Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Aanav Construction Company vs Oil And Natural Gas Corporation ...
2008 Latest Caselaw 2138 Del

Citation : 2008 Latest Caselaw 2138 Del
Judgement Date : 3 December, 2008

Delhi High Court
M/S. Aanav Construction Company vs Oil And Natural Gas Corporation ... on 3 December, 2008
Author: Manmohan
*      IN THE HIGH COURT OF DELHI AT NEW DELHI

+                      WP(C) No. 7730/2008

                                          Reserved on : November 21st, 2008

%                                   Date of Decision: December 3rd, 2008


M/s. Aanav Construction Company                       ..... Petitioner
                           Through:                   Ms. Geeta Luthra,
                                                      Advocate

                                      Versus

Oil and Natural Gas Corporation
Limited & Ors.                                        ..... Respondents
                             Through:                 Mr. Rakesh Sawhney,
                                                      Advocate

CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE MANMOHAN

1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?



                               JUDGMENT

MANMOHAN, J

1. The present writ petition has been filed under Article 226 of

the Constitution of India seeking a direction to the Respondents to

permit the Petitioner to participate in the subsequent September

2008 tender for excavation work at Plot Nos. 5A and 5B, Vasant

Kunj Shopping Mall, New Delhi. In the alternative, the Petitioner

has prayed for setting aside the fresh advertisement dated 16 th

September, 2008 and for a direction that only the parties

technically qualified in the initial Notice Inviting Tender

(hereinafter referred to as "NIT") dated July, 2007 be considered

for award of contract.

2. Briefly stated the facts of this case are that in July, 2007

Respondent No. 1 (hereinafter referred to as ONGC) issued a

notice inviting tender in The Economic Times, The Times of India

and Navbharat Times for excavation work at Plot Nos. 5A and 5B,

Vasant Kunj Shopping Mall, New Delhi. The tender was in two

parts, namely, technical and financial.

3. In response to the said NIT, the Petitioner filed its bid on 2nd

August, 2007. While the Petitioner‟s bid was being processed, the

Manager (ATC), Airport Authority of India addressed a letter dated

10th October, 2007 to the Regional Executive Director (NR), Airport

Authority of India, stating that he was authorised to issue an NOC

for height clearance in favour of ONGC, only upto a restricted

height of 20.74 mtr. AGL or 263.74 mtr. AMSL. Accordingly, ONGC

was directed to revise its sanctioned plan as ONGC‟s initial

application for NOC indicated the proposed height of its building

as 276 mtr. Though ONGC protested against the reduction in the

height of its building, it continued to process the bids filed in

response to its tender for excavation work. While on 5th December,

2007 ONGC opened the price bids of the Petitioners, on 27th

December, 2007 ONGC asked the Petitioner to extend its bank

guarantee till February, 2008. But as ONGC was unable to

persuade the Airport Authority of India to sanction 276 mtr. height

of its proposed building, ONGC decided on 29th December, 2007 to

cancel the tender for excavation work.

4. However, even after cancellation of tender for excavation,

ONGC continued to pursue the Airport Authority of India to

sanction its building with a height of 276 mtr. It pointed out that

in the neighbourhood, buildings with similar heights had already

been constructed and further lowering the height would prejudice

its interest as it would have to contend with a building three floors

less.

5. Ultimately, on 18th August, 2008 the Manager (ATC), Airport

Authority of India confirmed to the Regional Executive Director

(NR), Airport Authority of India that an NOC could be issued to

ONGC for a height clearance upto 281.50 mtr. Upon receipt of

said letter and whilst awaiting the formal NOC, ONGC issued a

fresh NIT on 16th September, 2008 for the same excavation work

at Plot Nos. 54A & 5B, Vasant Kunj Shopping Mall, New Delhi which

was advertised in Indian Express (Delhi edition), the Financial

Express (Delhi, Kolkata and Chennai editions), Jansata (Delhi

edition) and Asian Age (Mumbai edition).

6. Ms. Geeta Luthra, appearing for the Petitioner contended

that there was no change of circumstances between the floating of

the first NIT and its cancellation (July to December, 2007) as ONGC

never had an NOC for construction of building. She further

contended that the excavation work under both the NITs of July,

2007 and September, 2008 was absolutely identical and,

therefore, technically shortlisted bidders for the first NIT should

have been allowed to submit their price bids for the second NIT.

Ms. Luthra also stated that cancellation of the initial NIT and

floating of the new NIT was done at the instance of Respondent

No. 3 (Chief Engineer, ONGC) as he wanted to award the tender to

a particular bidder, namely, M/s. Star Construction. Though

Ms. Luthra did not urge yet we find that the primary ground taken

in the writ petition is that in a bid to restrict competition, the

subsequent NIT was not published in the same newspaper as the

original NIT, but was published in a newspaper which had a

comparatively smaller circulation.

7. Mr. Rakesh Sawhney, learned Counsel for ONGC submitted

that initially NIT had been issued in anticipation of receipt of

height clearance for ONGC‟s proposed building. He stated that

ONGC was optimistic that it would receive the height clearance as

buildings constructed in the neighbourhood had a similar height.

Mr. Sawhney stated that it was only when ONGC realised that

getting the height clearance certificate would take a long time, it

decided to cancel the initial NIT for excavation work. He further

pointed out that there was no attempt on the part of ONGC to

either restrict competition or prevent the previously shortlisted

tenderers from bidding under the new NIT. He stated that in the

initial NIT, Petitioner was not the lowest tenderer and in fact the

lowest tenderer had even participated in the subsequent NIT. He

pointed out that while the initial NIT was published on behalf of

ONGC by National Building Construction Corporation in

newspapers of its choice, the subsequent NIT had been published

by ONGC itself but that choice of newspapers had been made by

its Corporate Communication Group in which Mr. Sethi,

Respondent No. 3 had no role to play.

8. On hearing the parties, we are of the view that the

cancellation of the initial July, 2007 NIT has not been challenged

by the Petitioner in the present proceedings. In any event, we are

of the view that the cancellation of the initial NIT was neither

arbitrary nor done to favour some third party. The decision to

cancel was based on non-receipt of height clearance in October,

2007 from the Airport Authority of India and this, to our mind, was

a valid ground of cancellation specially when ONGC was uncertain

as to whether it would receive permission and if so at what time.

Moreover, from the record it is clear that ONGC wanted to further

pursue its permission for 276 mts. height building, as it did not

want to construct a building with three storeys less.

9. We are also not impressed with the Petitioner„s arguments

of malafide and restriction of competition as, firstly, M/s. Star

Construction, which is supposed to be the favoured party, has not

been added as respondent in the present proceedings. Secondly,

the bidder who had quoted the lowest price in the initial NIT has

participated in the subsequent NIT. Thirdly, there is no document

on record to indicate that there is such a vast difference between

the circulation of The Times of India and The Indian Express that

the subsequent NIT floated by the ONGC would go unnoticed. In

any event, we find that the subsequent NIT had been loaded on

the website of ONGC and if the Petitioner had been vigilant, it

would have been able to file its bid.

10. Consequently, the present writ petition being devoid of merits

is dismissed but with no order as to costs.

MANMOHAN, J

MUKUL MUDGAL, J DECEMBER 3rd, 2008 rn

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter