Citation : 2008 Latest Caselaw 1361 Del
Judgement Date : 18 August, 2008
* HIGH COURT OF DELHI AT NEW DELHI
+ FAO (OS) 341/2008
Mohan Meakin Ltd. ..... Appellant
Through Mr. Dinesh Agnani, Advocate.
versus
1. International Breweries Pvt. Ltd.
2. Scotia Bank
3. Bank of India
4. HDFC Bank
5. ICICI Bank Extension Counter ..... Respondents
Through Mr. Pardeep Dhingra with Ms. Ritika
Sen, Advocates.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE DR. JUSTICE S.MURALIDHAR
1. Whether reporters of the local papers be allowed to
see the judgment ?
2. To be referred to the Reporter or not ?
3. Whether the judgment should be reported in the
Digest ?
ORDER
18.08.2008
CM No. 11403/2008(exemption)
Allowed, subject to just all exceptions.
Caveat No. 164/2008
Caveator has put in appearance. Hence, caveat stands
disposed of.
FAO(OS) 341/2008 & CM No.11401/2008(stay) & CM No. 11402/2008(taking additional documents on record)
1. By consent of the parties, the appeal is taken up for final
hearing.
2. This appeal is directed against an order dated 23rd July, 2008
passed by the learned single Judge in OMP No.332/2008, a petition
under Section 9 of the Arbitration and Conciliation Act, 1996 (Act)
filed by the appellant Mohan Meakin Ltd. (MML) against the
respondents International Breweries Pvt. Ltd. (IBPL) and the
Respondents 2 to 5 banks for securing the Award amount of
Rs.1,42,82,463.87/-.
3. The background to the passing of the impugned order is that
an agreement was entered into between the appellant MML and
Respondent No. 1 IBPL on 14th June, 2001 which was extended by
a letter dated 26th July, 2006. A further brewing agreement was
executed on 01st May, 2007 between the parties. In terms of the
agreement, the disputes that arose between the parties were
referred to the arbitration of Shri N.K. Tyagi, a sole Arbitrator, who
passed an interim Award dated 22nd October, 2007 in an
application filed by MML under Section 17 of the Act. IBPL was
restrained from operating and transferring any funds from its
accounts with the Scotia Bank, Bank of India, HDFC Bank and ICICI
Bank. This interim Award was communicated to the respective
branches of the said banks. The applicant claims that the banks
honoured the interim Award.
4. It is further claimed by a letter dated 24th October, 2007 IBPL
admitted its liability and assured MML that the entire outstanding
of MML shall be cleared within a time bound schedule. According
to MML, IBPL reiterated the above assurance in a subsequent
letter dated 4th December, 2007 where it proposed to provide fix
deposit receipts in the sum of Rs. 81 lacs initially and thereafter
reconcile the accounts. However, IBPL chose not to appear before
the learned arbitrator and contest the claim of the appellant MML.
The appellant claims that the proposal made by IBPL vide its letter
dated 4th December, 2007 was not acceptable to it. Even earlier
by a communication dated 4th August, 2007 IBPL had admitted its
liability to the extent of Rs. 1,42,82,463.87 and it had proposed to
MML that it would settle the account by paying 50%. This proposal
was also not acceptable to MML.
5. A final Award was passed by the arbitrator on 23rd April, 2008
in which it was held that the MML had to recover from IBPL a sum
of Rs.1,42,82,463.87 together with interest @ 7% calculated with
effect from 31st July, 2007 till the date of recovery, an amount of
Rs.50,000/- towards arbitration fees, a sum of Rs.1,45,000/- on
account of stamp duty, a sum of Rs.4,000/- and Rs.2,000/- towards
administrative expenditure and costs respectively. It was further
stated in the final Award that the interim Award dated 22nd July,
2007 was being made absolute in that IBPL would be restrained
from operating or transferring funds from its accounts.
6. According to MML, after the passing of the final Award, IBPL
refused to honour it. The Respondents No. 2 to 5 banks also
refused to continue the restraint on IBPL from operating its
accounts with them. Faced this situation, the appellant MML took
steps to get a transfer certificate for execution of the Award from
the courts in Ghaziabad which in terms of the agreement would
alone have jurisdiction in relation to the disputes between the
parties. According to MML since the Respondents No. 2 to 5 banks
were within the territorial jurisdiction of this court, MML filed a
transfer application before the Ghaziabad court for a transfer
certificate to enable the MML to execute the award through this
court. It is claimed that the transfer certificate thus issued was
sent to this Court and received by the Registry vide Diary No. 9894
dated 28th May, 2008. However, the counsel for the appellant was
informed by the Registry that the said certificate was not
traceable.
