Citation : 2008 Latest Caselaw 1397 Del
Judgement Date : 20 August, 2008
61
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Pronounced on 20.08.2008
+ CS (OS) 179A/1999
PRAVEEN KUMAR GUPTA. ..... PLAINTIFF
Through: Mr. Vivekanand, Advocate.
versus
DDA ..... DEFENDANT
Through: Ms. Monica Sharma, Advocate for
Ms. Anusuya Salwan, Advocate.
CORAM:
HON'BLE MR. JUSTICE S. RAVINDRA BHAT
1. Whether the Reporters of local papers Yes
may be allowed to see the judgment?
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be
reported in the Digest? Yes
Hon'ble Mr. Justice S. Ravindra Bhat (Open Court)
%
1. The present proceedings concern the legality and validity of an Award dated 26th
December, 1998, published by the Sole Arbitrator Sh. A.Shankaran, retired Additional Director
General of the Central Public Works Department (hereafter referred to as "the Arbitrator").
The Arbitrator was nominated in terms of Clause 25 of the contract entered into by the parties,
on behalf of the Delhi Development Authority, the Objector (hereafter referred to as "the
DDA").
CS (OS) 179A/1999 Page 1
2. Briefly, the facts of this case are that the plaintiff (hereafter referred to as "the
Contractor") bid for the works in question, namely, 3224 HIG Dwelling units in Sector III, IV, V,
VII AND VIII at Rohini (SH) Const. of 128 MIG dwelling units in Sector-V, Pocket A I at Rohini. In
terms of the contract, as officially awarded on 2.3.1983, the stipulated starting date was
12.03.1983. The contractor was to complete the work on or before 11.06.1984 i.e. 15 months
after the date of start. It is not in dispute that the work was not completed within the
stipulated time. However, parties accused each other for the delay. The DDA rescinded the
contract on 27.05.1985. The contractor raised disputes which were referred to arbitration
under Clause 25.
3. The contractor made 16 claims; (11 main claims and 5 additional claims), the DDA in
turn made 7 counter claims and 3 Additional counter claims. The Arbitrator in the impugned
Award summarized his findings in para 6 which would disclose that as against the contractor's
claim, three were turned down and in respect of the other claims, part of the amounts claimed
were granted. The total amount awarded was Rs.4,67,689/-. The Arbitrator also awarded 12%
interest per annum for the period 27.11.1985 to 26.11.1995. He also awarded interest of 12%
for the period 12.03.1998 to 26.12.1998 and calculated accrued and past and pendente lite
interest amount, at Rs.6,05,657/-. Thus, the total amount awarded is Rs.10,73,350/- with
future interest at 12% per annum. The award of interest was conditional. In case the amount
was paid on or before 28.2.1999, no future interest was payable. In case any other
circumstances, i.e. if the amount was not paid by that period, future simple interest at 18% per
annum was awarded from 27.12.1998 till date of actual payment.
CS (OS) 179A/1999 Page 2
4. The DDA has filed objections to the Award. It is contended that the Arbitrator's
findings, as regards the absence of justification for recession of the contract cannot be
supported in law. Counsel contends that the arbitrator misread the materials placed before
him in concluding that the recession was unjustified. According to the objections, which were
reiterated by learned counsel, the delay was due to the contractor's fault. It was submitted
that the contention about drawings not being issued is not correct. Counsel submitted that
20% of the period could not be utilized. However, as regards the 80% of the period, the
Contractor was free to carry out the work. It was also contended that the Contractor failed to
manage the work property and under no circumstances could the period, except high monsoon
or such like weather be regarded as hindrances. Other aspects of the Award with regard to
heads of delay found by the Arbitrator were also attacked.
5. Learned counsel contended that the Award of Rs.98,624/- towards Claim No.1, cost of
work done but withheld, was not justified and is not based on any materials on record. Learned
counsel for the DDA further contended that as the contractor was a defaulter, in terms of
Clauses 2 & 3 of the contract, he could not claim any payment under Clause 10 (c) towards
escalation in labor charges. Therefore, the Arbitrator acted contrary to the contract in
awarding the sum of Rs.17,388/-. Learned counsel relied upon certain documents being Ex. R-
8, R-16, R-9 and R-3 in this regard.
6. Learned counsel next attacked the findings of the Arbitrator under Claim No.4 and
submitted that the Contractor had to submit his bills for regular monthly payments; however,
the records disclose that he did not do so. The DDA, therefore, contended that as and when
bills were furnished, payments were released. In these circumstances, the Contractor could not
CS (OS) 179A/1999 Page 3
have made a claim on this head. She relied upon the Ex.R-4, a communication written to the
Contractor by the DDA on 17.12.1994. It was, therefore, submitted that the Award to the
extent of Rs.5,896/- is unjustified. Learned counsel contended that the award towards claim
No.8 i.e. differential cost of over weight of steel was not justified in the circumstances of this
case. On this head, the Arbitrator had awarded the sum of Rs.3,00,000/-. Learned counsel
relied upon Clause 12 of the agreement in this regard to say that no claim on this account could
have been entertained by the Contractor. It was also submitted that the value of steel after
additional condition No.12 according to the specification - which were part of the contract- had
not been considered, while awarding the amounts on that head. Learned counsel contended
that the Award of Rs.2,700/- towards retention of T.N.P. at work site is unjustified.
7. The DDA complains that the award of Rs.29,884/- towards the Additional Claim No.1 i.e.
differential cost of the secured advance withheld by it from the contractor, is not supported in
law. It was submitted that according to the DDA's document Ex. R-18, the Contractor was
entitled only to the sum of Rs.1184/-. Similarly as far as the award of Rs.5,028/- towards
Additional Claim No.2 is concerned, DDA attacked it as contrary to the facts.
8. Learned counsel next contended that the Arbitrator had held that the contractor was
not responsible for the lapses and, therefore, awarded additional Claim No.3 to the extent of
Rs.64,302/- withheld by way of retained security deposit. These were in two amounts i.e. fixed
deposits of Rs.53000/- and Rs.11302/- as cash. DDA contends that in view of the fact that the
recession was justified and lawful, the security deposit was not refundable to the contractor. It
was also urged that no amount could be awarded in respect of additional Claim no.4 though the
arbitrator awarded Rs.10,000/- for extra work. Learned counsel relied on additional condition
CS (OS) 179A/1999 Page 4
No.6 which stated that no payment shall be made to Contractor for damage caused due to rain,
snow falls etc. Learned counsel submitted that findings in regard to the additional claim No.5
were unfounded. It was submitted that the Arbitrator's observations based on entries in the
measurement book and P-46 about dismantling of the brick work etc. were not justified on the
facts of this case. It was lastly argued that the findings towards Claim Nos. 5,6 and 11 made by
the Arbitrator whereby he had awarded the sum of Rs.2,36,867/-, are unsustainable. According
to the DDA, these sums were not payable and it could not be fastened with the liability since
there was no delay in its part in handing over of the site or in performing its part of the
contract. The DDA submitted that under Clauses 1 and 3 of the specifications and conditions of
the contract, at best, the contractor was entitled to seek extension of time but not ask for
additional compensation for the work done during the extended period. Learned counsel relied
upon the pleadings to submit that as a matter of fact, the scheme of contract between the
parties had been grossly mis-interpreted by the Arbitrator. The hindrances and delay, in any
case, did not amount delay so as to invest the Arbitrator with jurisdiction to award any amounts
under these heads. The DDA also challenged award of post award interest as excessive.
9. Mr. Vivekanand, learned counsel for the plaintiff relied upon the award and contended
generally that the sole arbitrator was a technical person who meticulously considered the
claim, counter claims and the numerous materials placed before him while rendering his
reasoned findings. Counsel urged that in such circumstances, the Court ordinarily defers to the
findings based on evidence and would be slow in interfering with the award unless patent
illegality or perversity in the appreciation of the fact is made out.
CS (OS) 179A/1999 Page 5
10. Learned counsel relied upon the findings on the preliminary issue regarding delay and
contended that the Arbitrator's approach was sound and unexceptional. Learned counsel
relied upon the findings to say that even though the work was to start on 12.3.1983, the parties
had agreed before the Arbitrator the foundation drawings were given to the Contractor on
18.06.1983. Learned counsel also pointed out to other specific findings such as the facts that
the design of foundation, concrete thickness was increased by 3" in August 1983, (para 3.3.2 of
the Award) the findings of escalation of the surplus according to the directions of the DDA
resulted in 900 cu.m. of surplus earth and causing hindrances in the performance of the work
till September 1983 (para 3.3.3 of the Award); delay from respondent in issue of superstructure
structural drawings (para 3.3.4 of the Award) changed in design of brick work in level 1 and
level 2 on 18.8.1983 and several other similar factors. It was contended that all these were
cumulatively taken into account by the Arbitrator when he held that the recession was
unjustified. The contractor submitted that even though the parties had agreed that the date of
the complaint would be 11.6.1994, the 12 factors found by the Arbitrator clearly pointed out to
culpable inaction on the part of the DDA which render the performances within the stipulated
period.
