Citation : 2008 Latest Caselaw 1411 Del
Judgement Date : 21 August, 2008
7
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) 1760A/1995 & IA No.3974/1996
ANANT RAJ AGENCIES ..... Plaintiff
Through : Mr. Harish Malhotra, Sr. Advocate with Ms.Namita
Chaudhary, Advocte
versus
DELHI DEVELOPMENT AUTHORITY ..... Defendant
Through : Ms. Anusuya Salwan with Ms. Monica Sharma
and Ms. Renuka, Advocates
CORAM:
Mr. Justice S. Ravindra Bhat
1.
Whether reporters of local papers may be allowed to see the judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
Mr. Justice S. Ravindra Bhat (Oral)
IA No.3974/1996
1. In this proceeding the defendant/Delhi Development Authority (DDA)
challenges the legality and correctness of an award dated 20th July, 1995,
published by the sole arbitrator, appointed by the parties.
2. The brief facts, essential for deciding this case are that the claimant-
plaintiff (hereinafter referred to as the Contractor) was awarded civil works i.e
development of land at Rohini, Phase I, SH : providing and lying water supply
distribution lines in Sectors IV and V. According to the agreement the work was
to be completed on 26th March, 1983. However, it is an undisputed fact that
for varied reasons the time period was not adhered to. The DDA apparently
granted extension of time without levying compensation though it had the
power to do so. The work was completed on 01.10.1985. The contractor
raised several claims and ultimately the matter was referred to arbitration by
the DDA. The arbitrator entered upon the reference on 13.03.1992. The
parties to the proceedings lead evidence and on 20.07.1995 and the impugned
award was made and published. The contractor had raised nine heads of
claims with two heads of additional claims in arbitration. The DDA had initially
contended in the arbitral proceedings that the disputes were "excepted"
matter and that the claims were time barred. The arbitrator over-ruled both
the objections and published his award on the merits.
3. The DDA, through its counsel contends that the findings with regard to
claim No.2 are without foundation. It was contended by Ms.Anusuya Salwan,
counsel for DDA, while relying on Clause 7, the award of Rs.47,306.28 was not
justified in the facts and circumstances. It was contended that the claims of
the contractor in the final bill were barred by limitation and that the arbitrator
ignored Clause 7 which enjoined him (the contractor) to submit the bill within
one month of the date fixed for completion of the work or of the date of the
certificate furnished by the Engineer In-charge.
4. Learned counsel next contended that the award for the sum of
Rs.1,97,130/- under the head claim No.3 was untenable. She relied upon the
Additional condition No.1 which stipulated that the contractor should have
been acquainted with the proposed site of the works and studied specifications
and conditions before submitting the tender. It was submitted that the amount
awarded to the contractor, are in the nature of damages which cannot be
sustained having regard to the various decisions of the Court.
5. Learned counsel next contended that the findings and the award in
respect of claim No.4 are unsustainable in law as the arbitrator had termed it
"infructuous expenses". The amount of Rs.1,20,000/- was awarded against the
DDA. Counsel submitted that this finding is unsupported by any evidence. It
was urged that even assuming that the contractor had a legitimate claim, the
existence of such claim did not absolve him from leading evidence in support
of it. Thus in the absence of evidence and any reasoning in support, the
arbitrator should not have awarded a sum of Rs.1,20,000/- in favour of the
contractor for so called infructuous expenses.
6. Learned counsel submitted that uniform interest @ 18% per annum with
quarterly rests under claim Nos. 5, 8 and 9 was completely unjustified. It was
submitted that the contractor had preferred separate heads of claim in arbitral
proceedings towards pre-suit, pendent lite and future interest; instead of
applying his mind and awarding reasonable interest (assuming the contractor
was entitled to any amount) the arbitrator awarded a uniform rate of interest
which works in excess of 20% p.a., based on the formula adopted. Learned
counsel relied upon recent judgments to say that upholding of such award of
higher rate of interest under the present circumstances is unfeasible.
7. Learned counsel submitted that the award of Rs.3,01,143.51 in favour of
the contractor towards first additional claim is also not tenable in law. The
contractor had urged that the extension of contract resulted in deprivation of
opportunity to make reasonable profit. Counsel contended that adoption of
hypothetical mathematical formula to arrive at a figure of Rs.3,01,143.51
which was ultimately awarded on this head, was not correct. She relied upon
judgment of this Court reported in Delhi Jal Board Vs. Subhash Pipes Ltd., 2005
(2) Arb. Law Reports 213 and Avtar Singh Chadha Vs. Municipal Corporation of
Delhi, OMP 296/2006 decided on 21st May, 2007. Learned counsel further
relied upon the judgment of the Supreme Court reported in Bharat Coking Coal
Ltd. Vs.L.K. Ahuja, 2004 (5) SCC 109.
8. Ms. Salwan, lastly submitted that the award of 8% interest from
01.04.1986 till the date of payment on the sum of Rs.1,00,000/-, was
unjustified. The arbitrator had allowed this claim on the ground that the
contractor had to maintain a fixed deposit for a sum of Rs.1,00,000/- to comply
with the stipulation for keeping alive a bank guarantee. The DDA contends
here that the bank guarantee had in fact lapsed and that in any case the fixed
deposit itself earned interest.
9. Mr. Harish Malhotra, learned senior counsel for the contractor resisted
the opposition to the award. He submitted that having regard to the limited
jurisdiction of the Court, the findings in the award cannot be interfered.
Learned counsel submitted that the approach of the arbitrator cannot be
faulted as unreasonable and that the findings were supported by the evidence
as well as materials on record.
10. Learned counsel pointed out that the findings of the arbitrator regarding
the culpability of the DDA in regard to the various delays which led to
extension being granted without levy of compensation has not been impugned.
The arbitrator found that even according to the records of the DDA there was
delay of 920 days on its part. The counsel submitted that the discussion in
this regard is elaborated in the findings concerning claim No.3. It was
submitted in these circumstances, the award for the sum of Rs.47,306.28, can
hardly be characterized as arbitrary; in any event the DDA's objections in this
regard are without basis. Counsel submitted that as far as findings on claim
No.3 for the award of Rs.1,97,130/- is concerned, the reasoning is sound. It
was submitted that the contract entered into by the parties stipulated for
compensation only as regards as escalation in labour cost by way of Clause 10
(C). In the circumstances the arbitrator was justified in awarding the sum of
Rs.1,97,130/- as against the claim for Rs.12,98,100/-.
11. It was further submitted that the formula adopted, in the absence of any
compensatory stipulation to the contrary, is valid and legal. Learned counsel
relied upon the previous judgments of this Court in Metro Electricals
Corporation Vs. Delhi Development Authority, New Delhi, AIR 1980 Del 266,
and also the judgment in Delhi Development Authority Vs. S.S. Jaitley (2001
(1) Arb. LR 289 (Del). Counsel also submitted that the entire issue was
considered in Delhi Development Authority Vs. U.Kashyap, 1998 VII AD (Delhi)
300, where it was ruled that decision in Metro Electricals Corporation's case
(supra) and subsequent judgments, where the arbitrator had awarded
amounts in the backdrop of Clause 10 (C) but in the absence of any other
stipulation, permitting award of compensation for other items, was justified.
The said decision upheld the previous judgments in that regard even while
ruling that in contracts where subsequent stipulations i.e. Clause 10 (CC) had
been added, the aggrieved contractor could not claim on the basis of a formula
alien to such a stipulation.
12. Learned counsel submitted that the objection to claim No.4 is also not
tenable. It was urged that the arbitrator's basis for awarding Rs.1,20,000/- was
factually the determination of 30 months delay. The award relied upon the
Hudson in Building and Engineering Contracts, Xth edition in support of the
award of Rs.1,20,000/-. Counsel contended that the reasoning cannot be
characterized as arbitrary. He also relied upon the Division Bench ruling of this
Court in Delhi Development Authority Vs. S. S. Jaitley case (Supra) in this
regard.
13. So far as the objections to claim Nos. 5, 8 and 9 i.e. interest for different
periods are concerned Shri Malhotra contended that at the time when the
contract was being performed the prime lending rates were high and the award
in this regard cannot be considered excessive or illegal.
14. Learned counsel submitted that the award concerning additional claim
was fully justified. He relied upon the judgment reported as Dwarka Das Vs.
State of Madhya Pradesh, AIR 1999 SC 1031 and a previous judgment of the
Supreme Court in M/s A.T. Brij Paul Singh & Bros Vs. State of Gujarat, AIR
1984 SC 1703. It was submitted that in these judgments the Supreme Court
upheld awards where 15.damages had been granted on the head of loss of
profitability.
The above factual matrix shows that there is practically no dispute on the
facts. The admitted facts are that there was delay of almost of about 30
months in the performance of the contract. However, this delay was found to
be due to inaction and omissions of the DDA, by the arbitrator. The arbitrator
also ruled that the DDA records established that the admitted delay was 960
days. On the basis of this material and also the circumstance that extension of
time for performance was granted to the contractor without levy of
compensation, arbitrator concluded that the DDA's conduct was not free from
blame which has formed the basis of the findings of claim No.2 which relate to
various heads concerning preparation of final bill. The claimant/contractor had
demanded for release of no less than 13 heads terms as extra items for which
the DDA had withheld amounts from it. Though the contractor claimed a sum
of Rs.36,54,080/- on account of final bill, what was finally awarded was
Rs.47,306.28. The arbitrator has adduced reasons as against each head of
claim allowed in favour of the contractor. The DDA has not been able to point
out any infirmity in this reasoning or establish through material that such
findings were unsupported by evidence. In these circumstances, neither the
award nor the approach of the arbitrator as regards this head of claim can be
faulted.
16. The DDA attacks the award of Rs.1,93,130/-, in claim No.3 found in
favour of the contractor. The contractor had claimed Rs.12,98,100/- on account
of damages for the work done during the extended period of the contract. In
view of the finding that the actual delay is of 920 days, the arbitrator reasoned
that the claimant was justified in demanding the damages. He then went on to
apply the prevalent cost index to the value of work done on the basis of the
IIIrd Running Account bill (RA Bill) and also took into account the final bills.
After applying the formula, he awarded a sum of Rs.1,97,130/-.
17. The contract with the DDA stipulated only grant of escalated labour
charges in clause 10 (C). Numerous previous decisions of this Court starting
from Metro Electricals Corporation Vs. Delhi Development Authority, New Delhi
to DDA Vs. U.Kashyap (supra) hence spoken of the legality of such damages,
since the escalation clause in the contract (as existing during those days) only
neutralized higher labour costs, but nothing else. Therefore, the award cannot
be characterized as illegal or amounting to legal misconduct under the
Arbitration Act, 1940. Learned counsel for the DDA could not dispute that this
proposition is far too well settled by now. In these circumstances, it is held
that the objections to the award of Claim no.3 are unfounded.
17. The next ground of challenge relates to claim no.4 where the arbitrator
had awarded Rs.1,20,000/-. DDA's argument here cannot be accepted for
more than one reason. The Arbitrator in the opinion of the Court indicated
sufficient reasons in support of the award, on this head of claim. He reasoned
that the contractor was entitled to reckon 30 months delay. All that the
arbitrator did, as far as this claim is concerned was to award Rs.4,000/- per
month for 30 months, on account of manager's salary ( apparently a
presumptive one which cannot by any means can be called unreasonable
under the circumstance) for each of those 30 months. The second ground why
this objection is untenable is that the similar awards have been upheld
previously by this Court. Undoubtedly in view of the judgment in S.S. Jaitely
case (supra), the objections to the award under claim No.4 are without any
foundation.
18. The objections of the DDA to claim nos. 5, 8 and 9, in the opinion of the
Court are substantial and worthy of acceptance. The arbitrator has applied
18% interest per annum with quarterly rests for all the three purposes i.e. pre-
suit, pendent lite as well as future interest, though there might have been
some justification at some point of time when the prime lending rates were
high, the arbitrator was not justified in awarding such a uniform rate which
cannot but result in hardship, when the award was published in 1995. The
Supreme Court too has in recent past held that award of high rates of interest
is not warranted. In the circumstances, this Court hereby modifies the award
to the extent of rate of interest; in respect of all the three periods indicated
which shall stand substituted to 12% p.a. (but without quarterly rests).
