Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Amarnath Charanji Lal & Company vs Dcm Daewoo Motors Limited
2002 Latest Caselaw 1659 Del

Citation : 2002 Latest Caselaw 1659 Del
Judgement Date : 18 September, 2002

Delhi High Court
Amarnath Charanji Lal & Company vs Dcm Daewoo Motors Limited on 18 September, 2002
Equivalent citations: 102 (2003) DLT 637, 2003 42 SCL 167 Delhi
Author: R Chopra
Bench: R Chopra

JUDGMENT

R.C. Chopra, J.

1. This petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the "Act" only) was filed by the petitioner on the basis of an arbitration clause contained in the tender document dated 9.11.1995. Clause 104 of the said tender document contained an arbitration clause according to which in case of any dispute or difference between the parties touching or concerning the work or the executing or maintenance thereof under the contract or the rights touching or concerning the work or the execution thereof. or to the rights or liabilities disputes or differences between the parties arising out of the contract in question, the decision of the Engineer in charge shall be final and binding. According to the petitioner the respondent did not make payment under the contract and as such the petitioner issued a notice dated 2.11.2001 invoking the arbitration clause but vide is reply dated 21.11.2001 the respondent refused to appoint arbitrator and raised illogical and absurd grounds to resit the claim of the petitioner. Hence the petition for appointment of Arbitrator.

2. The respondent filed a reply to the petition raising preliminary objections that this Court has no pecuniary jurisdiction as the value of the subject matter is less than 20 lakhs; that there is no arbitration agreement between the parties; that the petitioner is not a legal entity; that there is no cause of action against the respondent. It is stated that the tender was granted to a partnership firm M/s Amarnath Charanji Lal & Co. which was an unregistered firm and as such the petitioner has no right to sue the respondent. The agreement as well as arbitration clause are denied and it is stated that the tender was issued to a partnership firm and not to the petitioner. The dues as claimed by the petitioner are also controverter.

3. I have heard learned counsel for the petitioner and learned counsel for the respondent. I have gone through the records of the case.

4. In view of the judgment of the Apex Court in Konkan Railway Corporation (P) Ltd. v. Rani Construction Pvt. Ltd. of the Act does not require even issuance of a notice to the opposite party before the appointment of an arbitrator. It does not contemplate a response from the opposite party nor does it contemplate any decision by the Chief Justice or his designate on any controversy that the other party may raise even in regard to its failure to appoint an arbitrator within the period of 30 days. All that the Chief Justice or his designate has to see is the documents and the correspondence between the parties annexed to the petition and take into account the qualifications required of the arbitrator by the agreement between the parties and other considerations likely to secure the nomination of an independent and impartial arbitrator. No adjudicatory decision is contemplated. In view of Section 16 of the Act, the arbitral Tribunal itself has to rule on its own jurisdiction which includes the objections in regard to the existence or validity of the arbitration agreement between the parties. Therefore, the objections being raised by the respondent in the present case would be looked into by the arbitrator only and not by this Court while disposing of the petition under Section 11 of the Act. The objection in regard to pecuniary jurisdiction of the Court is untenable.

5. In view of the existence of an arbitration agreement between the parties and the non-appointment of an Arbitrator by the respondent after notice under Section 11(4)(a) of the Act, this Court is of the considered view that the petitioner has made out a case for appointment of an Arbitrator under Section 11(6) of the Act. In the result the petition is allowed and Shri Niranjan Singh, Supdt. Engineer, Delhi Central Circle-I, CPWD, I.P. Bhawan, New Delhi-110002 is appointed an Arbitrator to enter upon the reference and adjudicate the disputes between the parties arising out of the tender document dated 9.11.1995. The fee shall be fixed by the Arbitrator himself keeping in view the number of sittings required but it shall not exceed a sum of Rs. 35,000/- in all.

6. The parties are directed to appear before the Arbitrator for further directions on 30.9.2002 at 2.00 PM.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter