Citation : 2008 Latest Caselaw 1342 Del
Judgement Date : 13 August, 2008
* HIGH COURT OF DELHI
% Date of decision: August 13, 2008
+ WP(C) 4729/2008 & CM.9121/2008
Ramunia Fabricators Sdn Bhd & Ors : Petitioners
through
Mr.Neeraj K Kaul,Sr.Adv
with Mr.Ashok Sagar &
Mr.R.Vasanth,
Advs.
Versus
Oil and Natural Gas Corporation Ltd : Respondents
& anr through
Mr.Vikas Singh, Addl.
Solicitor General with
Mr.R.Chandrachud, Adv.
Coram :
Hon'ble Mr.Justice Manmohan Sarin.
Hon'ble Ms.Justice Veena Birbal
(1) Whether reporters of local paper may be
allowed to see the judgment? Yes
(2) To be referred to the reporter or not? Yes
(3) Whether the judgment should be reported
in the Digest ? Yes
Manmohan Sarin, J.
1. Petitioners have filed the present writ petition,
challenging the rejection of the bid, submitted by petitioner
No.1 in respect of B-22 Field Development Project. A
WP(C). 4729/2008 Page 1 of p direction is further sought for quashing of decision dated
14th May, 2008, by
which the tendering process in respect of B-22 Field
Development Project was annulled. Additionally, a direction
is sought for award of contract in respect of project to
petitioner No.1 in view of the fact that petitioner No.1 was
the lowest bidder.
2. The facts giving rise to the present writ petition
and the subsequent developments necessary for disposal of
this petition may be briefly noted:
Petitioners challenge the decision of respondent
No.1/ONGC to annul the tendering process as mala fide
and detrimental to public revenue. It is assailed as contrary
to the directions given in the judgment dated 11th April,
2008 of this Court in WP (C) No.9661/2007. It is urged that
petitioners, whose bid was 108 million dollar less than that
of respondent No.2, have been ousted from the bid process
to the detriment of the revenue.
Respondent No.1/ONGC had invited bids for the
Project vide Tender No.MR/OW/MM/B-22/04/2007.
Petitioner No.2 was issued the tender documents by
WP(C). 4729/2008 Page 2 of p respondent No.1/ONGC. The bids received from the
petitioner No.1 as also respondent No.2/L&T Ltd. were
forwarded to the Consultants for evaluation. Eventually,
petitioners came to know that respondent No.1 only opened
the price bid of respondent No.2 and called them for price
negotiation and the petitioners' bid was not being
considered by respondent No.1, on the ground that the
tender documents had been purchased by one company
while the bid was submitted by another. Petitioners were
constrained to file WP(C).No.9661/2007, challenging
respondent No.1's action in not considering the petitioners'
price bid. In the event, writ petition was allowed by this
Court vide judgment dated 11th April, 2008, quashing the
decision of respondent No.1/ONGC rejecting the bid of the
petitioners on the ground that tender documents had been
purchased by one company, while the bid was submitted
by another. Respondent No.1/ONGC was directed to
consider the bid offered by petitioner No.1. It is the
petitioners' case that petitioner No.3 was the holding
company of petitioner Nos.1 and 2 and all of them
constitute one single economic entity, combining their
WP(C). 4729/2008 Page 3 of p respective experiences and resources for the tendered
contract. Petitioners claim to have made a full disclosure of
the relationship between them and the documents with the
bid included a corporate guarantee issued by parent
company petitioner No.3 to provide financial and technical
support and expert manpower in procurement etc.
Petitioner Nos.1 and 2 are the wholly owned subsidiary of
petitioner No.3.
3. Following the decision of this Court respondent
No.1 sought from the petitioner extension of the validity of
the bid up to 31st May, 2008 and the bank guarantee and
bonds, which were duly given. Respondent No.2/ L&T, the
other bidder, filed a Special Leave Petition bearing
No.13385/2008 against the judgment dated 11th April,
2008. On 13th May, 2008, notice was issued in the said
Special Leave Petition. The Supreme Court directed
maintenance of status quo. Respondent No.1/ONGC moved
an application in the said SLP seeking directions. In the
said application, it was stated that a decision had been
taken not to award the contract to petitioners even though
their price bid was 108 million dollar less than that of L&T.
WP(C). 4729/2008 Page 4 of p The decision was said to be taken on the basis that ONGC
having lost confidence in petitioners as it had failed to
provide a performance bank guarantee and Certificate of
Insurance etc., in respect of another Contract, which had
been awarded to it, namely, B-193 Field Development
Project, It was further stated that considering that there
was only one competent bidder i.e., of L&T remaining,
ONGC had decided on 14th May, 2008 to annul the
tendering process under Clause 25 of the "Instructions to
Bidders". The contract relating to B-193, Field
Development Project, which had been awarded to the
petitioners had been terminated on 16th May, 2008.
4. L&T in view of the application moved by ONGC
and the facts stated therein withdrew the Special Leave
Petition. The order as passed by the Supreme Court is
reproduced for facility of reference:
"Oil and Natural Gas Corporation, respondent No.4 has filed I.A.No.7/2008 stating the circumstances mentioned therein that in view of subsequent development, the Special Leave Petition © No.13385 of 2008 has become infructuous. The said statement has not been controverted.
In view of the fact that the Special Leave
WP(C). 4729/2008 Page 5 of p Petition has become infructuous, as stated in the I.A., learned counsel for the petitioner seeks leave of the Court to withdraw this petition. Permission granted. The Special Leave Petition is disposed of as withdrawn. I.A., is, accordingly, ordered."
5. The learned Additional Solicitor General on
behalf of respondent/UOI submits that in view of the failure
of the petitioner to submit the performance guarantee in a
contract awarded to it in respect of Project B-193 for 683
million dollar, they have lost confidence in the petitioner
and accordingly they decided that they could not entrust
the present strategically important project to the petitioners
and have accordingly cancelled the tender process. In the
aforesaid background of facts, learned counsel for the
petitioner submitted that respondent ONGC, which is an
instrumentality to the State, has acted in a discriminatory
manner. Firstly, petitioners were sought to be disqualified
and made ineligible on the specious ground of the tender
having been purchased by one entity and the bid having
been submitted by two other petitioners, ignoring the
relationship between petitioner No.3, who is the holding
WP(C). 4729/2008 Page 6 of p company of petitioner Nos.1 and 2. Respondent ONGC had
ignored the documents, including the corporate guarantee
and other documents placed on record and the fact that
petitioners were single economic entity and petitioner Nos.1
and 2 were wholly owned subsidiary of petitioner No.3.
6. Petitioner was, therefore, constrained to file
WPC.No.9661/2007 to vindicate its position as to its
eligibility for the bid. Petitioners having succeeded there
and their bid being 108 million dollar less,
respondent/ONGC have chosen to annul and cancel the
tender process itself to the detriment of the revenue.
Mr.Neeraj Kaul submitted that there was no justification in
denying the award of the present contract to the petitioner
on the ground that petitioners had failed to furnish a
performance guarantee in respect of another contract i.e.,
B-193 Field Development Project. Mr.Kaul further
submitted that considerations of public revenue itself
should have outweighed lapses in performance of another
contract, which deserved to be condoned. Petitioner should
have been given the chance to perform this contract after
furnishing the requisite guarantees in terms of this contract
WP(C). 4729/2008 Page 7 of p as its bid was 108 million less. Mr.Kaul also assailed the
contemplated issuance of notice, whereby petitioners were
sought to be blacklisted for all the tenders as a draconian
measure.
7. We have heard Mr.Vikas Singh, learned Additional Solicitor General in opposition. Learned Additional Solicitor General submitted that
respondent/ONGC had moved the application, referred to
earlier, seeking directions in the pending SLP, filed by L&T,
challenging the order of High Court of Delhi, holding the
petitioners eligible and directing considerations of their bid.
In the said application, respondent/ONGC had duly placed
before the Supreme Court the circumstances in which the
decision to annul the tender process covered by the present
writ petition, namely, B-22 Field Development Project was
taken. Respondent/ONGC had duly placed on record the
failure of the petitioners to furnish the performance
guarantee and certificate of insurance despite opportunity
and time being given in respect of B-193, Field Development
Project. Petitioners in the writ petition had set out in detail
the circumstances, namely, the process of under-going a
WP(C). 4729/2008 Page 8 of p reverse take over and resultant negotiations with other
major construction groups and the efforts made to submit
the performance bank guarantee and Certificate of
Insurance. The fact remains that despite this petitioner was
unable to do so and this is the admitted position. In these
circumstances, respondent/ONGC contended that there
was loss of confidence in the petitioners and it had taken a
decision to annul and cancel the tender process in respect
of B-22, Field Development Project. Learned Additional
Solicitor General submits that ONGC was fully justified in
nurturing bona fide doubts on the performance and
capability of the petitioners to execute the contract in
respect of B-22, Field Development Project, if awarded to
them. This strategic contract had already been delayed over
9 months and it could not afford to take any risk or
chances in respect thereof. In these circumstances, it was
decided to cancel and annul the tender process and invite
fresh bid. He submitted that the allegation of ONGC having
acted mala fide with a view to favour L & T stands repelled
with the decision to call fresh tender and not awarding the
work to the sole surviving bidder that is L & T.
WP(C). 4729/2008 Page 9 of p
8. The Supreme Court after hearing the parties
including the petitioners' counsel, who was present, passed
the order, reproduced in para 4 hereinabove. From the
order passed, as aforesaid, by the Supreme Court, it was
clear that the Supreme Court acted on the submissions in
the application, filed by L & T and SLP was held to have
become infructuous. Further, this position was not
controverted by the parties, as recorded in the order. Thus,
the decision to annul the tender process had been duly
brought to the notice of and placed on record before the
Supreme Court in the SLP also and whereafter the aforesaid
petition was permitted to be dismissed as withdrawn.
9. We may also note that during the course of
proceedings in this writ petition on 9th July, 2008 itself, we
had put to the learned counsel for the petitioners that even
in these proceedings, petitioners could prima facie
demonstrate their capacity and financial capability to
perform the contract by furnishing of performance/bank
guarantee, as required for the purposes of this Project to
allay the fear and apprehension of the respondent/ONGC.
Learned counsel for the petitioners after obtaining WP(C). 4729/2008 Page 10 of
instructions on 5th August, 2008, submitted that they were
unable to do so in the absence of formal award of contract,
as their Bankers insist on formal award of contract prior to
issuance of any performance or bank guarantee and are not
willing to furnish the performance guarantee in the absence
of deposit being made or formal order being placed. It
would, thus, be seen that unfortunately petitioners were
not able to avail of this opportunity to demonstrate their
financial capacity to perform the contract.
10. In view of the foregoing discussion and the
decision to annul the tender process and the contemplated
issuance of show cause notice to the petitioners, it would be
for them to challenge the said show cause notice in
separate proceedings. The present writ petition has become
infructuous in view of the decision to call fresh tenders and
in particular the decision not to award the contract to the
petitioners due to loss of confidence on its failure to furnish
the performance guarantee and insurance certificate in
respect of B-193, Field Development Project.
We are of the view that the Supreme Court
having permitted the SLP, challenging the judgment in
WP(C). 4729/2008 Page 11 of favour of the petitioners, to be withdrawn as having become
infructuous on being informed by the ONGC of its decision
to cancel the tendering process, the challenge by the
petitioners to the same in these proceedings would not be
maintainable. Moreover, we are prima facie of the view that
the plea of loss of confidence taken by the
respondent/ONGC in the petitioners for having failed to
furnish the performance guarantee appears to be justifiable
deserving credence. However, we refrain from expressing
any final opinion in the matter lest it affects the petitioners'
case in challenging any contemplated show cause notice
debarring them from participating in tenders in future.
Writ petition is, accordingly, dismissed.
Manmohan Sarin, J.
Veena Birbal, J.
August 13, 2008 aka.
WP(C). 4729/2008 Page 12 of
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!