Citation : 2008 Latest Caselaw 1454 Del
Judgement Date : 27 August, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ R.F.A. No. 288/2006
S.M.MALHOTRA ........Appellant
Through: Mr. Vikas Dutta, Advocate
VERSUS
M/S. BLUE STAR ........ Respondent
Through: Ms. Manjula Gandhi, Advocate
RESERVED ON:
20.08.2008
DATE OF DECISION:
% 27.08.2008
CORAM:
HON'BLE MR. JUSTICE PRADEEP NANDRAJOG
HON'BLE MR. JUSTICE SUNIL GAUR
1. Whether reporters of local papers may be allowed
to see the judgment?
2. To be referred to the Reporter or not?
3. Whether judgment should be reported in Digest?
: PRADEEP NANDRAJOG, J.
1. The plaintiff is in appeal. He sought recovery of
Rs.5,69,290.35 against the defendant. Claim was predicated
on 3 contracts awarded by the defendant to the plaintiff under
work orders; work order No.2351 dated 26.3.1996, Ex.PW-1/1,
work order No.2105 dated 4.7.1996, EX.PW-1/2 and work order
No.1768 dated 16.8.1996, Ex.PW-1/D-1.
2. It may be noted at the outset that the work order
Ex.PW-1/D-1 was in supercession of the work order Ex.PW-1/2.
3. Plaintiff's case as pleaded in the plaint was that
under work order Ex.PW-1/1 he was to execute thermal
insulation work after defendant had executed ducting work
awarded to it by NPC. That basic material like polystyrene and
fiber glass had to be supplied by the defendant. He alleged
that the work of insulation which had to be completed by
28.2.1997 could not be completed for two reasons. Firstly, the
polystyrene material supplied by the defendant was rejected
by NPC, the party who had contracted the work with the
defendant, and secondly due to defendant not completing
ducting work. It was further pleaded that vide work order
Ex.PW-1/2 defendant awarded balance ducting work to the
plaintiff. It was alleged that to execute the work pertaining to
the work order Ex.PW-1/2 the defendant agreed to provide
accommodation, free of cost, to the workers to be deployed at
site by the plaintiff. It was further alleged that on 16.8.1996,
in supercession of the work order Ex.PW-1/2, work order
Ex.PW-1/D-1 was awarded.
4. Claim was predicated on alleged unpaid bills stating
that over and above the works executed at the contract rate,
the plaintiff had to rectify earlier ducting work and that for long
durations labour deployed at the site by the plaintiff remained
idle for which plaintiff claimed recompense. It was further
stated that the defendant had to arrange for "A-Grade
Welder". None was provided. It was further pleaded that while
settling the bills submitted by the plaintiff, the defendant had
illegally deducted alleged room rent for the labour stationed at
the site by the plaintiff and also for alleged supply of ancillary
materials.
5. The defendant denied any liability to pay.
According to the defendant, far from any amount payable to
the plaintiff, the defendant was entitled to a refund of
Rs.14,104/-. The defendant denied delay on its part and also
denied that it was obliged to provide, free of cost,
accommodation to the labour of the plaintiff.
6. Bar of limitation, lack of territorial jurisdiction and
non-joinder of a necessary party; requiring suit to be dismissed
were also pleaded as technical defences.
7. The plaintiff succeeded on the technical defences
raised by the defendant. The suit was held to be within
limitation. The Court found that it had territorial jurisdiction. It
was held that no necessary party was omitted to be impleaded
as a defendant.
8. Since the defendant has not filed any cross appeal
or cross objections pertaining to issues decided against the
defendant we need not bother ourselves with the facts
constituting the 3 technical defences and hence we
concentrate on the main issue debated between the parties;
namely, whether the plaintiff was entitled to a decree in sum of
Rs.5,69,290.35 or whether it had received excess payment in
sum of Rs.14,104/-.
9. At this stage, we may note that though having
pleaded that it had paid Rs.14,104/- in excess to the plaintiff
the defendant did not seek recovery thereof by way of a
counter claim.
10. Plaintiff examined himself as his only witness. The
defendant examined its Senior Manager (Commercial)
Sh.T.K.S.Kuti as its only witness.
11. Apart from proving the 3 work orders on which we
note parties were not at variance the plaintiff reiterated the
case pleaded in the plaint. The plaintiff proved Ex.PW-1/6, a
bill raised upon the defendant on 31.7.1996 raising a claim for
idle labour in sum of Rs.27,900/-. Plaintiff also proved Ex.PW-
1/7, a letter dated 15.7.1996 written by the defendant
acknowledging not meeting the commitment of the defendant.
The plaintiff also proved Ex.PW-1/9, being defendant's letter
acknowledging that stationing "A Grade Welder" was a
problem at site.
12. Various other communications addressed between
the parties were proved at the trial which we are not noting for
the reason, while arguing the appeal learned counsel for the
appellant urged submissions predicated on Ex.PW-1/6, Ex.PW-
1/7and Ex.PW-1/9.
13. As against the aforesaid documentary evidence of
the plaintiff, defendant hinged its case on Ex.PW-1/D-3, Ex.PW-
1/D-4 and Ex.PW-1/D-5.
14. Ex.PW-1/D-3 is a communication dated 28.11.1996
from the defendant to the plaintiff enclosing therewith a
statement of the running bills received by the defendant from
the plaintiff with defendant's remarks thereon; the document
terminates with the defendant's certification of the bills raised
by the plaintiff as settled for payment by the defendant and
money released. Ex.PW-1/D-4 is defendant's lettter dated
4.12.1996 addressed to the plaintiff. It refers to the bills
received from the plaintiff post 28.11.1996. It records the
defendant's version of what was payable to the plaintiff under
the bills. It refers to excess payments raised by the plaintiff. It
refers to the fact that the plaintiff did not execute certain
works, which were claimed to have been executed by the
defendant at the risk and cost of the plaintiff.
15. Ex.PW-1/D-5 is defendant's letter dated 26.5.1997
addressed to the plaintiff refuting the claim for any further
payment and requesting plaintiff to refund Rs.14,104/-.
16. The defendant's witness gave evidence in harmony
with the defence set up.
17. Noting that in the oral testimony of the two
witnesses i.e. the witness of the plaintiff and the defendant,
respective versions were given, the Learned Trial Judge held
against the plaintiff for the reason there was no documentary
evidence to show that the plaintiff refuted Ex.PW-1/D-3, Ex.PW-
1/D-4 and Ex.PW-1/D-5. The findings returned by the learned
Trial Judge are as under:-
"16. On the other hand, it is argued by ld counsel for the defendant that Sh.Rajput was representative of the plaintiff working at the site at Banglore with whom matter was sorted out. It is argued that subsequently plaintiff also admitted that he had received statement of the payments made to the plaintiff Ex.PW-1/D-3, PW-1/D-4 and D- 5 but he did not prefer to give reply thereto which is a clear proof that nothing was due and payable to the plaintiff. It is argued that plaintiff has not denied that Ex.PW-1/D-4 and D-5 were received by him and further has admitted that it preferred to give no reply to these letters, hence, no amount is due and payable.
17. It is true that plaintiff has proved on record that orders Ex.PW-1/1 and 1/2 were given to him and that he submitted bills Ex.PW-1/6, 1/7. However, the fact remains that defendant had sent a statement of account regarding claim of the plaintiff and payments made to him. It has been proved as Ex.PW-1/D-3. It is dated 28.11.96. In this document, defendant has given details of
various payments made to the plaintiff. Similarly defendant wrote the plaintiff Ex.PW1/D-4 dated 4.12.96. In Ex. PW1/D-4, it has been mentioned by the defendant that it had sent final bill against work order No.2351 and it was also mentioned that various payments had been made to the plaintiff. Defendant had also requested the plaintiff to settle the payment on receipt of which hammer drilling machines will be returned. Again, defendant wrote another letter Ex.PW1/D-5 which is dated 26.5.97. In this letter also, various payments made have been mentioned. It was also mentioned by the defendant that when statement of account was drawn it was found that an excess payment of Rs.14104/- was made to the plaintiff and it was requested that plaintiff should refund the same. In Ex.PW1/D-3 defendant had made references to the payments made in respect of bill No.2351. In Ex.PW1/D-4 there is a reference of work order No.2351 and the payments made. It was also mentioned in this letter that final bill in respect of work orders No.2351 was received. The defendant pointed out that it had already paid Rs.14104 in excess to the plaintiff in respect of these works and had requested the plaintiff to refund the same. In letter Ex.PW1/D-5 there is reference to work order No.2105. In this letter, it has been mentioned that the representative of the plaintiff Mr.Rajput was requested to make a final bill for the work carried out and according to final bill made by him and scrutinized by representative of the defendant claims were finalised. It is mentioned that when statement of account was drawn it was found that defendant had paid excess amount of Rs.14104/- to the plaintiff and requested him to refund the same. In his cross examination, PW-1 has admitted that he has received the statement of payments Ex.PW1/D-3 but he did not reply the same. In Ex.PW-1/D-3 he has also admitted that he did not send reply thereto. He has even admitted that he has received Ex.PW1/D-4 and D-5 but no reply was sent by him to these letters. When the plaintiff admitted that he had received letters Ex.PW-1/D-3 to D-5 containing assertion on behalf of the defendant that it did not owe any liability to
the plaintiff, I am of the view that inference is that plaintiff did not dispute the position as set up by the defendant. In other words, inference is that plaintiff admitted that it did not have any claim against the defendant. I am, therefore, of the view that it has been proved on record by the defendant that claim of the plaintiff was settled by the defendant. I, therefore, hold that plaintiff has failed to prove that he had any cause of action to file the present suit or the defendant is liable to pay any amount to the plaintiff. These issues are accordingly decided in favour of defendant and against the plaintiff."