19. The arbitrator had awarded a sum of Rs.3,01,143.51 towards the loss of
profitability (Additional Claim No.1) on application of a hypothetical formula.
This pre-supposed that during the extended period, the contractor was
deprived of legitimate profit. The grant of such amount presumes that the
contractor would have been prevented from carrying out other works. The
grant of such presumptive damages in the opinion of this Court in such
circumstance is without justification. The Supreme Court in its judgment
reported as Bharat Coking Coal Ltd. Vs.L.K. Ahuja case (supra) held as follows :
"24. Here when claim for escalation of wage bills and price for materials compensation has been paid and compensation for delay in the payment of the amount payable under the contract or for other extra works is to be paid with interest thereon, it is rather difficult for us to accept the proposition that "Loss or Profit". It is not unusual for the contractors to claim loss of profit arising out of diminuation in turnover on account of delay in the matter of completion of the work. What he should establish in such a situation is that had he received the amount due under the contract, he could have utilized the same for some other business in which he could have earned profit. Unless such a plea is raised and established, a claim for loss of profits could not have been granted. In this case, no such material is available on record. In the absence of any evidence, the arbitrator could not have awarded the same. This aspect was very well settled in Sunley (B) & Co. Ltd. Vs. Cunard White Star Ltd, 5 (1940) 1 KB 740, by the Court of Appeal in England. Therefore, we have no hesitation in deleting a sum of Rs.6,00,000 awarded to the claimant."
20. Aside from the above decision, it would be also important to recollect
that the grievances of a contracting party about wrong doing by the other
party, amounts to a complaint of breach. The principles for awarding damages
are embodied in Sections 73 and 74 of the Contract Act. In such a case, the
aggrieved party would have to establish through some evidence the loss in
monetary terms which has been suffered by it. It would not be open for it to
claim a certain amount and co-relate it with abstract formula not sanctioned by
law. The decisions of the Supreme Court relied upon by the contractor namely
Dwarka Das Vs State of Madhya Pradesh & Another and M/s A.T. Brij Paul Singh
& Bros Vs. State of Gujarat (supra) were rendered in circumstances where the
contract was rescinded. However, here the Court is dealing with the case
where the contract was extended with mutual consent. Due to this important
distinction, the Court is of the opinion that the rationale supported in these two
judgments of the Supreme Court cannot apply in the present case. Besides
this Court is also fortified in its finding by the previous judgments of this Court
in Delhi Jal Board and Avtar Singh Vs. MCD (Supra) referred to above.
21. Another reason why such formula may not be acceptable is that unlike
Section 74 - which supported parties reasonable pre-estimate of damage,
Section 73 prescribes the statutorily mandated formula, i.e. the difference
between the contracted price, and the price on date of breach. The claimant in
cases falling under Section 73 would have to prove the amount, by some
evidence. Though adoption of formulas as was done in this case is a
convenient method of arriving at some figure, the danger of accepting it would
be to universalize an approach, which does not have statutory basis. Besides,
there would be fluidity in standards, leaving each arbitrator to chart his own
course.
22. As far as the last challenge to the additional claim no.2 is concerned,
here the objections made by DDA in the opinion of the Court are merited. The
arbitrator did not take into consideration the fact that the contractor kept the
amount of Rs.1,00,000/- in the fixed deposit which undeniably earned him
some interest. In the circumstances the award of further interest for almost a
20 year period was unjustified.
23. In view of the above conclusions, the objections of the DDA have to be
partly allowed. The award in so far as it pertains to additional claim Nos. 1 and
2 are hereby set aside. The award of interest is modified from 18% with
quarterly rests (claim nos. 5,8 and 9); it shall, however, be substituted with
direction to pay 12% interest per annum for the said periods.
IA No.3974/1996 is allowed in the above terms.
CS (OS) No.1760A/1995
The award is made rule of the Court subject to modifications indicated in
the order in IA No.3974/1996.
A decree shall be drawn in the above terms.
S. RAVINDRA BHAT, J.
AUGUST 21, 2008 mb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!