11. It was contended moreover that the DDA was fully aware of its lapses and intentionally
did not issue any letter extending the contract for its duration but just issued a letter of
extension on 29.8.1985 (after issuing the letter of recession dated 27.9.1985). In these
circumstances, the finding regarding illegality of recession, and lack of justification on the one
hand and entitlement of the contract or for the amounts awarded can hardly be characterized
as illegal. It was submitted that the attack to the various findings of the Arbitrator are without
CS (OS) 179A/1999 Page 6 any basis. It was submitted that the objection to the findings on claims 1,2,4,8 and 9 are
unsubstantiated. It was submitted that the materials sought to be relied upon by the DDA were
considered by the arbitrator and discussed in his Award.
12. Learned counsel submitted that the reliance placed, on Additional Condition 12 so far as
the objection to Claim No.8 is concerned and additional Claim No.4 is concerned are without
any substance. These objections too were duly considered by the Arbitrator. The counsel
submitted that the extended period when the contract had to be performed, the contractor
had to be duly compensated. Since the Arbitrator held the recession to be illegal, the
contractor was fully justified in claiming amounts under Clause 10 (C) for escalation of the labor
cost. Similarly, the withholding of 2% from the bills was held to be unjustified by the Arbitrator.
Learned counsel for the contractor also submitted that the findings on additional claim No.3
were fully justified in view of the Arbitrator's determination on the preliminary issue.
13. The above discussion would show that the contract between the parties initially
scheduled to be completed within 15 months of the date of the start i.e. on or before
11.06.1994, was continued by some tacit consent. It was, however, rescinded on 27.05.1995 by
the DDA. The DDA did not dispute that the foundation drawings were furnished to the
contractor on 18.06.1983; before the Court it does not attack findings with regard to the delay
on its part as regards no less than 11 other items. Its attack to the findings on culpable delay
by the DDA are general and vague. No materials were brought to the Court's notice, to submit
that the Arbitrator mis-conducted himself or acted perversely or ignored any material
document. The Court has also considered the award, which a reasoned one. The arbitrator has
listed all the relevant materials and dealt with the question of preliminary findings as regards
CS (OS) 179A/1999 Page 7 the various heads of delay in no less than 10 pages. In these circumstances, findings on the
delay on the part of the DDA in performing its part the agreement, cannot be characterized as
unjustified or amounting to legal misconduct under Sections 30 or 33 of the Indian Arbitration
Act, 1940. The Arbitrator's approach in this regard can hardly be found faulted.
14. It would also be necessary to notice at this stage that curiously the DDA seems to have
issued an extension letter on 29.8.1985 after it issued a recession letter on 27.5.1985. This
extension letter purported to extend the period of contract from 11.6.1994 i.e. ordinarily
agreed for completion, on 26.05.1996 (one day before the actual date of recession). No
attempt was made by the DDA in these proceedings to justify such "retrospective" extension of
a contract which already stood rescinded according to it.
15. So far as the individual findings are concerned, this Court has considered the objections.
The arbitrator awarded the sum of Rs.98,624/- against Claim No.1 as against the sum of
Rs.2,50,000/- claimed. In this regard, he relied upon several documents such as Ex. C-59, Ex. R-
43, notices and inventories admittedly placed before him. Undeniably, this head pertains to
cost of work done but amount withheld in that regard. No fault can bound with the Award on
this score. Similarly, as regards the award of Rs.17,388/- granted under Claim No.2, as against
the sum of Rs.22,000/-, the Arbitrator took into consideration the documents such as Ex.C-1, C-
2, C-54 as well as respondents' documents R-90. He accordingly awarded Rs.17,388/-. This too,
cannot be characterized as illegal being a pure finding of fact.
16. As regards Claim No.4, the DDA's objections on this score are wholly unfounded and
insubstantial. The objection here is that the Contractor never used to furnish the bills within
time. However, no chart or any materials are pressed into service in support of the arguments.
CS (OS) 179A/1999 Page 8 As regards the award for claim No.8, which is the difference in price of steel bars, the DDA
sought to place reliance on additional condition No.12. The arbitrator here observed that the
said stipulation deals with claims for length, shape or size of bars, which cannot be made by the
contractor. However, he concluded that the claim in this case related to deviation from the
rolling standard weight as laid down in the ISI code. In the circumstances, this finding can
hardly be characterized as unreasonable. During the hearing, learned counsel was unable to
support the attack to the finding on Claim No. 8, on any ground whatsoever.
17. Now, as far as findings on additional claims 1 to 4, 5, 6 and 11 are concerned, DDA like in
the case of other findings, was unable to substantiate its objections. The scope of a Court's
jurisdiction under Section 30 and 33 of the Arbitration Act, 1940 to interfere with an Award are
well settled. This jurisdiction of the Court is neither appellate nor revisional. The court cannot
"second guess" the findings of an Arbitrator, who is a nominated and agreed adjudicator by the
parties. The Court has to generally satisfy itself that the approach of the Arbitrator conforms to
the law and that the Award does not disclose any patent or manifest illegality in the findings or
in the application of law. The Supreme Court in its decisions reported as State of Rajasthan vs.
Puri Construction Co. Ltd. and Anr., (1994) 6 SCC 485 and the previous decision in Sudarsan
Trading Co. v. Govt. of Kerala, (1989) 2 SCC 38 ruled that the Court cannot substitute its
evaluation of the conclusions of the law or fact, to hold that the findings of the Arbitrator were
contrary to the bargain between the parties. It is also held that whether any particular amount
was liable to be paid by within the domain of the Arbitrator. The Court, therefore, cannot take
upon itself the burden of saying that what was actually found was contrary to the contract and
as such beyond jurisdiction of the Arbitrator. More importantly it had been held (Puri
CS (OS) 179A/1999 Page 9 Construction Co. Ltd's case) that if a view taken by the Arbitrator on certain amount is a
possible view though not perhaps the only one, the Award still cannot be examined by the
Court; where reasons are furnished the correctness or reasonableness cannot also be subject of
scrutiny.
18. The above approach has been consistently approved, and applied in all several later
judgments of Supreme and has been adopted and applied by various High Courts including this
Court. On an application of the rule enunciated by the Supreme Court in its above decisions and
consistently applied by all Courts, this Court is of the opinion that the findings of the Arbitrator
in the award impugned as regards the claims of the petitioner and to the extent that declined
the counter claims of the respondents, cannot be faulted. They are neither arbitrary nor
contrary to law; they also do not disclose any patent illegality or manifest injustice.
19. Another additional factor is that principle of law is that the Arbitrator does not have to
disclose mathematical precision, in the Award. If the Award shows that application of mind and
a view which is plausible by the Arbitrator, it can be taken as correct. In Delhi Development
Authority v. Bhagat Construction Co. (P) Ltd. and Anr., 2004 (3) Arb. LR 481 (Del) (DB), it was
held that:
"From the above, it would be clear that the Arbitrator who was well versed in the matter before him as a former Director General of CPWD on the basis of his experience took into consideration the various aspects and that is why instead of awarding a sum of Rs. 16 lakhs 50 thousand as claimed by the claimant restricted the said claim to Rs. 3 lakhs 50 thousand. Arbitrator has not to disclose the basis or the mental process for arriving at such figure. Even otherwise Arbitrator when called upon to give a reasoned Award is still not required to write a detailed Judgment as the Judges do. It is sufficient that he has indicated his trend and given outline to indicate the basis on which he has arrived at such figure."
The objections, therefore, are unsustainable, and have to fail.
CS (OS) 179A/1999 Page 10
20. In view of the above findings, the Award has to be made Rule of the Court. However, the
court is mindful of the fact that the arbitrator had not awarded future interest, if the principal
and interest, as awarded were paid within a stipulated date; in case of failure, he directed
payment of 18% future interest. The said rate, in the opinion of the court, cannot be sustained;
accordingly, the petitioner contractor shall be entitled to the post award interest @ 9% from
the date of filing of the present petition till realization. I.A.8017/2000, is, for the above reasons,
dismissed. Suit decreed in the above terms. No costs.
S. RAVINDRA BHAT
( JUDGE )
August 20, 2008
CS (OS) 179A/1999 Page 11
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!