Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Guru Bachan Kaur vs Delhi Vidyut Board
2002 Latest Caselaw 1188 Del

Citation : 2002 Latest Caselaw 1188 Del
Judgement Date : 31 July, 2002

Delhi High Court
Guru Bachan Kaur vs Delhi Vidyut Board on 31 July, 2002
Author: S K Kaul
Bench: S K Kaul

JUDGMENT

Sanjay Kishan Kaul, J.

1. The writ petition has been filed seeking directions against the respondents to withdraw the electricity bill in respect of the meter bearing K No. 79742775. It is stated in the petition that the petitioner is residing at S-93, WZ-221, Ground Floor, Vishnu Garden, New Delhi where the electricity meter was installed. On 15.6.92 a notice was served on t he petitioner to show cause in view of the fact that the tampering of the glass of the meter was found on inspection. An FIR was also lodged on 17.6.1992 for theft of electricity and the meter was removed. It is stated in the petition that the petitioner was discharged on 18.7.1996 from the criminal case though the copies of the orders have not been annexed to the writ petition. It is further stated that though the meter was removed yet the electricity bills are still being sent and a bill of Rs. 34,32,232/- has been sent even though the sanctioned load is of 0.25 KW. Since no response was forthcoming form the respondent, the writ petition has been filed.

2. In the counter affidavit it is stated that the action was taken by the respondent in view of inspection report dated 29.4.1992. The petitioner filed suit bearing No. 786/92 in October, 1992 and the trial court was pleased to pass an order for restoration of electricity and accordingly the electricity was restored. The petitioner, however, failed to make the payment even after the reconnection of electricity. The suit was subsequently dismissed for non-prosecution and the electricity was again disconnected. All these facts have not been disclosed in the writ petition.

3. It is stated in the counter affidavit that in pursuance to the inspection report dated 29.4.1992 a case of theft was made out along with load violation and a bill of Rs. 8,77,296.29 was raised in the month of September, 1992. This bill was raised as per the tariff provisions prevalent at that time in terms whereof the bill had to be raised for a period of 3 years preceding from the date of inspection. The electricity had been restored on 14.10.92 in pursuance to the orders of the Civil Judge for domestic purposes or a load of 0.25 KW and supply again was disconnected on 14.7.1994. The bill is stated to have been raised on the following basis after approval from the competent authority:-

i) The petitioner has been charged on load basis from 11th March, 1992 to 17th June, 1992 i.e., the date of the removal of the meter and lodging of the FIR.

ii) From 14th October, 1992 to 14th July, 1994, the petitioner has been charged on domestic tariff on the load of 0.5 KW and six months M.G. have been charged after the disconnection of the supply and meter rent up to date;

iii) The petitioner has also been charged LPSC of Rs. 9368.10 paise on F.A.E. bill plus 3% LPSC from October, 1993 to March, 1999 per month plus 1-1/2 LPSC per month from April, 1998 till date for an amount of Rs. 8,77,296.29.

4. It is also stated in the counter affidavit that the provisional demand had been subsequently withdrawn and the bill revised in terms whereof the net amount payable is Rs. 30,55,573.27. A copy of the bill has been annexed to the counter affidavit. It is also stated that the connected load of 37.246 KW was being used for industrial purposes and that is the reason why bill is of such a high value which includes the parameters as mentioned above. It is stated that it is not a case of only tampering of glass but also of direct tapping for industrial purpose. This is apparent from the discrepencies mentioned in the notice dated 15.6.1992 which is as under:-

1. Phase of electric supply directly for working three phase supply.

2. Tampering with glass of meter no.343571 against K.No.7974275.

3. Tampering of service line against K.No. 84-145/63.

5. Learned counsel for the petitioner sought to contend that there was no explanation for such a high value when the connected load was only 0.25 KW. However, on a specific question being put the learned counsel had no answer as to why there was no disclosure in the writ petition of the earlier suit proceedings or of the fact that why the suit was not prosecuted further.

6. The aforesaid facts show that the petitioner approached the civil court and obtained a reconnection of the electricity, failed to pay electricity charges and thereafter did not pursue the suit and let the suit be dismissed. In my considered view this itself is an abuse of the process of court proceedings.

7. The petitioner has also not further come with clean hands before this court. The petitioner has failed to disclose the facts regarding the past proceedings for which there is no explanation. The petitioner is thus guilty of suppression of material facts.

8. Even in respect of the merits of the controversy it has been correctly explained in the counter affidavit that the case of the petitioner was not one of mere tampering with the glass and theft of electricity but of direct theft also from direct tapping on 3rd phase for using for industrial purposes and the tampering of the service line. It was in fact found that against an original sanctioned load of 0.25 KW the connected load was 37.264 KW.

9. In view of the aforesaid I find no merit in the writ petition and dismiss the same with costs of Rs.5,000/-.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter