have directed NHAI to seek

clarifications because as per Clause 2.20, clarifications, if any, are to

be sought by NHAI on its own and not on the directions of the

Government. In terms of clause 2.20, it was in the discretion of NHAI

as to whether or not to seek clarifications. In other words, NHAI was

not obliged to seek clarifications. The defence taken by Union of India

(UOI) in its counter-affidavit that NHAI ought to have taken

clarifications is thus contrary to clause 2.20(i) of the RFQ.

(c) Such clarifications could not have been sought after the

completion of the shortlisting process. Clarifications, in terms of

clause 2.20(i) of the RFQ were meant for the purpose of facilitating

the evaluation of the applications. The evaluation process was

completed on 27th June 2008 when the shortlisted candidates were

declared. No clarifications could have been asked for or entertained

thereafter. Thus, in terms of Clause 2.20(ii) all the applicants were

barred from questioning the interpretation arrived at by NHAI.

Additionally, it needs to be noted that NHAI had sought clarifications

earlier, i.e. before completing the shortlisting and after receiving the response to such clarifications, NHAI evaluated the applications and

then announced the names of shortlisted bidders on 27th June 2008.

(d) No clarifications could have been sought by NHAI on the basis of

representations received by Government from applicants, who had

failed to qualify, which representations were forwarded by the

Government to NHAI for consideration, comment and subsequently for

further action of seeking clarifications. The making of any

representation to NHAI was specifically barred under clause 2.21,

which is reproduced as under:

"2.21 Short-listing and notification

After the evaluation of Applications, the Authority would

announce a list of short-listed pre-qualified Applicants

(Bidders) who will be eligible for participation in the Bid Stage.

At the same time, the Authority would notify the other

Applicants that they have not been short-listed. The Authority

will not entertain any query or clarification from Applicants

who fail to qualify."

(e) The entire decision making process was vitiated, defective,

illegal, and contrary to the terms of the RFQ. Further, once

clarification had been sought for, and decision was taken, the

applicants were debarred from questioning the interpretation of

NHAI. Once the decision was taken, no representation or clarification

could have been entertained from applicants who had failed to qualify

as per clause 2.21 of the RFQ.

(f) Once the evaluation process was completed and the short list

was declared by the letter dated 27th June 2008, NHAI had no further

role to play insofar as evaluation under the RFQ was concerned.

There is no power of re-evaluation of review given in the RFQ.

(g) The respondents, particularly UOI has stated in its counter

affidavit that in terms of clause 2.20 of the RFQ, NHAI could have

sought clarifications from applicants. Since, this was not done, UOI

directed NHAI to seek clarification. There is no provision in the RFQ

which gives UOI the power to supervise the tender process and

further clarification in terms of clause 2.20 could have been sought by

NHAI for the purposes of evaluation of the applications. It was in the

discretion of NHAI whether or not to call from clarification and NHAI

could not have been directed to do so. A necessary corollary is that

clarifications, if any, could have been sought only till such time that

the process of evaluation was not complete. Once the evaluation

process was completed and the short-list was declared, there was no

provision in the RFQ under which clarification could have been sought

or entertained and there is no provision under which UOI could have

directed NHAI to call for clarifications.

(h) The entire process of re-evaluation was undertaken on the basis

of representations received from the unsuccessful bidder, who had

not been shortlisted for the Bid Stage. This was contrary to the

express terms of the RFQ, namely clause 2.20(ii) which barred any

applicant from questioning the decision arrived at by NHAI after clarifications had been sought, and clause 2.21 thereof, which

provided that no clarification or query from any unsuccessful

applicant would be entertained.

(i) According to well established practice and procedure, NHAI had

no power to recall/review its order/decision once it had informed

petitioner that it had been pre-qualified for the Bid stage. NHAI by

seeking to consider representations received by from unsuccessful

applicants was acting in breach of Clause 2.21 of the RFQ. In terms of

Clause 2.21 of the RFQ, NHAI could not consider any representation

made by unsuccessful applicants. Furthermore, there was no

provision in the RFQ to keep the pre-qualification into abeyance.

(j) The arguments of the UOI regarding the inherent power of the

NHAI to carry out 're-evaluation or review', at least to the extent of

self-correction, to achieve the object of "seeking the best man for the

project" and the inter-linked argument of the inherent power of the

Government to intervene and direct NHAI to carry out 're-evaluation

or review', at least to the extent of self-correction, is wholly fallacious.

(l) The entertaining of representations from unsuccessful bidders;

constituting a committee to give recommendations; calling for

clarifications after the process of evaluation was over and list of short-

listed candidates had been declared; and carrying out re-evaluation,

was contrary to the terms of the RFQ and amounted to changing the

rules.

(m) The reliance by the respondents on Section 33 of National

Highway Authority of India Act, 1988 is totally misplaced since the

said section applies only to laying down of policy which admittedly in

the instant case is not applicable. The said section only permits the

issuance of a generic fiat on policy matters alone and does not permit

the issuance of person-specific directions based on individual

grievances brought to its notice. Should the said clause be read so

widely as to include the right to interference in every decision making

process with regard to award of any particular contract by giving a go-

by to the RFQ, the entire independence and autonomy of the authority

so created under National Highway Authority of India Act, 1988 would

be negated.

6. The learned Additional Solicitor General Shri Gopal Subramanium on behalf

of the Union of India (UOI) contended as follows:-

(a) By virtue of Section 3 of the National Highways Authority of India Act, 1988,

the NHAI has been constituted. Section 11 of the said Act empowers the Central

Government to vest in or to entrust to NHAI such national highway or stretch

thereof as may be specified in a notification to be published in the official gazette.

Proviso to Section 15 of the said Act states that no contract exceeding such value

or amount as the Central Government may prescribe shall be entered into by

NHAI without the prior approval of the Central Government. By virtue of Section

17 of the said Act, the Central Government has been empowered to provide any

capital that may be required by NHAI or pay to NHAI by way of loans or grants

such sums of money as it may consider necessary for the efficient discharge of the functions by NHAI. Section 21 of the said Act mandates that the consent of the

Central Government is necessary before NHAI borrows money from any source.

By virtue of Section 24, the Central Government has an obligation to place the

annual report and auditor's report of NHAI before each House of Parliament.

Section 31 empowers the Central Government to temporarily divest NHAI of the

management of any national highway if it is of the opinion that in the public

interest it is necessary to do so. Section 32 empowers the Central Government to

supersede NHAI in specified situations. Section 33 empowers the Central

Government to issue directions on questions of policy to NHAI and NHAI shall be

bound by such directions. Sections 37 states that the rules and regulations made

under the said Act have to be placed before each House of Parliament.

(b) A perusal of the aforesaid provisions of the National Highways Act, 1956 and

the National Highways Authority of India Act, 1988 and Government of India

(Allocation of Business) Rules, 1961 clearly shows that national highways vest in

the Central Government and NHAI is an implementing agency of the Government

of India in matters relating to development of highways. In the present case, the

highway in question vests with the Central Government by virtue of the Schedule

to the National Highways Act, 1956. A perusal of the 1988 Act clearly shows that

the Central Government has the power to ensure that NHAI functions efficiently

and in a transparent manner. The provision relating to the consent of Central

Government being required before NHAI enters into contracts of a specified value

and the provision mandating prior approval of the Central Government clearly

shows the role played by the Central Government in the functioning of NHAI.

(c) In the present case, in December 2007, based on the model RFQ published by the Planning Commission, NHAI invited applications from prospective bidders for

their pre-qualification of the project. As per clause 3.5.2 of the RFQ document

(which has been upheld by this Hon'ble Court), NHAI had the power to pre-qualify

and prepare a shortlist of 5 bidders which could go upto 6. NHAI constituted an

Evaluation Committee and took the help of financial consultants for carrying out

the evaluation. After the evaluation, 6 applicants were shortlisted and were

informed of the same by NHAI by letter dated 27th June 2008.

(d) After the shortlisting of the said 6 applicants, the Central Government received

representations from various unsuccessful applicants stating that they have been

wrongfully disqualified. On 2nd July 2008, the Central Government forwarded the

said representations to the Chairman, NHAI requesting him to look into the matter

and give his comments on the said representations. It was also requested that the

process of issue of RFP may be deferred by 10 days. On 4th July 2008, NHAI sent

its comments on the representations forwarded to it by the Central Government.

Along with the said letter, NHAI enclosed a representation received from another

unsuccessful applicant. In order to ensure that transparency is maintained, the

Central Government constituted a Committee on 11th July, 2008 consisting of two

members who were in the Board of NHAI to go into all the representations that

have been received. The report of the said Committee was required to be placed

before the NHAI Board which had to take a final decision in the matter. Since the

examination by the said Committee would take some time, the Central

Government by its letter dated 11th July 2008 requested the NHAI to defer the

issue of RFP. The two member Committee examined the matter and submitted its report on 28th July 2008. By a letter dated 29th July 2008, the Central Government

forwarded the report of the Committee to NHAI. It was requested that the said

report may be placed before the NHAI Board along with the

recommendations/comments of the Chairman, NHAI. On 7th August, 2008, the

Central Government sent a letter to NHAI requesting NHAI to obtain necessary

clarifications and to immediately re-evaluate the applications. NHAI was

requested to place the findings of the re-evaluation before the NHAI Board for a

decision in the matter. Accordingly, the applications were re-evaluated and the

result of the re-evaluation exercise was considered by the NHAI Board in its

meeting held on 19th August 2008 which decided to qualify the six most qualified

applicants pursuant to the re-evaluation.

(e) The aforesaid chronology of events has been described only to show that the

role of the Government in the entire exercise has been to ensure that

transparency and fair play are adhered to. As the administrative Ministry of NHAI,

it is the duty and obligation of the Ministry of Shipping, Road Transport and

Highways, Government of India to intervene to ensure that the process of

tendering takes place in a transparent manner. As submitted earlier, if any

questions are raised with respect to the tender process in Parliament, it is the

Ministry of Shipping, Road Transparent and Highways, Government of India which

has to answer the said questions in Parliament. The Government of India is not

concerned with individual applicants and is only concerned with the process of

arriving at the shortlist of six most qualified applicants. In a project of such

magnitude, it is in public interest that the most qualified applicant gets the

contract and it is the duty of the Government to ensure that NHAI undertakes the process in such a way that the most qualified applicant gets the project.

(f) There is a difference between 'intervention' by the Government and

'interference' by the Government in the functioning of NHAI. In the present case,

the Central Government has intervened by writing letters to NHAI forwarding the

representations received by the Government from unsuccessful applicants.

Further, the Government intervened by constituting a Committee consisting of

members of NHAI Board to look into the representations. The ultimate decision of

accepting the report of the said Committee was not that of the Government but of

the NHAI Board. The Government by its letters had only requested the NHAI Board

to take appropriate decision after considering the report of the Committee. The

ultimate decision for undertaking the re-evaluation based on the report of the

Committee was undertaken by the NHAI Board in its meeting held on 19th August,

2008. The attempt of the Petitioners to portray the intervention of the Central

Government to ensure transparency as interference in the functioning of NHAI is

misconceived.

(g) Therefore, it is submitted that the role of the Government was limited to

pointing out to NHAI the representations received by the Government and

constituting a Committee to look into the said representations. The argument that

the Government cannot intervene at all under any circumstance whatsoever in a

tender process being undertaken by NHAI is too farfetched and has far reaching

consequences. The Government definitely has a right and is in fact duty bound to

intervene if it is of the view that certain aspects need to be brought to the

attention of NHAI in order to ensure transparency and fair play. Needless to say,

as the administrative Ministry of NHAI, the Ministry of Shipping, Road Transport and Highways, Government of India was well within its rights to write the letters

dated 11th July 2008, 29th July 2008 and 7th August 2008 to NHAI and was also

justified in constituting the aforesaid Committee on 11th July 2008. The intention

of the Government was bonafide and in any event no allegation of malafide has

been made by any of the parties.

7. The main plea of the petitioner which needs to be addressed by us is

whether the revaluation was legal and /or justified and indeed both the learned

counsel agreed that if this plea was held in favour of the petitioner, i.e., the power

to review at the behest of the unsuccessful applicants, then we need not go into

the other pleas raised by the learned counsel for the petitioners. It is necessary

therefore to consider the source of the process of revaluation. The revaluation

appears to have been subsequent to the letters dated 7 th July 2008 and 10th July

2008, which were preceded by the letter dated 30th June 2008 by M/s Reliance

Infrastructure Ltd. and other representations received from M/s Isolux-Soma-

Omaxe Consortium, M/s Macquarie and M/s Cintra. The said representation was

addressed to the Secretary, Ministry of Road, Transport and Highways.

8. However, a letter dated 2nd July 2008 was received by the NHAI from the

Government of India, Ministry of Shipping, Road Transport and Highways. By this

letter dated 2nd July 2008, the Government forwarded representations received

from certain unsuccessful aspirants for the tender and directed that the matter

may be reviewed by the NHAI and asked for forwarding of the comments of the

NHAI on the representations to the ministry within three days. It was also directed

that the issue of Request for Proposal (RFP) document may be deferred for at least 10 days. The said letter was replied to and comments sent by the NHAI by

its letter dated 4th July 2008. The relevant portion of the said letter reads as

follows:-

"Sub.: Representations from M/s. Isolux-Soma-Omaxe

Consortium, M/s. Reliance Infrastructure Ltd., M/s. Macquarie

and M/s. Cintra in respect of RFQ process for four laning of the

Hyderabad-Vijayawada and Vijayawada - Machilipatnam

Sections on NH-9 under NHDP Phase-IIIA.

Ref.: Ministry letters No. RW/NH-37011/33/2008 - PIC dated

2nd July 2008.

Sir, With reference to Ministry's three letters on the subject

cited above, it is submitted that the matter in respect of

representations of M/s. Isolux-Soma-Omaxe Consortium, M/s.

Reliance Energy Ltd. and M/s. Macquarie Securities Asia Pvt.

Ltd. in respect of RFQ process for four laning of the Hyderabad-

Vijayawada and Vijayawada - Machilipatnam sections on NH-9

under NHDP Phase III has been reviewed and following

submissions are made:

(i) Prequalification process for following 3 stretches has

been completed by NHAI till date:-

            (a)       Hyderabad-Vijayawada


            (b)       MP/Maharashtra Border-Dhule


            (c)       Pimpalgaon-Gonde


            (ii)         The    evaluation    of    RFQs    for     Vijayawada-

            Machilipatnam is still under process.

2. NHAI has also received a representation from M/s.

Cintra (copy enclosed for ready reference) in this regard.

3. Evaluation of RFQ for Hyderabad-Vijayawada stretch

has been carried out by M/s. Almondz Global Securities Ltd.,

the Financial Consultants. Consultants have mentioned in

their report that while carrying out evaluation, in the event of

related document being deficient in certain aspects, attempts

were made to evaluate by interpreting the

information/documents available elsewhere in the application

for qualification. It has further been mentioned by the

Consultants that at times, different documents could be

interpreted in different ways thereby introducing an element of

subjectivity in the evaluation process and accordingly

evaluation has been carried out based on the information as

brought by the relevant documents e.g. Statutory Auditors

certificate relating to Associate status and quoted experience.

This approach had also become inevitable due to too

voluminous documents submitted by the applicants so as to

pre-qualify in top six short-listed applicants.

4. The applications of all responsive applicants have been

evaluated as per Clause 2.2.9 of RFQ road with the reply given

in the pre-bid meeting with respect to Associate status and the

eligibility criteria prescribed in Clause 3 of RFQ. Further,

evaluation is Annexure IV instructions No. 13 and 14.

  5.        Applicant-wise      comments     on     the    reply   them

  representations made by them are as under:-


(a)    M/s. Isolux-Soma-Omaxe Consortium
 Name            of Claimed    Evaluated Comments

member/Asso         score     Score     (response            for

ciates                                  all difference)
                    4047.13   3205.80   (i)      Experience
M/s.      Isolux-
                                        claimed       for    the
Corsan
                                        period               not
Concessions
                                        related               to
S.A. (member)
                                        prescribed           five

                                        year period has

                                        been excluded.

                                        (ii)     Experience

                                        claimed       relating

                                        to     project      "not

                                        commissioned"

                                        under category 1

                                        &2      has         been

                                        excluded.
Corsan Corviam 6048.85        0         There         is      no

Construction,                           document

S.A.                                    certified             by

(associates)                            Statutory Auditor

                                        to          establish

                                        "Associate"

                                        relationship




Isolux              895.56    0         There         is      no

Ingenieria,                             document

S.A.(associate)                         certified             by

                                        Statutory Auditor

                                        to          establish

                                        "Associate"

                                        relationship.
Soma                642.32    0         The applicant has

Enterprise                              submitted

Ltd.,(member)                           certificates        from

                                        a             Charted
                                          Accountant,

                                         which   does    not

                                         mention that it is

                                         from            the

                                         Statutory

                                         Auditor.
Omaxe                0         0         -

Infrastructure

and

Construction

(P)           Ltd.

(member)
Omaxe         Ltd. 2929.19     0         The applicant has

(associate)                              submined

                                         certificates   from

                                         a           Charted

                                         Accountant,

                                         which   does    not

                                         mention that it is

                                         from            the

                                         Statutory Auditor.
Omaxe                1122.80   0         The applicant has

Buildhome      (P)                       submined

Ltd. (associate)                         certificates   from

                                         a           Charted

                                         Accountant,

                                         which   does    not

                                         mention that it is

                                         from            the

                                         Statutory Auditor.




It is relevant to refer to the clarification given by NHAI to the

quarries received from applicants. It was clearly stated that in

case of an Associate, supporting statement s certified by

Statutory Auditor should be provided.

Annexure-IV of the RFQ specifies two Formats

(a) Certificate from the Statutory Auditor regarding BOT

Projects and

(b) Certificate from the Statutory Auditor/Client regarding

construction experience on eligible projects.

Instructions contained in Annexure-IV Sl. No. 12 states that

certificate from the Client or the Statutory Auditor must be

furnished as per format. Similarly, instruction contained in

Annexure-IV Sl. No. 13 & 14 states that if the applicant is

claiming for experience under the Category 1 and 2, or

Category 3 an4 4 it should provide a certificate from its

Statutory Auditor regarding BOT projects or certificate from its

Statutory Auditor/Client regarding construction works

respectively.

The applicant has not provided the mandatory Statutory

Auditors Certificate while claiming their individual, as well as

their Associates technical capacity. This has resulted in

reduction of their claimed technical score.

Besides total experience score, as per Clause 2.2.2 (A)(iii)

Para-3 the applicants are required to have at least 1/4th of the

Threshold Technical from the eligible project in Category 1 and

/ or Category 2, specified in Clause 3.2.1 (i.e. Highway Sector)

The applicant has scored nil in his category due to deficient

certificate and were declared ineligible

(b) M/s. Reliance Energy Ltd.

 Name           of Claimed       Evaluated   Remark
                     score      Score
member/Associ

ates
Reliance Energy 16708.47        0           In the experience

Ltd. (member)                               Certificate            it    is

                                            not     mentioned

                                            that    it        is        not

                                            mentioned that it

                                            is from Statutory

                                            Auditor
Reliance             32501.22   0           Certificate                  in

Communication                               support                      of

s             Ltd.                          Associate

(associate)                                 relationship with

                                            AAA

                                            Communication

                                            (P) Ltd. (member)

                                            is from Charted

                                            Accountant but it

                                            has     not            been

                                            mentioned that it

                                            is from Statutory

                                            Auditor
JPTEGOL              418.98     439.19      Due          to             the

                                            Applicable

                                            Foreign Currency

                                            Conversion              rate

                                            there         is            as

                                            increase          in        the

                                            Technical Store.




The reduction in score is due to (i) non-submission of

"documents certified by Statutory Auditor" in support of

Associate Status and (ii) submission of certificates from a

Charted Accountant, which does not mentioned that it is from the Statutory Auditor. In addition, the experience relating to

electricity business has been quoted in consolidated form

without giving the required project specific details.

(c) Gammon Infrastructure Projects Limited-Macquarie

Securities (Asia) PTE Limited

Name of Claimed Evaluated Remark

member/Ass score Score

ociates Gammon 1841.58 0 • In the Experience

Infrastructure Certificate it is not

Projects Ltd. mentioned that it is

(member) from Statutory

Auditor.

                                               •   Statutory Auditor

                                               Certificate            not

                                               submitted        in   some

                                               cases.

                                               •             Experience

                                               claimed     relating    to

                                               project               "not

                                               commissioned"

                                               under category 1 & 2

                                               has been excluded.
Gammon              1848.18     1742.48    Experience claimed for

India Ltd.                                 the period not related

                                           to prescribed five year

                                           period         has        been

                                           excluded.
Macquarie           0           0          -

Securities

(Asia)       Pte.

Ltd.

(member)
Macquarie           24616.25    0          There is no document
 Infrastructure                       certified by Statutory

Group                                Auditor   to     establish

(associate)                          "Associate

                                     relationship".
Macquarie        37372    0          There is no document

Airports                             certified by Statutory

(associate)                          Auditor   to     establish

                                     "Associate

                                     relationship".




The reduction in score of M/s. Gammon Infrastructure Projects

Ltd. is due to (i) non submission of Statutory Auditor

Certificate, (ii) submission of certificates in which it is not

mentioned that they are from Statutory Auditor and (iii)

experience claimed relating to project not commissioned

under category 1 & 2. In case of M/s. Gammon India Ltd., the

reduction is due to exclusion of claimed experience not

relating to the prescribed five years period.

In case of M/s. Macquarie Securities (Asia) Pte. Ltd., the

claimed score has not been taken into account in the absence

of a document certified by Statutory Auditor to establish

associate relationship with M/s. Macquaire Infrastructure

Group Group and M/s. Macquaire Airports, the entities whose

experience has been claimed as associate.

The applicant score therefore, relates to M/s. Gammon

Infrastructure Projects Ltd. & M/s. Gammon India Ltd. and the

score of M/s. Macquarie is Nil.

It will not be out of place to mention here that NHAI has

completed evaluation in two more projects namely MP/Maharashtra Border to Dhule and Pimpalgaon to Gonde in

the State of Maharashtra in which this consortium is an

applicant and M/s. Pricewater House Coopers are the

Financial Consultants. The consortium has been shortlisted in

the above two projects. However, their inclusion is solely on

account of score of M/s. Gammon Infrastructure Projects Ltd.

and the score of M/s. Macquarie Securities (Asia) Pte. Ltd. has

been evaluated Nil in these case as well.

       (d)    Cintra Concessioners De Infrastructuras

       De Transporte S.A.




A representation from Cintra Concesiones De Infrastructuras

De Transporte S.A. has also been received in the office of

Chairman, NHAI. In their representation the applicant has

stated that they have submitted all documents in due

compliance of RFQ (copy enclosed). However, during

evaluation it was noted that the applicant in this case has

submitted "independent Reasonable Assurance Report" by a

Charted Accountant instead of a certificate in the prescribed

format from the Statutory Auditor.

Further, M/s. Cintra has stated under item 3 on page 1 of their

representation that in the said report, on page 2 to 8 it is

mentioned that for "Statutory Auditor Certificate see page 9",

whereas in the documents submitted it is written for "Statutory

Auditor Certificate see page 9". Further, pages 2 to 8 have not been authenticated by the signatory of the report.

It has also been stated that PWC has issued "Statement of

Associates". The details have been rechecked, but no such

statement in support of claimed experience could be found.

This letter is being issued with approval of the Competent

Authority."

9. Another letter dated 11th July 2008 was received by the NHAI from the

Government of India, Ministry of Shipping, Road Transport and Highways wherein

the Government has directed the NHAI to place the matter before the Board of

NHAI and requested the authority that the process of issue of RFP be deferred

until further intimation. The letter of 11 July, 2008 to the NHAI by the Ministry of

Shipping, Road Transport and Highways reads as under:-

"Sub.: Representation from M/s. Reliance Infrastructure Ltd. in respect of RFQ process from four laning of the

Hyderabad-Vijayawada section on NH-9 under NHDP

Phase IIIA. Reg.

Sir, Please refer to your reply submitted vide letter dated

4th July 2008, in response to our letters dated 2nd July

2008 regarding representations/complaints of some

applicants on the evaluation process for aforesaid

stretch.

The reply mentions that the applicant has submitted

certificates from a Charted Accountant which does not

mention that it is from the statutory auditor. Generally, RFQs allows employer to seek clarifications in case of any

doubt/ambiguity in the information provided by bidders.

In this case it appears that such clarifications were not

obtained by NHAI while seeking other clarification. It

would not be out of the context to mention here that

NHAI had earlier sought clarification from the bidders in

similar cases. During bid evaluation under NHDP - V,

some discrepancies were observed in the ECs submitted

by bidders and NHAI had sought clarifications after

seeking legal advice which had opined as under:-

'Rejection of the bid on this account alone may be

challenged on the ground that the NHAI is acting in the

technical manner and without due application of mind.'

It appears that different approach/yardstick has been

followed in the evaluation of bids of aforesaid package

and under NHDP-V.

Meanwhile on more representation from M/s. Reliance

Infrastructure Ltd., dated 7th July 2008 (copy enclosed)

has been received. It has been indicated in the

representation that some other companies have been

qualified / shortlisted though they submitted documents

with many other serious irregularities, in addition to the

so called irregularities in the documents of M/s. Reliance.

It is, therefore, requested that the matter may be placed

before the Authority (Board). It is also requested that the

process of issue of RFP may be deferred until further

intimation."

10. Further thereto the Government of India, Ministry of Shipping, Road

Transport and Highways appointed a two Member Committee comprising of the

Director General (Road Development) and Special Secretary and Member-

Technical, NHAI to review the entire matter. The said committee submitted its

Report, which was forwarded by the Government of India, Ministry of Shipping,

Road Transport and Highways under cover of its letter dated 29th July 2008 which

reads as under:-

"Sub.:- Representations against RFQ process for four laning of the Hyderabad - Vijayawada section of NH-9

under NHDP Phase-III-Report of the Committee-

regarding.

Sir, Kindly find enclosed herewith a copy of the report of

the two member Committee constituted in the Ministry

on the above mentioned subject vide its OM dated

11.07.2008.

It is, therefore, requested that the report of the said

Committee may by placed before the NHAI Board along

with the recommendations / comments of the Chairman,

NHAI urgently for a decision of the matter."

11. One of the recommendations of the Two Member Committee to the

Authority was to re-look into the qualification exercise for the project package

following the same procedure as for the other seven project packages and ask the

bidders for clarification on the qualification aspects without allowing them to

submit additional document and without any addition in further claims of score as

was being followed in other seven project packages.

12. The learned counsel for the UOI Mr. Gaurav Duggal was directed on 20th

November 2008 to hand over the list of dates showing the passage of the

representation of the tender process through the Ministry within three days. The

order was complied only on 8th December 2008. However, since we have to

examine the validity of the decision making process, we consider it necessary to

take on record and analyse the documents relating to the passage of

representation of the entire tender process as filed by the learned counsel for

NHAI and particularly the file notings of the Project Implementation Cell of the

Ministry of Shipping, Road Transport and Highways which are as under:

"(A) Para-5 of file noting dated 11th July, 2008

5. In this context note of Hon'ble Minister at page 4/ante

may kindly be referred. It has been desired by Hon'ble Minister

that "with reference to all representations in this project, once

the report is received if required clarification on technical

issues could be sought from Planning Commission/Ministry of

Finance.

(B) Para-2 of file noting dated 30th July, 2008

2. In the matter relating representations against the RFQ

process completed by NHAI in respect of four laning of

Hyderabad-Vijayawada section on NH-9 in Andhra Pradesh on

BOT basis, a two member Committee consisting of DG (RD) &

SS and Sh. Nirmaljit Singh, Member (Tech.) NHAI was constituted with the approval of the Hon'ble Minister (S, RT&H)

on 11.07.2008. The report of the Committee has been

received vide their letter dt. 28.07.2008.

(C) File noting dated 5th August, 2008

A meeting was taken by Hon'ble Minister (S, RT&H) on

5.8.2008 to review the progress of evaluation of RFQ and

award of concessions for projects under NHDP. The meeting

was attended by Secretary (RT&H), DG (RD) & SS, Advisor to

Dy. Chairman, NHAI and concerned officials of NHAI and the

Ministry. In the subsequent meeting taken by Secretary

(RT&H), the matter relating to Hyderabad-Vijayawada project

was also discussed. In this regard, it was mentioned that the

report of the two Member Committee in the matter has already

been forwarded to NHAI vide this Minister's letter of even no.

dated 29.7.2008. During the discussion, it was mentioned by

the Chairman, NHAI and the concerned Member (Tech.) that as

per the committee report the queries/clarification to be asked

from the applicants of the project have already been prepared

and are ready for issue. However, it was indicated that the

previous decision taken by Chairman, NHAI can't be changed

at the same level suo-motto."

13. A letter dated 7th August 2008 was received by NHAI from the Government

of India, Ministry of Shipping, Road Transport and Highways wherein it was stated

as follows:

"Sub.: RFQ process for four laning of the Hyderabad- Vijayawada section of NH-9 under NHDP Phase-III-

regarding.

Sir, A meeting was taken by Hon'ble Minister (S,RT&H)

on 05.08.2008 to review the progress of evaluation of

RFQ and award of concessions of projects under NHDP.

In the meeting taken by Secretary (RT&H) subsequent

the above meeting, the matter relating to Hyderabad -

Vijayawada project was also discussed. In this regard, it

may be recalled that the report of the two Member

Committee has been forwarded vide this Ministry's letter

of even no. dated 29.07.2008. During the discussion, it

was mentioned by you and the concerned

Member(Tech.) that as per the committee report the

queries/clarification to be asked from the applicants of

the project have already been prepared and are yet to

be issued.

In order to expedite the process, it is requested that

necessary clarifications from the applicants may be

obtained immediately and the applications re-evaluated.

The findings of the re-evaluation may be placed before

the NHAI Board for a decision in the matter."

14. It is thus clear from the above letter dated 7th August, 2008 that the Union

of India has not only forwarded the representations received from the

unsuccessful bidders who failed to qualify after the first evaluation conducted by

the NHAI, but also issued directions to NHAI to put the process on hold and the

Ministry had pursuant to the report of the two member committee to look into the

evaluation, directed the NHAI to seek clarifications from the bidders and re-

evaluate the bids. In fact, it is apparent from the letter dated August 7, 2008 that the Ministry of Shipping, Road Transport and Highways has itself been reviewing

the progress of evaluation of RFQ and award of concessions for projects under

NHDP. The above action on the part of Union of India is not contemplated by the

provisions of the NHAI Act which envisages the NHAI as an autonomous statutory

body. The actions of the Union of India in the present case indicates that not only

the autonomy granted to NHAI by the Parliament by a statute enacted in this

regard been curtailed and eroded, but the NHAI is sought to be reduced to a mere

department of the Government with the Ministry of Shipping, Road Transport and

Highways. The mandate of the letter dated 7th August, 2008 clearly spells out the

course of action in no certain terms and merely ask the NHAI to endorse formally

the decision expressed in the said letter. The entire process adopted from 2 nd July

2008 to 26th August 2008 clearly shows that the mandate of section 33 had been

abrogated and the decision had already been taken to re-evaluate the bid and the

NHAI was merely asked to formally act on such a decision.

15. Considerable emphasis has been laid upon Section 33 of the National

Highways Authority of India Act, 1988 (hereinafter referred to as "the NHAI Act").

In fact, in our view, it is necessary to extract Sections 31, 32 in addition to Section

33 of the NHAI Act which read as follows:

                   "31. Power      of   the   Central    Government       to

                   temporarily     divest     the    Authority     of    the

                   management of any national highway - (1) If, at

any time, the Central Government is of opinion that in

the public interest it is necessary or expedient so to do,

it may, by order, direct the Authority to entrust the development, maintenance or management of any

national highway or a part thereof with effect from such

date and for such period and to such person as may be

specified in the order and the Authority shall be bound

to comply with such direction.

(2) Where development, maintenance or management

of any national highway or part thereof is entrusted to

any person specified under sub-section (1) (hereafter in

this section referred to as the authorized person), the

Authority shall cease to exercise and discharge all its

powers and functions under this Act in relation to such

national highway or part thereof and such powers and

functions shall be exercised and discharged by the

authorized person in accordance with the instructions,

if any, which the Central Government may give to the

authorized person from time to time:

Provided that no such power or function as may be

specified by the Central Government by a general or

special order shall be exercised or discharged by the

authorized person except with the previous sanction of

the Central Government.

(3) The Central Government may reduce or extend the

period mentioned in sub-section (1) as it considers

necessary.

(4) During the operation of an order made under sub-

section (1), it shall be competent for the Central

Government to issue, from time to time, such

directions to the Authority as are necessary to enable the authorized person to exercise the powers and

discharge the functions of the Authority under this Act

in relation to the national highway or part thereof, the

management of which has been entrusted to him and

in particular, to transfer any sum of money from the

Fund of the Authority to the authorized person for the

management of the national highway or part thereof

and every such direction shall be complied with by the

Authority.

(5) On the cesser of operation of any order made under

sub-section(1) in relation to any national highway or

part thereof, the authorized person shall cease to

exercise and perform the powers and functions of the

Authority under this Act in relation to such national

highway or part thereof and the Authority shall

continue to exercise and perform such powers and

functions in accordance with the provisions of this Act.

(6) On the cesser of operation of any order made under

sub-section (1) in relation to any national highway or

part thereof, the authorized person shall hand over to

the Authority any property (including any sum of

money or other asset) remaining with him in

connection with the management of such national

highway or part thereof.

32. Power of the Central Government to

supersede the Authority - (1) If, at any time, the

Central Government is of opinion -

(a) that on account of a grave emergency the Authority is unable to discharge the functions and duties

imposed on it by or under the provisions of this Act; or

(b) that the Authority has persistently made default in

complying with any direction issued by the Central

Government under this Act or in the discharge of the

functions and duties imposed on it by or under the

provisions of this Act; or

I that circumstances exist which render it necessary in

the public interest so to do, the Central Government

may, by notification in the Official Gazette, supersede

the Authority for such period, not exceeding one year,

as may be specified in the notification:

Provided that before issuing a notification under this

sub-section for the reasons mentioned in Clause (b),

the Central Government shall give a reasonable

opportunity to the Authority to show cause why it

should not be superseded and shall consider the

explanations and objections, if any, of the Authority.

(2) Upon the publication of a notification under sub-

section (1) superseding the Authority -

(a) all the members shall, as from the date of

supersession, vacate their office as such;

(b) all the powers, functions and duties which may, or

under the provisions of this Act, be exercised or

discharged by or on behalf of the Authority, shall, until

the Authority is reconstituted under sub-section (3) be

exercised and discharged by such person or persons as

the Central Government may direct;

I all property owned or controlled by the authority shall,

until the Authority is reconstituted under sub-section

(3), vest in the Central Government.

(3) On the expiration of the period of supersession

specified in the notification issued under sub-section

(1), the Central Government may-

(a) extend the period of supersession for such further

term, not exceeding one year, as it may consider

necessary; or

(b) reconstitute the Authority by fresh appointment and

in such a case, any person who vacated office under

clause (a) of sub-section (2) shall not be deemed

disqualified for appointment:

Provided that the Central Government may, at any time

before the expiration of the period of supersession

whether as originally, specified under sub-section (1) or

as extended under this sub-section, take action under

clause (b) of this sub-section.

(4) The Central Government shall cause a notification

issued under sub-section (1) or sub-section (3) and a

full report of any action taken under this section and

the circumstances leading to such action to be laid

before both Houses of Parliament as soon as may be.

33. Power of the Central Government to issue

directions: - (1) Without prejudice to the other

provisions of this Act, the Authority shall, in the

discharge of its functions and duties under this Act, be

bound by such directions on questions of policy as the Central Government may give to it in writing from time

to time.

(2) The decision of the Central Government whether a

question is one of policy or not shall be final."

16. In our view, the mandate of the above statutory provisions is clear and

indicates beyond doubt the nature and extent of the control of the Government

over a statutory authority such as the National Highway Authority of India which is

a Public Sector Undertaking, meant for construction and maintenance work of the

roads and highways. The NHAI being a Public Sector Undertaking certainly could

be given policy directions under Section 33 of the NHAI Act.

17. We have no hesitation in agreeing with the plea of Shri Gopal

Subramanium, the learned Additional Solicitor General appearing for the Union of

India that the Act mandates as under:

a) Sections 3, 11, proviso to Section 15, Section 17 clearly indicate that NHAI is a

creature of the Central Government created by the medium of NHAI Act.

b) Section 21 also indicates the control of the Central Government of any

borrowing by NHAI.

c) Section 24 places an obligation on the Ministry to place annual report and the

auditor's report of the NHAI before the Parliament.

d) Section 31 also extends the control of the Ministry to temporarily divest NHAI of

the management of any national highway, if it is thought that in public interest it

is necessary to do so.

e) Section 32 empowers the Central Government to supersede NHAI in specified

situation;

f) Section 37 states that the rules and regulations made under the Act are to be placed before each House of Parliament.

g) The provisions of the National Highways Act, 1956, the National Highways

Authority of India Act, 1988 and the Government of India (Allocation of Business)

Rules, 1961 clearly show that the national highways vest in the Central

Government and NHAI is an implementing agency of the Government of India

created by the Parliament in matters relating to development of highways.

We agree with the plea of the learned ASG that the Central Government has the

power to ensure efficiency and transparency of the functioning of the NHAI. The

financial sanction of the specified amounts from the Government also shows the

role of the Central Government in the functioning of the NHAI. We have no

hesitation even in agreeing with the above plea of the learned ASG but, in our

view, the aforesaid plea indeed shows the nature and extent of the statutorily

mandated administrative control, the financial control and the power to divest

certain highways vesting with the Government of India. In our view, the nature

and extent of the control having been specified by the various provisions of the

Act delineated by the learned ASG, leave no further scope for intervention save

and except in the manner indicated by Section 33.

18. In our view, the nature, extent, control and intervention of the Government

are clearly specified in the above provisions noted by us. Since the Parliament has

prescribed the nature and manner of control of the Ministry over the NHAI, such

control, in our view, is sufficient to ensure the proper, transparent, efficient and

independent functioning of NHAI. The very nature and detailed extent of the

above control clearly indicates that apart from the above control there can be policy directions by the Ministry to the NHAI under Section 33 of the Act. The

crucial question which arises in the present writ petition is whether the impugned

intervention by the Ministry can fall within the scope of Section 33 or whether the

actions or complaints are counter to the scheme delineated by Section 33 of the

Act. However, the very nature of the power vested in the Government through

administrative Ministry, i.e., Ministry of Shipping, Road, Transport & Highway

under Section 31 and 32 of the Act clearly shows that the powers of the NHAI are

not unbridled and the Government can in public interest effectively divest a

malfunctioning NHAI from the control of a particular National Highway. An even

stronger power to supersede the NHAI also exists with the Government. If either

under Section 31 the Hyderabad-Vijaywada Highway was taken over by the

Central Govt. from the control of the NHAI or the authority had been superseded

for persistent misconduct under Section 32, then the impugned actions of the

Government to ensure the revaluation of the bids through the NHAI could have

been sustained in law. However, since action was admittedly not taken under

Sections 31 and 32 of the Act and purportedly taken under Section 33 of the Act,

we are satisfied that the impugned action of revaluation could not have been

directed by the Ministry to be taken by the NHAI in the present case.

19. However, the petitioner has rightly submitted that such policy directions

could not extend to giving of detailed directions in respect of a particular tender

by the Government of India. This plea of the petitioner is in addition to the plea

that while it was open to the UOI to seek clarification from the bidders this could

not be done at the behest of an unsuccessful applicant which is clearly proscribed

by Clause 2.21. Reliance has been laid upon a decision of the Division Bench of this Court in the case of Arun K. Saraf & anr. V. Lt. Governor of Delhi, 52

(1993) DLT 307, and in particular, paragraphs 10 and 11 which read as follows:

"10. The Vice-Chairman had requested the Secretary, Ministry of Urban Development that the decision of the

Government be communicated on or before 13.3.93. In

the file of the Ministry there is nothing on record as to

on what basis the State Minister for Urban

Development issued the direction to the DDA not to

accept the valid bid. When the reserved price has

specifically mentioned and adequate publicity had

been made and the tender was accepted following the

procedure with the approval of the LG of Delhi who is

Chairman of DDA and the DDA itself has represented to

the Ministry that if this tender is not accepted the DDA

is apprehensive that there would be financial loss

leading to the audit and other objections. The Secretary

has also opined that the Government should not

interfere in this matter.

11. We feel that the action of the State Minister in

issuing a directive under Section 41 of the DDA Act was

rather arbitrary. No material whatsoever was with him

to move in such a manner. Normally such a note by the

Minister should show as to how he got the information

and whether he considered the same to be reliable.

Minister should have been aware that DDA is a creation

of statute of the Parliament and there has to be no

interference by the Central Government otherwise as

provided by law, i.e., DDA Act, particularly in matters which have been examined at all level by appropriate

authority and no mala fide is alleged or involved.

Undue interference by the Central Government in areas

which are occupied by rules and regulations of DDA is

to be avoided otherwise the whole purpose of enacting

a Central Act and to incorporate a statutory body would

become redundant and nugatory. This may result in

uncalled for decision and arbitrary actions. In the

circumstances of the case, we find the impugned action

of the Central Government neither fair nor just and

rather arbitrary."

20. In the present case, the Union of India/ Ministry's direction to NHAI to put

the process of selection on hold, appointment of the two member committee to

look into the evaluation at the behest and instance of the unsuccessful applicant

contrary to clause 2.21 of the RFQ and giving of directions to the NHAI to seek

clarifications from the bidders and re-evaluation of the bids, does not involve any

matter of policy as envisaged by Section 33 of the NHAI Act. Such intervention in

policy matters fetters the administrative autonomy. Jurisdiction statutorily vested

in the NHAI by the Parliament under Section 33 is not to be exercised for

interfering with the routine functions of the NHAI or in its day to day business of

which evaluation of bids received from interested parties pursuant to a Request

for Proposal issued by NHAI is a part.

21. The approach to the Secretary of Ministry of Shipping, Road Transport and

Highways by the unsuccessful bidders amounted to circumventing the bar

imposed by clause 2.21. Thus, the unsuccessful bidders in order to achieve what was forbidden by clause 2.21 adopted the route of approaching the Ministry. In

our view this is not permissible as it is an indirect recourse to power of review

which is not permissible under clause 2.21. Such unsuccessful bidders could

always challenge their wrongful exclusion by recourse to a court of law. However,

this case demonstrated that a route adopted by the unsuccessful bidders by

approaching the Ministry and in particular the manner and method by which the

evaluation process was practically directed by the Ministry demonstrates that the

action of the Ministry travelled beyond the mandate of Section 33.

22. However, we make it clear that our findings should not be construed to

mean that the Ministry of Shipping, Road Transport and Highways, as an

administrative Ministry of the NHAI cannot forward what appear to be genuine

complaints to the NHAI. To adopt such a construction would in our view denude

the Ministry of any administrative control over the NHAI. However, in our view if

such a complaint/grievance/representation is forwarded by the Ministry to the

NHAI, it could and should be processed in terms of the process given in the tender

terms as per Clause 2.20 which reads as under:-

"2.20 Clarification

(i) To facilitate evaluation of Applications, the

Authority may, at its sole discretion, seek

clarifications from any Applicant regarding its

Application. Such clarification(s) shall be provided

within the time specified by the Authority for this

purpose. Any request for clarification(s) and all

clarification(s) shall be in writing.

(ii) If an Applicant does not provide clarifications sought under Sub-Clause (i) above within the

prescribed time, its Application shall be liable to be

rejected. In case the Application is not rejected, the

Authority may proceed to evaluate the Application

by construing the particulars requiring clarification

to the best of its understanding, and the Applicant

shall be barred from subsequently questioning such

interpretation of the Authority."

(emphasis supplied)

It is for the NHAI then to raise queries and seek clarification in accordance with

Clause 2.20. This interpretation of the interplay of the power and jurisdiction and

the extent of the Ministry's control would in our view adequately protect the

public interest inherent in the mandate of Section 33 without in any manner

denuding the administrative control of the Ministry and the statutory autonomy

granted by the NHAI Act.

23. The NHAI Act indicates that to execute vital infrastructural projects

involving massive outlay of funds and resources and considering the nature of the

work required to be executed, the participation of international bidders is

anticipated and expected. It is evident that the NHAI Act was enacted to

constitute an autonomous body such as the NHAI to lend assurance of the

autonomy of the NHAI to large scale investors and in particular international

infrastructure companies. Such an assurance was inherent in the highway project

and the regulator being bound only by the statute without any other interventions

except Section 33. Section 33 clearly expresses the parliamentary concern about

the nature of intervention and control of the Ministry and the preservation of the

autonomy of the NHAI in its day-to-day functioning. In the present case, while no lack of bonafide can be attributed to the manner of

intervention by the Ministry which may have been motivated to redress a

grievance, which in one or two cases may appear to be entirely genuine,

nevertheless, such intervention was not contemplated by the Act. The Ministry

could have certainly forwarded the representation as part of its administrative

control over the Ministry for consideration by the NHAI, who then could have

considered it as mandated by Clause 2.20 which permits NHAI to seek

clarification. However, the appointment of a Committee and the day-to-day

monitoring and control by the Ministry, in our view, does not accord with the

mandate of Section 33 of the Act. A policy matter under the mandate of Section

33 would contemplate a general policy direction, such as, to indicate the choice of

field generally.

24. The learned counsel for the petitioner GMR Infrastructure Ltd. has raised

the plea that as per the RFQ, those projects ought to have been considered by the

NHAI where even part of the project had been commissioned/completed and not

the whole project itself. However, we are unable to agree with the plea raised by

the petitioner as this formula of exclusion of non-completed/commissioned

projects has been uniformly applied by the NHAI to all parties taking part in the

tender proceedings. It is also to be seen that if partial work is taken into account,

it could lead to a major problem itself as in the event of the project either being

abandoned or not being completed satisfactorily, the bidder would have already

got the benefit of the marks for such an incomplete project, thus making the

whole process vulnerable to error.

25. In view of the above findings, the rule in the writ petition is made absolute. We quash the letter dated 26th August, 2008 issued by the NHAI to the

petitioners, i.e., GMR Infrastructure Ltd. and Madhucon Projects Pvt. Ltd. We also

uphold the validity of the letter dated 27th June, 2008 informing the

petitioners that they have pre-qualified for the bid stage of the tender. Any action

taken by the Respondent NHAI subsequent to the letter dated 27th June, 2008

stands quashed and set aside. Consequently, the writ petitions bearing Nos.

6792/2008 and 6419/2008 filed by GMR Infrastructure Ltd. and Madhucon Project

Pvt. Ltd. respectively are allowed and accordingly disposed of.

26. It is also pertinent to note that a public authority needs freedom from

controls applicable to ordinary governmental department to the extent that such

controls are unduly restrictive for an agency with commercial functions. Thus, the

autonomy of a public sector enterprise constitutes an important facet of modern

governance of State. This issue has been dealt with felicitously and in great detail

in the concurring judgment. The view in the concurring judgment are fully

endorsed and adopted for arriving at the conclusions in this judgment.

MANMOHAN, J. - (CONCURRING)

1. While I concur with the conclusions in the Division Bench judgment

delivered by my learned brother Justice Mukul Mudgal, but keeping in view the importance of the issues involved, namely, the interse relationship between the

Central Government and a public enterprise and the power of Central Government

to intervene in tenders floated by public enterprise, I wish to place on record my

views in the matter.

2. 'Public Enterprise' is a very broad term. It includes all the regulatory,

promotional and productive activities of the modern State. However, Public

Enterprise may be organized and managed either as a departmental undertaking

like Railways or a local body like New Delhi Municipal Council (NDMC) or a

company registered under the Companies Act, like National Thermal Power

Corporation (NTPC) or a statutory corporation like Life Insurance Corporation (LIC)

or statutory authority like National Highways Authority of India (hereinafter

referred to as 'NHAI').

3. A statutory authority is one that is created by an Act of Legislature, which

defines its power, liabilities and prescribes the form of management as well as its

relationship with the Government. Admittedly, a statutory authority though

wholly owned by the State has a legal personality separate and independent from

the Government.

4. The learned Additional Solicitor General, Mr. Gopal Subramaniam, as

recorded by my learned brother, Justice Mukul Mudgal, submitted that the intent behind the Ministry of Shipping, Road Transport and Highways' (hereinafter

referred to as 'the Ministry') direction to revaluate the bids was only to ensure

that NHAI acts fairly and in a transparent manner. He submitted that the Ministry,

keeping in view its accountability to Parliament and its statutory control over NHAI

had only corrected a manifest error and its direction to revaluate under Section 33

was only an intervention and not an interference with the day-to-day functioning

of a statutory authority. He further submitted that the said direction did not dilute

the essential tendering purpose and process.

5. Though, Mr. Subramaniam submitted that the Ministry had not interfered in

the functioning of NHAI, the counter affidavit of NHAI candidly admits that the

revaluation of the bids had been done only in accordance with the directions of

the Ministry. The relevant extract of the counter affidavit of NHAI is reproduced

hereinbelow:-

"That it is the humble and respectful submission of the Respondent No. 1 that the entire sequence of events as

aforesaid confirm that the Respondent No. 1 Authority has

acted as per the directions of the Government of India,

Ministry of Shipping, Road Transport and Highways.....

The whole exercise of re-evaluation was subsequent to the

directions of the Government of India by which the

Respondent No. 1 is bound under the provisions of Section 33

of the National Highways Authority of India Act, 1983............." (emphasis supplied)

6. Mr. Rajiv Nayyar, learned senior counsel who appeared for Respondent

Isolux Corsan Concesiones S.A., (the bidder who was shortlisted at the subsequent

revaluation) after referring to various provisions of the National Highways Act,

1956, the rules framed thereunder and the National Highways Authority of India

Act, 1988, submitted that NHAI was under continuous and all pervasive control of

the Central Government, in particular the Ministry. He further submitted that the

power to issue directions under Section 33 should not be confined to policy

issues. In this context he relied upon three judgments of the Hon'ble Supreme

Court which are referred to hereinbelow along with their relevant paragraphs:-

(a) AIR India Ltd. vs. Cochin International Airport Ltd. & Ors. (2000) 2

SCC 617

"Even when some defect is found in the decision making process the Court must exercise its discretionary power under

Article 226 with great caution and should exercise it only in

furtherance of public interest and not merely on the making

out of a legal point. The Court should always keep the larger

public interest in mind in order to decide whether its

intervention is called for or not. Only when it comes to a

conclusion that overwhelming public interest requires

interference, the Court should intervene."

(b) Real Food Products Ltd. & Ors. vs. A.P. State Electricity Board &

Ors. (1995) 3 SCC 295.

"8. The only surviving question is with regard to the nature and effect of the direction given by the State Government

under Section 78A of the Act. The question has to be

examined in the context of the facts of the present case which

is confined to the charging of a flat rate per H.P. for

agricultural pump sets. The nature of the function of the board

in fixing the tariffs and the manner of its exercise has been

considered at length in the earlier decisions of this Court and it

does not require any further elaboration in the present case.

Section 78A uses the expression "the Board shall be guided by

such directions on questions of policy as may be given to it by

the State Government." It does appear that the view

expressed by the State Government on a question of policy is

in the nature of a direction to be followed by the Board in the

area of the policy to which it relates. In the context of the

function of the Board of fixing the tariffs in accordance with

Section 49 read with Section 59 and other provisions of the

Act, the Board is to be guided by any such direction of the

State Government. Where the direction of the State

Government, as in the present case, was to fix a concessional

tariff for agricultural pump sets at a flat rate per H.P., it does

relate to a question of policy which the Board must follow.

However, in indicating the specific rate in a given case, the action of the State Government may be in excess of the power

of giving a direction on the question of policy, which the

Board, if its conclusion be different, may not be obliged to the

bound by. But where the board considers even the rate

suggested by the State Government and finds it to be

acceptable in the discharge of its function of fixing the tariffs,

the ultimate decision of the Board would not be vitiated

merely because it has accepted the opinion of their State

Government even about the specific rate. In such a case the

Board accepts the suggested rate because that appears to be

appropriate on its own view. If the view expressed by the State

Government in its direction exceeds the area of policy, the

Board may not be bound by it unless it takes the same view on

merits itself."

(c) Food Corporation of India & Ors. vs. Bhanu Lodh & Ors. (2005) 3 SCC

"12. In our view, the words of Sub-section (2) of Section 6 of the Act are very material and direct that the Board of Directors

in discharging its functions "shall act on business principles"

having regard to the "interests of the producer and consumer"

and shall be guided by "such instructions on questions of

policy" as may be given to it by the Central Government. First,

the expression "business principles" is one of widest import.

We see no reason as to why the policy of recruitment of officers/staff, which would obviously have serious financial

impact on the Corporation, is not subsumed under this

expression. Secondly, the Board of management is required to

have regard to the interest of the 'producers and the

consumers', and not merely of the officers and employees of

the FCI. Finally, the Board is required to discharge all its

functions and be guided by the instructions on questions of

policy, which may be given to it by the Central Government.

Questions of policy could be, not only with regard to the

organization of the FCI, its management and function, but also

with regard to its employment policy, recruitment and many

other details which would, in the long run, affect the interests

of the consumers/producers for whom alone the FCI is

established under the Act. Testing it on this anvil, we find no

difficulty in holding that the directive dated 21st August, 1995

followed by the directive dated 6th November, 1995 are well

within the ambit of Sub-section (2) of Section 6 of the Act. The

directive dated 21st August, 1995 indicates that the policy was

not to have any creation/upgradation of posts of any level

except where completely unavoidable. The policy was that

"the existing vacancies shall not be filled up by fresh

recruitment", and that there shall be no further revision in the

conditions of service without the prior approval of the Central

Government. The policy directive issued on 6th November,

1995 was a sequel and highlighted something being done

contrary to the Regulations. While the maximum age

prescribed under the Recruitment Rules is 35/40 years for the

concerned posts, departmental candidates in the age of 52-53

years were proposed to be appointed. Even assuming that there is a power of relaxation under the Regulations, we think

that the power of relaxation cannot be exercised in such a

manner that it completely distorts the Regulations. The power

of relaxation is intended to be used in marginal cases where

exceptionally qualified candidates are available. We do not

think that they are intended as an 'open Sesame' for all and

sundry. The wholesale go by given to the Regulations, and the

manner in which the recruitment process was being done, was

very much reviewable as a policy directive, in exercise of the

power of the Central Government under Section 6(2) of the

Act."

7. Therefore, the main issue that arises for consideration in the present

proceedings is the extent of Government interference in the administration of

statutory authorities. In fact, even in England, interference by the Ministries in

the administration of nationalized industries has been an issue of debate.

Professor Wade in his book "Administration Laws", 6th Edition, has stated as

under:-

"To judge by the small number of formal directions, however, would be highly misleading. In reality ministerial interference

is frequent and pervasive. The important financial powers can

be exercised informally; and in the background are the more

general powers, which cast a deep shadow over the

corporations' precarious independence. The minister has a

powerful lever in his control over the appointment and tenure

of the chairman and members. A chairman who is appointed for short term, perhaps three years, and who hopes for

renewal of his appointment, is in no position to resist pressure

from the minister, however informally applied. The

supervising ministries are in constant touch with the

corporations and they exercise much influence merely by

holding the trump cards, without having to play them.

Chairmen feel unable to act as public spokesmen for their

industries, in case they may offend the minister. The

Governor of the Bank of England is no longer the public

mouthpiece of the City of London. Chairmen complain (usually

after retirement) that the corporations have no genuine

commercial independence and no freedom to follow long-term

policies, since they are under constant political pressure and

ministers do not look beyond the immediate crisis of the

moment. The commercial independence that the corporations

were intended to enjoy has therefore failed to materialize.

They have fallen prey to political and bureaucratic influence.

This is objectionable constitutionally as well as managerially,

since ministers have exercised a great deal of power without

accounting for it publicly and without giving Parliament the

opportunity to comment.

This state of affairs was many times criticized by the House of

Commons' Select Committee on Nationalised Industries while

it still existed. The Committee reported, for instance, that the

Air Corporations were subject to 'a degree of control far in

excess of that envisaged by the statutes'. Thus, BOAC,

against their commercial judgment ordered too many Super

VC-10 aircraft. Similarly, ministerial control was established

over gas prices, although Area Boards were by statute responsible for fixing their own prices and were advised that

the minister had no legal power to control them. In 1968 the

Select Committee made a long report on ministerial control,

condemning confusion and uncertainty of purpose, and saying

that, despite the good intentions proclaimed in the

government's white papers of 1961 and 1967, the position

was almost the exact opposite of what Parliament intended:

instead of laying down broad policies and leaving

management to the industries, the government had constantly

interfered with management and given little clear guidance on

policies. The same theme recurred in later reports: ministerial

interference with British Steel was of dubious benefit to the

national interest but did patent damage to the Corporation,

and in controlling capital investment the attempts to observe

the policy of the white papers were far from successful. A

minister himself told the Select Committee that there was 'an

appalling record of private arm-twisting' in the relations

between ministers and corporation chairmen.