18. Though not expressly recorded by the learned Trial
Judge, it is apparent that the signature tune of the decision of
the learned Trial Judge is the contemporaneous conduct of the
parties; the contemporaneous conduct being the plaintiff not
responding, in writing, to Ex.PW-1/D-3, Ex.PW-1/D-4 and
Ex.PW-1/D-5. It is apparent that the rival oral versions, being a
case of word of mouth versus word of mouth, the impasse has
been broken by the learned Trial Judge with reference to the 3
documents, Ex.PW-1/D-3, Ex.PW-1/D-4 and Ex.PW-1/D-5 written
by the defendant to which no contemporaneous denial was
made by the plaintiff.
19. It was urged by learned counsel for the plaintiff that
the learned Trial Judge gravely erred in not appreciating that
while raising a bill Ex.PW-1/6 on 31.7.1996, the plaintiff had
raised a claim for idle labour. With reference to Ex.PW-1/7 the
learned counsel urged that the learned Trial Judge failed to
appreciate that in the said letter dated 15.7.1996 the
defendant acknowledged having failed to meet it's
commitment under the contract. With reference to Ex.PW-1/9,
learned counsel urged that the learned Trial Judge failed to
appreciate that in said letter defendant acknowledged that
providing "A Grade Welder" at the site had been a problem.
20. Per contra, learned counsel for the defendant urged
that the reasoning of the learned Trial Judge is correct for the
reason admittedly plaintiff never refuted Ex.PW-1/D-3, Ex.PW-
1/D-4 and Ex.PW-1/D-5.
21. It is settled law that where, on a given evidence,
two views are possible the Appellate Court would not
substitute its view with the view taken by the learned Trial
Judge. The jurisdiction of First Appellate Court and especially
when the Appellate Court is the final Court of law and facts is
to consider, with reference to the evidence, whether the view
taken by the learned Trial Judge is reasonably probable and
while so doing it has to be ensured that the learned Trial Judge
has neither ignored material evidence or a material
circumstance and has not included irrelevant evidence or an
irrelevant circumstance while evaluating evidence. If it is
found that material evidence or circumstance has been
ignored, the evidence has to be reconsidered bringing into
consideration the material evidence or the material
circumstance found ignored by the learned Trial Judge.
Similarly, where irrelevant evidence or irrelevant circumstance
has been brought into aid while considering evidence by the
learned Trial Judge, the Appellate Court has to reprobablize the
evidence ignoring the said irrelevant evidence or irrelevant
circumstance.
22. Indeed, the plaintiff never refuted Ex.PW-1/D-3,
Ex.PW-1/D-4 and Ex.PW-1/D-5. This gives credence to the view
taken by the learned Trial Judge that the contemporaneous
conduct of the parties reveals that the plaintiff did not refute the
reasons on which the defendant reduced the amount payable
when cleared the bills received from the plaintiff.
23. It would not be out of place to mention that vide
Ex.PW-1/D-3 all bills submitted by the plaintiff till 16.08.1996
were processed and against each bill, defendant gave comments
under the 'remarks' column. Further, cash payments made to the
employees/representative of the plaintiff at site were also
detailed. Further, Rs.45,790/- paid to the workers of the
appellant at site were referred to and deducted from the net
amount payable to the plaintiff. In the said document the
defendant made adjustment for material supplied by it to the
plaintiff by recording as follows:-
"I understand that we have supplied some material such as bolts, nuts, screws etc. to you from out office which is also debittable to your account. Your bills 105 and 106 are being processed and it will be adjusted in the excess payment already made to you."
24. No letter was shown to us by learned counsel for the
plaintiff rebutting the contents of Ex.PW-1/D-3.
25. Similarly, while writing Ex.PW-1/D-4 on 4.12.1996 the
defendant wrote: "based on your workers' demand and
subsequent discussions between NPC officials, your
representative Mr.Rajput and Blue Star Ltd., we have settled the
payment of wages of your 10 workers for a total amount of
Rs.45,790/-. A copy of the stamped receipts has been collected
by your representative Mr. Rajput."
26. No document was shown to us rebutting the aforesaid
contents as also other contents of Ex.PW-1/D-4. Similarly,
learned counsel for the plaintiff could not point out any letter
written by the plaintiff rebutting defendant's letter dated
26.5.1997 Ex.PW-1/D-5.
27. Conduct of the parties when a contract is under
execution is relevant evidence. It throws light as to how parties
understood the implementation of the contract from time to time.
Thus, we are in complete agreement with the view taken by the
learned Trial Judge that Ex.PW-1/D-3, Ex.PW-1/D-4 and Ex.PW-
1/D-5 show that the plaintiff never refuted the scaling down of
the bills submitted by the plaintiff; adjustment of payment
made to the workers of the plaintiff by the defendant as also
adjustment on account of certain material supplied by the
defendant to the plaintiff.
28. As noted hereinabove, learned counsel for the
plaintiff made submissions with respect to Ex.PW-1/6, Ex.PW-
1/7 and Ex.PW-1/9.
29. Vide Ex.PW-1/6, plaintiff raised a bill in sum of
Rs.27,900/- on account of idle labour. It was urged that receipt
of said bill and payment due pertaining to the bill stands
admitted by the defendant, being entry at serial No.3, in
Ex.PW-1/D-3. Learned counsel for the plaintiff urged that
having admitted entitlement of the plaintiff to receive idle
labour charges the defendant was precluded from urging to
the contrary.
30. Pertaining to Ex.PW-1/6, as urged by learned
counsel for the defendant, we note that while settling the
various bills raised by the plaintiff, in Ex.PW-1/D-3, the
defendant referred to the said bill but cleared payment only in
sum of Rs.10,000/- as against Rs.27,900/- claimed in the bill.
31. As noted hereinabove, the plaintiff never refuted the
contents of Ex.PW-1/D-3.
32. It is obvious that defendant accepted limited liability
on account of idle labour charges and released payment for
the amount relatable to the liability admitted and plaintiff
accepted the amount without demur. We say so for the reason
in Ex.PW-1/D-3, the defendant paid only Rs.10,000/- towards
idle labour charges.
33. That explains Ex.PW-1/6.
34. No doubt, vide Ex.PW-1/7, the defendant did write
that it did not meet defendant's commitment under the
contract. However, we note that the sentence on which
learned counsel for the plaintiff picked up is a polite language
used in a commercial letter. Read in the context of the
succeeding sentence the truth would be revealed. The
defendant has written as under:-
"We record to inform you that we could not meet our commitment just because of your uncomplete work. So far you did not shift your angles to the RAB-1 ladder welding generator. This is why we could not complete our supporting."
36. As we read the paragraph, in a polite language, the
defendant has conveyed to the plaintiff that on account of
plaintiff not shifting angles to the RAB-1 ladder welding
generator the defendant could not comply of its commitment.
Thus, we find no admission as alleged.
36. We note that two documents have been exhibited
as Ex.PW-1/9. The first is a letter written by the plaintiff to the
defendant (at page 337 of the record of the Trial Court). The
other is a letter written by the defendant to the plaintiff on
25.7.1996 (at page 345-347 of the Trial Court Record).
37. No doubt, in the said letter, the defendant has
acknowledged that non-availability of A Grade Welder at the
site has created a problem. But, that by itself would be neither
here nor there for the reason we find no evidence on record to
show the consequences of non-availability of A Grade Welder
at site.
38. We note that vide Ex.PW-1/10, plaintiff raised an
issue on account of non-availability of a welder at site for 2½
months. We note that Ex.PW-1/10 was written by the plaintiff
to the defendant on 4.8.1996.
39. In the absence of any evidence or material to link
idle labour deployed at the site by the plaintiff on account of
non-availability of A Grade Welder, we are afraid, we are
unable to quantify any amount payable to the plaintiff. We are
further handicapped for the reason learned counsel for the
plaintiff could not locate any proved document whereunder
plaintiff had raised a specific bill on account of labour rendered
idle for non-availability of A Grade Welder.
40. Learned counsel for the defendant pointed out to us
that the bill for idle labour raised on 22.7.1996 was the bill
relatable to idle labour on account of non-availability of A
Grade Welder. Counsel pointed out that said bill of the plaintiff
was duly noted in defendant's letter Ex.PW-1/D-3 and as
against claim in sum of Rs.27,900/-, the defendant had paid
Rs.10,000/-. Counsel urged that it is apparent that the bill for
idle labour on account of non-availability of A Grade Welder
was raised by the plaintiff in sum of Rs.27,900/- and accepted
by the defendant in sum of Rs.10,000/-. Further, when the
defendant accepted part liability and tender payment for the
same, plaintiff accepted the payment without demur.
41. In view of the fact that primary documents are not
available on the judicial record and in the absence of any other
bill for idle labour shown to us pre 4.8.1996 there is
considerable merit in the submissions made by learned
counsel for the defendant that the plaintiff was recompensed
for idle labour at site due to non-availability of A Grade Welder.
42. We find no merits in the appeal.
43. The appeal is dismissed.
44. Defendant would be entitled to cost all throughout.
PRADEEP NANDRAJOG, J.
August 27, 2008 SUNIL GAUR, J. mm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!