Citation : 2008 Latest Caselaw 1426 Del
Judgement Date : 22 August, 2008
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)2790/1993
% Date of decision : 22.08.2008
TARAPORE AND COMPANY ....... Petitioner.
Through: Mr Jagdeep Kishore with
Ms Rekha Gupta, Advocates
Versus
1. NATIONAL THERMAL POWER CORPORATION
LTD
2. RASHTRIYA PARIYOJAJA NIRMAN ...... Respondents
NIGAM LTD Earlier known as NATIONAL PROJECT CONSTRUCTION CORPN LTD
Through : Mr K.L. Budhiraja with Mr paritoshBudhiraja, Advocates for Respondent No.2.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? Not Necessary
3. Whether the judgment should be reported Not Necessary
in the Digest?
RAJIV SAHAI ENDLAW, J
A. The petitioner has applied under Section 20 of the Arbitration
Act 1940 on the ground, that the respondent No.2 had entered into
a contract containing an arbitration agreement with the petitoner in
relation to the works assigned by respondent No.1 to the respondent
No.2 and that differences had arisen in relation to the subject
matter of the said agreement between the respondent No.2 and the
petitioner and for the said agreement to be filed in court and for
appointment of a retired judge of this court as arbitrator to
adjudicate the said disputes and differences. Notice of the petition
was issued to both the respondents. The respondent No.1 was
proceeded ex parte on 11th July, 1995 and remains ex parte. On 11th
July, 1995 the following issues were framed:
"1. Whether the arbitration agreement between National Thermal Power Corporation and respondent No.2 as reproduced in annexure P-1 can be enforced by the petitioner as against respondent No.2? OPP
2. Whether the petition is within time? OPP (Onus objected to)
3. Whether the petition has been signed, verified and instituted by an authorized person on behalf of the petitioner? OPP
4. If it is proved that there is arbitration agreement between the parties, whether matter cannot be referred to the arbitration for the reasons stated in the written statement? OPD
5. Relief."
B. The petitioner and the respondent No.2 filed their affidavits
by way of evidence. Neither of the parties applied for cross
examination of the witness of the other.
C. The counsel for the petitioner and the respondent No.2 have
been heard. My issue-wise findings are as under:
On Issue No.1
1. The petitioner approached the court on the plea that a
contract dated 19th October, 1983 had been executed between the
petitioner and the respondent no.2; that the general conditions of
contract between the respondent No.1 and the respondent No.2
form part of the terms and conditions governing the contract
between the petitoner and the respondent No.2; that the said
general conditions of contract between respondents No. 1 and 2
contain an arbitration clause; that the respondent No.1 had been
impleaded as a Performa respondent for this reason; that though the
said general conditions of contract provided for the arbitration of
the General Manager of the respondent No.1 or of some person
appointed by the Chairman and Managing Director of the
respondent No.1 but the appointment of an arbitrator was sought
from the court; that the contract of petitioner with respondent No.2
was back to back contract between respondent No.1 and respondent
No.2; that the petitioner had issued notice dated 2nd August, 1983 to
the respondent No.2 for appointment of sole arbitrator but the
respondent failed to comply with the said notice.
2. The respondent No.2 in its reply averred that the petition
was not maintainable as there was no arbitration agreement
between the petitioner and the respondent No.2; it denied that the
contract between the petitioner and the respondent No.2 was on
back to back basis to the contract between the respondent No.1 and
the respondent No.2; it was averred that the contract between the
respondent No.1 and the respondent No2 was separate and had
nothing to do with the contract between the petitioner and the
respondent No.2 and as such the arbitration clause in the contract
between the respondents No 1 and 2 was not an agreement between
the petitioner and the respondent No.2.
3. The petitioner in its rejoinder reiterated that its contract
with the respondent was on a back to back basis to the contract
between the respondent No.2 and the respondent No.1 and that the
conditions of contract and general conditions of contract between
the respondents No. 1 and 2 were applicable to the contract
between the petitioner and the respondent No.2. The petitioner also
relied upon letter dated 12th May, 1990 of the respondent No.2
where the respondent No.2 had taken a stand that the payments by
the respondent No.2 could be released in favour of the petitoiner
only after receipt from the respondent No.1 and stating that the
contract with the petitioner was on a back to back basis.
4. The affidavits by way of evidence of the witnesses of
petitoiner and the respondent No.2 merely reiterated the pleadings
aforesaid. The respondent No.2 also filed letter dated 21st April,
1990 of the petitioner to the respondent No.2 (and which was
admitted by petitioner) as Exhibit R2/1 in which the petitioner in
response to a letter dated 13th April, 1990 of the respondent No.1,
had taken a stand that the contract of the petitioner with the
respondent No.2 was not on back to back basis as claimed by the
respondent No.2 in the letter dated 13th April, 1990.
5. The Arbitration Act 1940 in Section 2(a) thereof defines
the arbitration agreement as meaning a written agreement to
submit present or future differences to arbitration, whether an
arbitrator is named therein or not. It is therefore to be seen
whether any such written agreement exists between the petitioner
and the respondent No.2. The contract between the petitioner and
the respondent No.2 was reduced into writing dated 19th October,
1983 proved as Exhibit P3. The respondent No.2 vide the said
letter awarded the works mentioned therein to the petitioner on the
terms and conditions contained therein. The terms and conditions
specified therein refer to the contract of the respondent No.2 with
the respondent No.1 to define the scope of work of the petitioner
but does not refer to the agreement generally and does not contain
any clause that the terms and conditions between the respondent
No.1 and respondent No.2 shall mutatis mutandi or otherwise apply
to the contract between the petitioner and the respondent No.2.
6. The petitioner returned a copy of the said letter to the
respondent No.2 with its signatures in token of acceptance of the
terms and conditions contained therein and the same has been
proved as Exhibit R2/2. The respondent No.2 is a juristic person
and a governmental undertaking. There are authorisation / rules /
powers entrusted to each and every officer of such an undertaking.
Entering into an agreement by such undertakings is a formal act /
exercise and in the present case has been done formally by issuance
of Exhibit P3 / Exhibit R2/2 as aforesaid to the petitioner and by
receiving signatures of the petitioner on a copy of the same. When
the parties have reduced the terms and conditions agreed between
them into writing, the said writing unless the contrary is proved is to
be considered as the sole repository of the terms and conditions
settled between the parties. The parties then cannot be permitted
to setup terms and conditions contrary or inconsistent therewith.
The same is the spirit of Sections 91 and 92 of the Indian Evidence
Act, 1872. The petitioner has neither pleaded nor proved any other
agreement, besides that in Exhibit P3 / Exhibit R2/2.
7. The writing between the petitioner and the respondent
No.2 neither expressly nor by implication nor by reference contains
any arbitration agreement. The counsel for the petitioner urged
that the respondent No.2 did not deny the arbitration agreement in
response to the legal notice got issued by the petitioner and denied
the existence of the arbitration clause for the first time in reply to
the petition only. In my opinion the same is irrelevant. Under the
1940 Act there could not be arbitration agreement by one party
pleading the same and by the other party not denying the same. It
is only in 1996 Act that a provision has been made that an
arbitration agreement can be considered to be in writing if in an
exchange of statements of claim and defence in which the existence
of the agreement is alleged by one party and not denied by the other
(See section 7(4)(c) of the Arbitration and Conciliation Act 1996).
However, the said principle cannot be applied to the 1940 Act. As
far as the case of the petitioner of the agreement of the petitioner
with the respondent No.1 being on back to back basis to the
agreement between the respondents No. 1 and 2 is concerned, it is
not so provided in Exhibit P3 / Exhibit R2/2. In the absence of the
written agreement between the parties providing so, simply because
respondent No.2 assigned part of the work, assigned to it by the
respondent No.1, to the petitioner, it cannot be said that the
agreements were on back to back basis. Even though the letter
dated 12th May, 1990 of the respondent No.2 relied upon by the
petitioner in its rejoinder to set up a case of contract on back to
back basis has not been proved in evidence but if looked into, calls
the contract of the petitioner with respondent No.2 on back to back
basis only for the purposes of release of payments by the respondent
No.2 to the petitioner. The petitioner, however, itself disputed the
said position vide exhibit R2/1 (supra). The petitioner having at the
contemporaneous time disputed that the agreements were on a back
to back basis, cannot be permitted to setup a contrary case.
Moreover, the letter dated 12th May, 1990 is issued by a unit officer
of the respondent No.2 while the agreement dated 19th October,
1983 Exhibit P3 is signed by the General Manager of the respondent
No.2 and normally a unit officer would not be entitled to add to an
agreement which had been made by the General Manager.
8. The counsel for the petitioner relied upon M/s Dalmiya &
Co. Ltd v International Airport Authority of India 1994 IV AD
(Delhi) 437 and G. Ramachandra Reddy v Chief Engineer AIR
1994 SC 2381. However, in both these, the existence of arbitration
agreement was not in dispute and I do not find these judgments
relevant to the present lis.
9. I, therefore, hold that there is no arbitration agreement
between the petitioner and the respondent No.2. I also find that it
was not agreed between the petitioner and the respondent No.2 that
the arbitration agreement between the respondents No 1 and 2 can
be enforced by the petitioner against the respondent No.2. The
issue No.1 is thus decided against the petitioner and in favour of the
respondent No.2.
Though, upon decision of the issue No.1, the petition is liable to be
dismissed but since issues were framed, I proceed to decide the
other issues also.
On Issue No.2.
1. The petition states that the cause of action arose from
time to time when various letters were written by the petitioner
calling upon respondent to help them in execution of the work and
the cause of action lastly arose when notice dated 2nd August, 1993
for appointment of sole arbitrator was sent and the respondent
failed to comply with the said notice.
2. The respondent has pleaded that the work was completed
in February, 1987 and the final bill was submitted by the petitioner
on 9th December, 1987; that the final bill for the work was of Rs
20,42,934/- which was duly accepted by the petitioner and that full
and final payment had already been made as per duly accepted final
bill; that the petitioner had subsequently raised an alleged final bill
for Rs 1,24,03,910.75 and which was rejected by the respondent
No.1 vide its letter dated 10th April, 1989 and thus the claim was
barred by time.
3. The petitioner in its rejoinder admitted that the work was
completed in 1987 and the final bill was submitted on 9th December,
1987 but pleaded that the respondent No.2 in its letter dated 21 st
September, 1989 had intimated the petitioner that if the petitioner
was willing to give an undertaking agreeing to receive 50% of the
amount of claim as released from respondent No.1, the claim of the
petitioner would be sent to the respondent No.1. The petitioner
pleaded that this clearly meant that the payment was to be released
by the respondent No.2 to the petitioner only after receipt from the
respondent No.1. Upon the failure of respondent No.2 to disclose
the payment received from the respondent No.1, the petitioner had
written directly to the respondent No.1 and the respondent No.1
had vide its letter dated 25th February, 1994 to the petitioner
received by the petitioner after the institution of the petition
informed that the respondent No.1 had released full and final
payment to the respondent No.2 upon the respondent No.2
submitting No Demand Certificate on 25th October, 1993. It was
argued that the final payment would have been released by the
respondent No.1 to the respondent No.2 only after the No Dues
Certificate dated 25th October, 1993. It was therefore urged that
the claim could not be barred by time. The claim by the petitioner is
for the works done, extra work done, extra materials used at the
instance of the respondent No.2 and for escalation charges. The
agreement between the parties Exhibit P3 / Exhibit R2/2 in clause 8
provides that monthly running account payment was to be released
on the basis of quantities actually executed by the petitioner and
recorded at the close of every month and the payments were to be
released within 7 days from the date of submission of detailed bill
based on joint measurements. However, it was further provided
that the final quantities payable for the works executed shall in no
case exceed the quantities paid by the respondent No.1 to the
respondent No.2 and "therefore the final bill and monthly R.A. Bill
quantities payable to you shall be limited to the quantities billed and
paid" by the respondent No.1 to the respondent No.2.
4. Article 18 of Schedule I of the Limitation Act provides the
limitation of three years from the date when the work is done for the
recovery of price of work done by the plaintiff for the defendant,
where no time of payment has been fixed. In the present case,
however, time for payment has been fixed as after the receipt of
payment by the respondent No.2 from the respondent No.1.
5. The witness of the respondents in his affidavit has
referred to acceptance by the petitioner as full and final settlement
and with a further endorsement of no further claim for escalation.
However, no such document has been proved by the respondent
No.2.
6. That the agreement between the parties appears to
suggest that payments by the respondent No.2 to the petitioner
were to depend on the payments by the respondent No.1 to the
respondent No.2. If that were to be so, then the claim of the
petitioner does not appears to be barred by time. However, since
these are section 20 proceedings in which only affidavit evidence
has been led and since upon the finding on issue No.1, the petition
is to be dismissed, I refrain from giving any final finding on this
issue and leave it to be decided by examination and cross
examination of witnesses in appropriate proceedings, if any
instituted,
On Issue No.3.
1 The witness of the petitioner Shri R.K. Anand has stated
that he has instituted, signed and verified the petition on behalf of
the petitioner. The petitioner is stated to be a registered
partnership firm; the certificate of registration has been proved as
Exhibit P1 and the power of attorney in favour of the said Shri R.K.
Anand executed by one of the registered partners of the petitioner
has been proved as Exhibit P2. The petitioner has thus proved due
institution of filing of the petition. The Issue No.3 is decided in
favour of the petitioner and against the respondent No.2.
Issue No.4.
The said issue appears to have been framed on the plea of
the respondent No.2 of full and final settlement. However, as
aforesaid, the said document has not been proved by the respondent
No.2. The said issue is, therefore, decided in favour of the
petitioner and against the respondent No.2.
Issue No.5.
In view of the finding on issue No.1, the petition is
dismissed, however, with no order as to costs.
RAJIV SAHAI ENDLAW, J.
August 22, 2008.
M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!