With a view to bringing the situation into open the government

in 1978 proposed that ministers should be given power to

issue specific as well as general directions to the corporations,

but that the directions should be laid before Parliament at the

time and, in suitable cases, made subject to affirmative

resolutions; and that where directions led to financial loss, the

corporations should be compensated. The Select Committee

welcomed these proposals, but before action was taken on

them there was a change of government and the emphasis

shifted to denationalization."

8. In our view, in order to ensure that the affairs of the authority are

conducted in the best interests of society, a general governmental control over

the working of the authority is highly desirable, but such a control does not mean

governmental interference in the day-to-day working of the authority, which is

highly destructive of the idea of autonomy necessary for the success of any

commercial or service undertaking. We are further of the view, if the

governmental control is so extensive as to convert an authority into a

Government department, there is no point of having a statutory authority distinct

from the Government. A public authority needs freedom from controls applicable

to ordinary governmental department to the extent that such controls are unduly

restrictive for an agency with commercial functions.

9. According to Jain & Jain's Principles of Administrative Law, an important

technique evolved by the Legislature to reconcile government control with the

autonomy of a public authority is to authorize the Government to issue directives

to public authorities on matter of 'policy' without interference with matters of day-

to-day administration.

10. In our opinion, the purpose of directions as a technique of governmental control can prove beneficial only if these directions serve as a policy direction to

the authority. If the Government, through directions, interferes with the day-to-

day functioning of the authority, it would be a self-defeating technique.

11. In fact, in order to protect and safeguard the impartiality, independence

and objectivity of quasi- judicial bodies, our courts have held that directions ought

not to be issued to such bodies so as to restrict or control their discretion and best

judgment. The government should not issue directions to quasi- judicial bodies so

as to clog the exercise of their independent judgment in matters entrusted to

them for adjudication under the statute. This is regarded as "essential to

fundamentals of fair play in the administration of law." [refer to: B. Rajgopala

Naidu v. State Transport Appellate Tribunal, AIR 1964 SC 1573 : 1964 (7) SCR 1;

Ravi Roadways v. Asia Bi, AIR 1970 SC 1241, (1970) 2 SCC 259; Raman & Raman

Ltd. v. State of Madras, AIR 1959 SC 694: 1959 Supp (2) SCR 227; R. Abdulla

Rowdier v. State Transport Appellate Tribunals, Madras, AIR 1959 SC 896; and

Senior Supdt. of Police v. Izhar Hussain, AIR 1989 SC 2262 : (1989) 4 SCC 318.]

12. We are also not in agreement with Mr. Rajiv Nayyar's submission that the

Central Government and particularly the Ministry has an all pervasive control over

NHAI. It is pertinent to mention that one of the objectives behind The National

Highways Authority of India Act, 1988 as outlined in its Statement of Objects and

Reasons was to create 'an autonomous National Highways Authority'. Consequently, in our opinion Parliament while enacting the NHAI Act, consciously

intended to limit the scope of interference by the Central Government under

Section 33 by limiting the role of Central Government to only issue directions to

NHAI on matters of 'policy'. It would be unfair to deny flexibility to statutory

authorities, particularly in tender matters. We are also of the opinion that the

nature and extent of government control depends on the provisions of the statute

creating the authority. In our view, acceptance of Mr. Nayyar's submission that

the Central Government has the power to issue directions not just confined to

policy issues, would amount to doing 'violence with the provisions of the statute',

especially when the language used in the statute is clear and unambiguous.

13. As far as the judgment of Real Food Products Ltd. (supra) is concerned,

we are of the view that the Apex Court in the facts of the said case, reached the

conclusion that the direction of the State Government to fix a concessional tariff

for agricultural pump sets related to a question of policy. In the present case, the

direction by the Ministry to revaluate the bids was certainly not a policy direction

within the four corners of Section 33 as the issue as to whether a Statutory

Auditor's certificate for the purposes of networth and experience is a mandatory

or directory provision can certainly not be termed as a 'policy decision'. In fact, in

Commissioner of Police, Bombay Vs. Gordhandas Bhanji reported in AIR

1952 SC 16 the Supreme Court has held, "It is clear to us from a perusal of these

Rules that the only person vested with authority to grant or refuse a license for

the erection of a building to be used for purposes of public amusement is the Commissioner of Police. It is also clear that under Rule 250 he has been vested

with the absolute discretion at any time to cancel or suspend any license which

has been granted under the Rules. But the power to do so is vested in him and

not in the State Government and can only be exercised by him at his discretion.

No other person or authority can do it."

14. Even in the case of Food Corporation of India (supra), the Hon'ble

Supreme Court found that the direction in that case related to a question of policy

as it would in the long run affect the interest of the consumers/producers for

which Food Corporation of India had been established. But admittedly, in the

present case, the repeated directions of the Ministry were not related to a policy

issue and, therefore, to our mind, the said judgment has no relevance.

15. In our opinion, undue interference by the Ministry in areas which are within

the domain of the NHAI and which are governed by the NHAI Act is to be

discouraged otherwise the whole purpose of enacting a Central Act and to

incorporate a statutory body would become redundant and nugatory. Having

regard to the various letters written by the Ministry as well as the letter dated 7 th

August, 2008 we are of the view that the specific direction by the Ministry to

revaluate the bids was not only contrary to the statutory mandate but it also amounted to usurping the jurisdiction of a statutory authority and amounted to

interference in its day-to-day commercial functioning. The short listing of bidders

was to be conducted by NHAI in accordance with the terms of its tender and the

Ministry could not behave like an Appellate body by reversing a decision to

shortlist the bidders - a decision which had been arrived at not only by an

independent Financial Consultant but which had also been approved by NHAI's in-

house Evaluation Committee of five members, which comprised of four technical

and one financial member. While reaching this conclusion, we are of the view

that overwhelming public interest requires interference with the Ministry's

decision making process. We are doing this not merely to make out a legal point,

therefore, even the test for interference stipulated by the Hon'ble Supreme Court

in AIR India Ltd. (supra) is satisfied in the present case.

16. Before we conclude we may mention that it was brought to our notice by

the Counsel for the Petitioners that in the last two and a half years, NHAI has had

as many as five chairmen. The names of the five chairmen and their tenure are as

under:-

   Sl. No.   Name                            Tenure


             (i)      Mr. S.N. Das                   July 2006 - October 2006


             (ii)     Mr. Pradeep Kumar        October 2006 - July 2007


             (iii)    Mr. J.S. Maini           August 2007 - Sept. 2007


(iv)   Mr. N. Gokulram           October 2007 - Sept. 2008
             (iv)     Mr. B. Singh              October 2008 to till date.




17. According to us, frequent changes of chairman of a public authority

militates against the concept of an independent authority and makes any

chairman vulnerable to pulls and pressures, besides creating administrative chaos

and preventing implementation of any long term strategy. Learned ASG informed

us that the reason for frequent changes of Chairman of NHAI was on account of

the promotion of the individual officers to a higher post in the Government. Be as

it may, we are of the view that only those officers should be appointed to the post

of Chairman who are likely to act in that capacity for a substantial time. We

would suggest to the Law Commission and the Central Government to examine

the feasibility of incorporation of statutory provisions with regard to three to five

years fixed tenure of chairman of public enterprises and further laying of all the

directions issued by the Ministries/Central Government to the public enterprises

before Parliament in a fixed time frame. This, in our opinion, would ensure

transparency, efficiency and accountability to Parliament.

18. Thus in the present case we are of the opinion that the power under Section

33 could not have been exercised for interference with evaluation of bids received

from interested parties pursuant to RFQ issued by NHAI as the same amounted to

interference with NHAI's functioning as well as with its day-to-day business. With these concurring observations the rule is made absolute and the Petitioners are

entitled to the relief as granted by my learned brother.

                                          (MUKUL       MUDGAL)

                                          JUDGE




                                             (MANMOHAN)

                                          JUDGE

16th December, 2008                                         dr/s/rkb/rn
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter