Citation : 2008 Latest Caselaw 2222 Del
Judgement Date : 11 December, 2008
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) 2604A/1999
%11.12.2008 Date of decision: 11.12.2008
J.G. ENGINEERS (P) LTD ....... Petitioner.
Through: Mr. P.K. Mullick, Advocate
Versus
NATIONAL BUILDING CONSTRUCTION ....... Respondent
CORPN LTD
Through: Mr Yogesh Malhotra, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? YES
3. Whether the judgment should be reported
in the Digest? YES
RAJIV SAHAI ENDLAW, J.
1. The arbitral award dated 28th August, 1999 was filed in this
court and notice of filing whereof was issued on 30th November,
1999. Notice was accepted on behalf of the counsel for the
petitioner herein on the same date. The petitioner has not filed any
objections to the award. The respondent filed IA.No.2119/2000
under Sections 30 and 33 of the Arbitration Act, 1940 objecting to
the award. An affidavit in opposition thereto was filed by the
petitioner and a rejoinder thereto filed by the respondent. The
counsels have been heard.
2. The admitted position is that an agreement dated 14th August,
1978 was executed between the parties whereunder the respondent
engaged the petitioner as a Piece Rate Worker (PRW) for executing
the work of construction of 100 houses in Libya. The time for
completion of the said 100 houses was fixed at 18 months from 1st
September, 1978. Additional work of 28 houses was also awarded by
the respondent to the petitioner. The agreement, aforesaid,
provided for arbitration by the Project Director of the respondent or
some other officer not directly connected with the subject work.
Disputes and differences having arisen between the parties, and by
then the appointing authority having been changed from the Project
Director to the Chairman cum Managing Director of the respondent,
on 13th November, 1985 an arbitrator was appointed. However, the
said appointed arbitrator was unable to proceed further and
ultimately vide order dated 22nd March, 1991 of this court the
arbitrator who has rendered the award was appointed as the sole
arbitrator. The petitioner herein made claims under 15 heads before
the arbitrator. The respondent made claims under 8 heads. The
award has allowed only claims No. 3 to 6, 9 and 13, that too partly of
the petitioner. The remaining claims of the petitioner and all the
claims of the respondent have been disallowed. Neither any
objection has been preferred by the petitioner to its claims
disallowed nor has the respondent objected to its claims which were
disallowed (though in writing it was merely stated that they have
been wrongly rejected). The respondent has only objected to the
claims as aforesaid of the petitioner which have been allowed. The
said objections will hereinafter be discussed claim-wise.
Re: Claim No.3
3. This claim for Libyan Dinar (LD) 230,781.900 was for payment
of items of works executed by the petitioner and not paid by the
respondent. The petitioner made this claim as extra and over and
above the rates quoted by them. The respondent refused extra
payment and rejected the claim for the reason that all the items
claimed by the petitioner as extra were covered within the rates
quoted by the petitioner for the relevant items and covered in the
technical specifications part 1 and 2 forming part of the agreement.
The petitioner contended that only technical specification part 2
formed part of the agreement and technical specification part 1 did
not form part of the agreement and maintained that extra payment
was due to it. The arbitrator found that there was no document
bearing the title "technical specification part 1 applicable to the
agreement between the parties" but held that under the technical
specification part 2 and the general specifications forming part of
the contract the work was to be executed in a workman like manner
and held certain specifications which were being treated by the
petitioner as extra items to be impliedly covered in the contract. The
arbitrator awarded LD 74690 to the petitioner under the said head.
4. The main argument of the counsel for the respondent was that
payment for extra items was prohibited under the contract and thus
the award under this head is contrary to the terms of the agreement
and thus liable to be set aside. Reliance in this regard is placed on
clause 5A in the contract and which is as under:
"5A Extra items
The said PRW shall have to execute any extra substituted items arising during the progress as per the written directions of the corporation engineer. The rates of such extra/substituted items shall be settled mutually between the PRW and the corporation."
5. Relying on Bhagat Ram Sahani v DSIDC 132 (2006) DLT 427
(DB) and State of J&K v Dev Dutt Pandit AIR 1999 SC 3196 it is
contended that where it was the term of the contract that directions
for extra work had to be in writing, allowing a claim for extra work
without any such direction in writing to carry out the same was a
jurisdictional error and which could be corrected by the court. It was
argued that the arbitrator being a creature of the contract between
the parties, if ignores the specific terms of the contract, exceeds his
jurisdiction calling for interference of the award by the court. It was
emphasized that an arbitrator acts beyond his jurisdiction if he
travels beyond the contract and the same constitutes an error
apparent on the face of the record justifying the setting aside of the
award. The contention was that in view of specific provisions
contained in Clause 5A (supra) of the agreement between the
parties, the amounts claimed by the petitioner under claim No.3
towards extra items were beyond the scope of arbitration.
6. The counsel for the petitioner has not refuted the aforesaid as
a pure proposition of law. He has, however, argued with reference
to the arbitral record that it was nowhere the plea of the respondent
before the arbitrator that the claim No. 3 being for extra item could
not be allowed in view of clause 5A of the contract. On the contrary,
it was the case of the respondent before the arbitrator that the works
claimed by the petitioner as extra items were included in the ordered
quantity and the rates fixed therefor and thus the petitioner was not
entitled separately to claim for the same; this contention of the
respondent has been found to be incorrect by the arbitrator. It was
further contended that in Bhagat Ram Sahani (supra) immediately
upon claim for extra work being made, DSIDC had denied that the
said works had been entrusted to the contractor or had been
executed by the contractor; similarly in Dev Dutt Pandit (supra)
also it was the admitted position that there was no direction in
writing for carrying out the works. On the contrary, in the present
case it was not in dispute that the works claimed as extra had been
executed by the respondent. It was argued that thus the provisions
of Section 70 of the Contract Act were attracted in the present case.
Reliance was also placed on judgments of Single Judges of this court
in Hindustan Construction Corporation v DDA 98(2002) DLT
519, Architects Bureau v Delhi Agricultural Marketing Board
2002 III AD (Delhi) 32 and Civil Engineers (India) v DDA 60
(1995) DLT 26 in which such claims were allowed.
7. In my opinion in view of the judgments in Bhagat Ram
Sahani & Dev Dutt Pandit (supra), the reference to the judgments
of the Single Judges of this court is of no avail. I do not find clause
5A in the instant case to be any different from para materia clause
in Bhagat Ram sahani (supra). However, a peculiar feature of the
present case is that no such plea was taken before the arbitrator. In
the objections filed before this court also the respondent has
objected to the finding of the arbitrator of the works claimed as extra
items under claim No.3 being covered by the contract. However, no
argument in that respect has been addressed. It is only in the
alternative that in the objections for the first time reliance was
placed on clause 5A (supra) and which objection alone was
vehemently pressed during the course of hearing.
8. What has to be considered is whether, when a plea which is
factual in nature is not set up before the arbitrator, can objections in
that respect be set up before the court at the first instance. An
award could be set aside under the 1940 Act when there was an
error apparent on the face of the record or when the arbitrator is
found to have misconducted himself. In the absence of an
objection/plea being taken before the arbitrator and which plea was
not such which could be considered without pleadings or proof, it
can neither be said that there was an error apparent on the face of
the record nor that the arbitrator has misconducted himself. It is
always open to a party to a litigation and is commonly known to
happen, to give up a defence which may have been available to it. In
the absence of the defence or the plea, the arbitrator who is to
decide in an adversorial fashion, as the court is also to decide,
cannot be expected to render decision/award on such matter. If no
decision/award could have been rendered by the arbitrator without
the plea, no fault can be found with the award on such ground. The
award cannot be said to be invalid on this ground. A point not raised
before the Arbitral Tribunal cannot be permitted to be raised for the
first time before the court unless from the award itself the error of
law becomes apparent.
9. I have been persuaded to take the aforesaid view also for the
reason that I find a basic folly in objection being pressed against an
award without the same being pressed before the arbitrator. As the
record reveals, the matter remained pending in arbitration from
1985 till 1999 and since then is pending before this court. The
alternative dispute redressal machinery in the form of arbitration has
not been as successful as it ought to have been for the reason of the
same being not much more expeditious than the courts. This has led
to a vicious cycle. If such objections not taken before the arbitrator
and which are diametrically opposite to the pleas taken before the
arbitrator are to be entertained, the same would totally nullify the
purpose and intent of arbitration. As aforesaid, even a plea given up
in court of first instance is ordinarily not permitted to be taken in
appeal. There is no reason to entertain an objection to the award
contrary to the said principle.
10. Not only was there no plea as aforesaid and qua which
objection has been raised before this court for the first time but I
find that the defence raised by the respondent before the arbitrator
to claim No.3 also negates and estoppes the respondent from setting
up the said objection in a petition under Sections 30/33 of the Act.
When the respondent contended before the arbitrator that the works
claimed as extra by the petitioner were included in the ordered
quantity, the respondent admitted that there was a direction in
writing to the petitioner to carry out the said works. In a given case
it may be permissible to, in the alternative, set up a plea that if the
same were not found to be included in the ordered quantity, the
claim was, in any case, not maintainable because of no direction to
carry out the said works being contained in any writing. However, as
aforesaid, no such alternative plea was setup before the arbitrator.
The respondent persisted with the plea of the works being included
in the ordered quantity, in the objections under Sections 30/33 of the
Act before this court also. Merely because the said defence of the
respondent has not been found to be correct, it cannot be said that if
ipso facto follows that the claims are to be disallowed as extra items
also. The contract does not give any specific form of writing in
which directions for extra work is to be issued/given. It is also not
the requirement of the contract that the direction in writing has to
be prospective or in advance in the course of operation of the
contract. The contract did provide for the petitioner to remain in
continuous contact with the respondent; several documents may
have been exchanged between the parties. Once the stand of the
respondent is that the respondent treated the said works to be a part
of the ordered or included in the ordered quantity, it is not difficult
to envisage that in the writings, correspondence, documents, bills
which may have been exchanged between the parties, the consent of
the respondent to the petitioner carrying out the said works would
be contained and which would satisfy the requirement of clause 5A
(supra). However, the occasion for the petitioner to lead evidence to
the said effect before the arbitrator did not arise owing to the
respondent having not taken the said defence inspite of the
petitioner expressly in its claim petition stating that there was no
specific rate in the contract for the same and at places also calling
the said works as extra items of work. The only conclusion which is
possible in these circumstances is that there was writing from the
respondent to the petitioner for carrying out the said works.
11. The use of the expression jurisdictional error in Bhagat Ram
Sahani (supra) had made me wonder whether allowing the claim
No.3 was such which struck at the very jurisdiction of the arbitrator.
However, I find that the same becomes a jurisdictional issue only
when it is either admitted or in evidence that there was no writing
for the extra items. However, it is not a jurisdictional issue in the
facts of the present case and does not strike at the root of the
matter.
12. The counsel for the respondent had also feebly contended that
the award does not give any reason for allowing the amounts allowed
under claim No.3 and does not give any basis for the same and is bad
for this reason. I, however, find that the arbitrator has given
norms/guidelines broadly followed by him and even though the basis
/ calculation for individual items allowed under claim No.3 has not
been stated, I again do not find the same to be a reason for setting
aside of the award. The arbitrator has the final word in such factual
matters and the court is not to sit in appeal over the award.
13. I, therefore, do not find any merit in the objection to claim
No.3 awarded and dismiss the same.
14. Re Claims 4, 5 and 6
The said claims of the petitioner for LDs 234439.368,
219082.590 and 12915.816 respectively were for damages due to
undue and unjustified prolongation of the contract. It was the
contention of the petitioner that though the houses were to be
completed by 29th February, 1980 the work was actually completed
and taken over by the respondent on 1st December, 1982. It was
further the case that extension of time was granted upto 30 th
December, 1982. It was contended that the prolongation of the
contract period was caused on account of latches and breaches of
the respondent and, therefore, the respondent was liable to
compensate the petitioner for the extra expenses incurred by the
petitioner owing to such delay. The arbitrator found delay on the
part of the respondent in complying with some of its obligations. The
arbitrator further found that the amounts claimed by the petitioner
were highly exaggerated and not on a sound rationale basis. The
arbitrator in spite of noticing the contract between the parties as
under:
"Rates to be finalized
The rates accepted by the PRW shall be firm and shall include all his expenses for execution and handing over the works to the corporation as well as for maintenance during the maintenance period according to the terms of the contract. The PRW shall have no right to claim any increase in the agreed contract rates because of increase in the price of living or increase in price of oil or any other increase whatsoever."
awarded some LDs 5000 under claim No.4, LD 25,800 under claim
NO.5 and LD 1400 under claim No.6.
15. The counsel for the respondent besides submitting that the
allowing of the aforesaid claims inspite of noticing the aforesaid
clause in the contract and finding himself to be bound by the same is
an error apparent on the face of the record has also argued that the
award of the a foresaid amounts is again arbitrary without any basis
and the principle of 8% increase followed was not applicable in the
instant case.
16. The counsel for the respondent placed reliance on State of
Orissa v Sudhakar Das JT 2000(2) SC 465 and Ram Chandra
Reddy v State of AP 2001(4) SCC 241 to contend that in the
absence of any escalation clause an arbitrator cannot assume any
jurisdiction to award any amount towards escalation and the award
which grants escalation suffers from a patent error and is liable to be
set aside. It was further contended that mere extension of time
would not entitle the contractor to claim extra payment for increase
in rates of labour and material. Per contra, the counsel for the
petitioner has in this regard relied upon Kidar Nath Sharma v
Union of India 2002 (III) AD (Delhi) 601, Bengal Traders v West
Bengal State Electricity Board 2001 (Suppl) Arbitration Law
Reporter 7 (SC) to contend that a claim for escalation is different
from a claim for damages due to prolongation of work. A single
Judge of this court in Kidar Nath Sharma (supra) notwithstanding
the judgment of the Apex Court in Sudhakar Das (supra) held the
amount awarded to be not towards escalation charges but on
account of compensation for delay. Similarly, the Apex Court in
Bengal Traders (supra) held that what was prohibited in the
contract was escalation of unit rates and the same did not apply to
the claim for damages on account of delay.
17. The counsel for the respondent in rejoinder contended that the
clause in the contract in the present case set out above was extended
beyond the contractual period also and the award finds the delay
attributable to the petitioner as well and thus no damages could be
awarded in favour of the petitioner.
18. At the outset I may state that I find inconsistencies in the
award on claims No. 4 to 6. Para 4.2 of the award notices that the
respondent had protected itself against the claim for compensation
by including a clause in the contract as aforesaid and further holds
that the clause, though found to be onerous and unconscionable, was
nevertheless to be honoured by the arbitrator. Notwithstanding the
same the arbitrator in para 4.3 of the award proceeds to award as
aforesaid under the claims No. 4, 5 and 6 without stating as to how,
if the aforesaid clause of the contract was to be honoured, the award
even if for much less than the claimed amount was sustainable. It is
the settled legal position that an award which is found to be
inconsistent is liable to be set aside. It was held in K.P. Poulose v
State of Kerala AIR 1975 SC 1259 the Apex Court held that if the
arbitrator arrives at inconsistent conclusions it amounted to
misconduct within the meaning of Section 30 of the 1940 Act. Again
in UOI v Pundari Kakshudu & Sons AIR 2003 SC 3209 it was held
that award was liable to be set aside when on the one hand there
was award of damages, suggesting that party to be guilty of breach
and a finding to the contrary, the award was liable to be set aside for
inconsistencies. This court recently in UOI v Sanghu Chakra
Hotels Pvt Ltd 2008 (3) Arb. LR 255 (Delhi) held a mutually
contradictory award to be contrary to public policy within the
meaning of Section 34 of the 1996 Act.
19. As far as the distinction made out by the counsel for the
petitioner is concerned, I find that the language of the contract in
the present case to be absolutely barring any claim for such
compensation also. Clause 6 of the General Terms and Conditions
provides that the respondent shall not be responsible for any
variation at any stage and no claims at any stage shall be entertained
as a consequence of variations, if any, except otherwise provided in
terms & conditions. The expression, "or any other increase
whatsoever" used in the contract indicates that the parties had
agreed that no claims of the petitioner for the reason of any delay
shall be entertainable. This being the position of the contract, the
principle in Bhagat Ram Sahani (supra) aforesaid would become
applicable and the award under the said claims is found contrary to
the contract and thus found to be suffering from a jurisdictional
error. The objection to claims No.4, 5 and 6 thus succeeds and the
award to that extent is set aside.
Re: Claim No.9.
20. The petitioner claimed LD 36877.050 for enhancement of rates
on contractual items from start of work till 29th February, 1980 due
to increase in minimum wages and payment of desert allowances.
The respondent contested the said claim contending that under the
contract it was the liability of the petitioner to pay the minimum
wages and there was no provision in the contract permitting the
petitioner to claim enhancement on account of increase in minimum
wages. The arbitrator awarded LD 18151 against this claim.
21. The counsel for the petitioner has sought to justify the said
award by contending on the basis of Tarapore and Company v
State of MP (1994) 3 SCC 521 (para 26 thereof) and Pride
Construction Company v DDA (1990) 1 Arbitration Law Reporter
16 that since minimum wages were statutorily payable, even in the
absence of a contractual term, such increase is reimbursable by the
respondent. However, I may notice that in Tarapore (supra) the
Apex Court has held that "insofar as the increased payment on
account of rise in the rates of minimum wages is concerned the
parties were not in any sort of agreement - express or implied to
reimburse the same" and thus allowed the said claim. Similarly in
Pride Construction Company also there was a clause permitting
increase on account of increase in wages. On the contrary, in the
present case the contract as aforesaid expressly provides that the
respondent shall not be liable to pay increased amounts for any
reason whatsoever. Under the contract, the petitioner alone is
responsible for the manpower brought from India to Libya. Thus, the
judgments relied upon by the petitioner are not applicable and there
is merit in the objections of the respondent to claim No.9 and which
is allowed and the award thereunder is set aside.
Re : Claim No.13
22. The said claim for interest at 18% per annum for LD 18073.356
for delay in payment of 38th running account bill, LD 8795.154 for
delay in payment of final bill and LD 25194.375 for delay in release
of amount of security deposit has been allowed to the extent of
interest at 8% per annum in the sum of LD 5666.37 for 38th running
bill, LD 3517 for the final bill and LD 11686.03 for security deposit.
The only objection to the said award is on account of rate of interest.
Relying upon a passage from MCGregor on damages and
Miliangos v George Frank Textiles Limited 1977 1 QB 489 it was
argued by the counsel for the respondent that interest ought to have
been granted not as per the rates prevalent in India but as per the
rates applicable to interest on LD, since under the contract payment
was to be made in LD. I, however, find the said argument to be
misconceived. Though payment was to be made in LD but it is the
admitted position that the profits of the petitioner from the said
contract could not be kept by the petitioner in LD but had to be
repatriated and kept in Indian rupees only. The citations of the
respondent also are to the effect that in award of interest the rates
prevalent of the country where the petitioner is based are to be
relied upon and not of the country in whose currency the payment is
to be made. Thus, the petitioner is entitled to interest as prevalent
here and no challenge has been made to the award of interest at 8%
per annum in the Indian conditions. The objection to claim 13 is thus
dismissed.
23. Lastly, the counsel for the respondent has objected to the
apportionment of cost of arbitration in the ratio of 40/60 between the
petitioner and the respondent. It was argued that since the
arbitrator has found the petitioner to have made exaggerated claims,
following the Dev Dutt Pandit (para 232) (supra), the entire costs of
arbitration ought to have been borne by the petitioner. The
arbitrator has in award as to costs held the parties liable for the
costs incurred by themselves and apportioned the costs aforesaid
towards the fee of the arbitrator, travel and stay of arbitrator to
Libya as aforesaid.
24. The observation as to costs came to be made by the Apex Court
in Dev Dutt (supra) owing to the contractor therein having carried
out less than 50% of the work and having been paid more than 50%
of the total contract value and having made a claim totally
disproportionate to the contract value. In these circumstances, the
Apex Court set aside the award of costs in favour of the contractor.
However, in the facts of the present case it cannot be said that the
claims were farfetched. The claims which have been disallowed and
the claims allowed and objections where against have been upheld
has also been done for the reason of the law as evolved since. It was
not the case of the respondent also before the arbitrator that the
claims were contrary to law. In the circumstances, I do not find any
ground to set aside the award as to costs. The discretion in the
award of costs of arbitration ought not to be interfered with by the
court unless is contrary to the award.
25. The arbitrator has also awarded interest at 8% per annum on
the awarded amount from the date of the reference till the date of
the payment. NO arguments have been addressed on the same. I
find the rate of interest of 8% to be reasonable and the award to that
extent shall stand.
26. Thus, the award allowing claims 4, 5, 6 and 9 is set aside. The
award on claims 3 and 13 is made rule of the court and decree is
passed in terms thereof.
RAJIV SAHAI ENDLAW (JUDGE) December 11, 2008 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!