7. Thereafter MML filed OMP No. 332 of 2008 under Section 9
of the Act praying that Respondent No. 1 IBPL be restrained from
operating and transferring funds from its accounts with the
Respondents No. 2 to 5 banks. MML claimed that if the interim
protection as prayed for by it was not granted it would be very
difficult for it to get the Award executed. It accordingly prayed
that the interests of MML should be secured to the extent of the
principal amount awarded by the learned Arbitrator.
8. In the said application OMP 332 of 2008 an ex parte order
dated 16th June, 2008 was passed by a learned Single Judge of this
Court restraining the Respondents No. 2 to 5 banks from releasing
an amount of Rs. 1,42,82,464/- from the accounts held with them
by Respondent No. 1 IBPL.
9. While the above application was pending, Respondent No. 1
IBPL filed OMP No. 337 of 2008 under Section 34 of the Act raising
objections to the award. The appellant MML resisted the said
application on the ground that the territorial jurisdiction was only
with the courts at Ghaziabad and that the objection should have
been filed in that court. It is stated that the learned Single Judge
negatived the objection by an order which is being separately
challenged by the appellant.
10. Before the learned Single Judge, in OMP 332 of 2008, MML
contended that Respondent No. 1 IBPL had no business or assets
in India. If the Award amount was not secured, MML would be
unable to recover it in the event of IBPL's objections being
rejected. On the other hand it was contended by IBPL that the
Award as of date was not executable and therefore there was no
justification for depriving IBPL of the use of the monies in its
accounts with Respondents No. 2 to 5 banks. The learned Single
Judge was informed IBPL held over Rs. 2 crores in the said
accounts.
11. The learned Single Judge passed the following order which is
under challenge in this appeal :
"In the facts and circumstances of the case, the
equities will be balanced if the Respondent No. 1 secures about 50 per cent of the Award amount. The Respondent is accordingly directed to furnish the bank guarantee for Rs. 75 lacs in favour of the Registrar of this court for payment of the said amount, if the objections of the Respondent to the Award are dismissed. The Respondent No. 1 to also file the undertaking before the court for payment of the balance amount, if any, found due from the Respondent upon the Award. Upon furnishing of the bank guarantee and filing of the undertaking, the order dated 16th June, 2008 with respect to operation of the bank accounts shall stand discharged. The advance copy of the bank guarantee and the undertaking in the form of affidavit of the authorized person on behalf of the Respondent No. 1 be furnished to the counsel for the Petitioner.
The counsel for the Respondent No. 1 states that it intends to furnish the bank guarantee of Respondents No. 2 to 5 banks. The Respondents No. 2 to 5 banks may allow the accounts of the Respondent No. 1 to be operated only to enable the Respondent No. 1 to arrange the bank guarantee.
The petition is disposed of in above terms."
12. Learned counsel for the appellant submits that there was no
occasion for the learned Single Judge to have modified the ex
parte interim order dated 16th June, 2008 and permitted
Respondent No. 1 IBPL to secure only 50% of the Award amount
by furnishing a bank guarantee while leaving it open to the IBPL to
operate its accounts. It is submitted that when admittedly IBPL
has no business or assets in India, it would in all probability
withdraw the entire amount lying in its accounts, in which case
recovery of the entire Award amount would not be possible in the
event of IBPL's objections being dismissed by the Court. On the
other hand it is contended by learned counsel for the respondent
that since its petition under Section 34 is yet to be decided, the
Award was not executable as such and therefore no interference is
called for with the equitable order passed by the learned Single
Judge.
13. Having heard the learned counsel for the parties and having
perused documents on record, we are of the view that the learned
Single Judge ought to have ensured that the Award amount is
available for being recovered by the Appellant MML in the event of
IBPL's objections being ultimately dismissed. In the circumstances,
the appropriate order would be to require the Respondent No. 1
IBPL to deposit the entire Award amount in this court failing which
the interim order passed on 16th June, 2008 would continue till the
disposal of IBPL's objections under Section 34.
14. Accordingly the impugned order is set aside. It is directed
that Respondent No. 1 IBPL will deposit in this court the entire
Award amount in the sum of Rs. 1,42,82,463.87 within a period of
four weeks and upon such amount being deposited, the interim
order dated 16th June, 2008 passed by the learned Single Judge
would stand vacated. However if the amount is not so deposited,
the order dated 16th June, 2008 would continue to the extent of
restraining Respondent No. 1 IBPL from removing the said amount
from its accounts with Respondents No. 2 to 5 banks till the
disposal of its objection under Section 34 of the Act.
15. The appeal and the applications are accordingly disposed of
with no order as to costs.
CHIEF JUSTICE
S.MURALIDHAR
AUGUST 18, 2008 (JUDGE)
dk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!