Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S International Engineers & ... vs M/S Asea Brown Boveri Ltd. ...
2008 Latest Caselaw 1367 Del

Citation : 2008 Latest Caselaw 1367 Del
Judgement Date : 18 August, 2008

Delhi High Court
M/S International Engineers & ... vs M/S Asea Brown Boveri Ltd. ... on 18 August, 2008
Author: Ajit Prakash Shah
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                                                       #26

+      FAO(OS) 465/2007


       M/S INTERNATIONAL ENGINEERS &
       PROJECT CONSULTANTS LTD.                         ..... Appellant
                      Through : Mrs. Rachna Gupta, Advocate


                      versus


       M/S ASEA BROWN BOVERI LTD. (A.B.B.)              ..... Respondent
                      Through : Mr. Ratan Kumar Singh, Adv.


        CORAM:
        HON'BLE THE CHIEF JUSTICE
        HON'BLE DR. JUSTICE S.MURALIDHAR


                               ORDER

% 18.08.2008

This appeal is directed against the impugned order dated 3rd September, 2007

passed by the learned Single Judge of this Court rejecting the appellant's application IA

No. 10044/2007 in OMP No. 484/2007 for condonation of delay in refiling the Objection

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 (the Act).

2. The Award in the present case was pronounced on 6th September, 2006, whereas

the Objection Petition was filed by the appellant on 26th May, 2007. Earlier the appellant

had filed an application before the Arbitral Tribunal under Section 33 of the Act for

modification of the Award. The said application under Section 33 was allowed on 27 th

January, 2007 and the award was modified to the extent of correcting a typographical

error regarding award of interest to the appellant. Dissatisfied with this order, the

appellant filed an application under Sections 13 and 18 of the Act which came to be

dismissed on 28th February, 2007 on the ground of maintainability.

FAO(OS) 465/2007 Pg.1 of 3

3. It is submitted that the copies of the orders dated 27th January, 2007 and 28th

February, 2007 passed by the Arbitral Tribunal were received by the Appellant only on

5th March, 2007 and that in terms of Section 34(3) of the Act, the period of three months

had to be completed from that date. Therefore, it is contended that the application was

filed in time. The explanation offered for the delay in refiling the petition under Section

34 of the Act is that the clerk of the learned counsel for the appellant was remiss in

following up the defects pointed out by the Registry after the Objection Petition was

filed. The refiling of the application was further delayed on account of the illness of the

counsel herself. However, the learned Single Judge was not satisfied with the

explanation and accordingly dismissed the application for condonation of delay.

4. We have heard learned counsel for the parties.

5. The Chairman of the appellant company has filed an affidavit dated 11th August,

2008 stating that the envelope in which the order dated 28th February, 2007 of the learned

Arbitrator was sent was received in the office of the appellant only on 5th March, 2007. It

is contended that in terms of Section 34(3) of the Act, the period of limitation would

expire three months after receiving the Arbitral Award or "if a request had been made

under Section 33, from the date on which that request had been made disposed of by the

arbitral tribunal". It is submitted that inasmuch as the order dated 27th January, 2007 was

received only on 5th March, 2007, the objections which were filed on 26th May, 2007

were within time. This Court is satisfied with this explanation.

6. It also appears that the counsel for the appellant was indeed unwell and therefore

could not follow up on the defects pointed out by the Registry. Taking into account the

above circumstances, this Court is of the view that sufficient reasons have been furnished

by the appellant for the delay in refiling the petition under Section 34 of the Act. The

delay ought to have been condoned.

FAO(OS) 465/2007 Pg.2 of 3

7. Accordingly, the impugned order is set aside. The delay in refiling the Objection

Petition under Section 34 of the Act is condoned and accordingly IA No. 10044/2007 is

allowed.

8. OMP 484/2007 will now be listed before the learned Single Judge on 20th

October, 2008. The appeal is accordingly allowed with no order as to costs.




                                                   CHIEF JUSTICE



                                                   S.MURALIDHAR, J
AUGUST 18, 2008
Pk




FAO(OS) 465/2007                                                         Pg.3 of 3
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter