Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S R.K. Enterprises vs Chhattisgarh State Industrial ...
2025 Latest Caselaw 2875 Chatt

Citation : 2025 Latest Caselaw 2875 Chatt
Judgement Date : 22 August, 2025

Chattisgarh High Court

M/S R.K. Enterprises vs Chhattisgarh State Industrial ... on 22 August, 2025

Author: Ramesh Sinha
Bench: Ramesh Sinha
                                                          1




                                                                        2025:CGHC:42632-DB
       Digitally
       signed by
       SHOAIB
SHOAIB ANWAR
ANWAR Date:
       2025.08.23
       11:34:19
       +0530                                                                          NAFR

                               HIGH COURT OF CHHATTISGARH AT BILASPUR


                                              WPC No. 4512 of 2025



                    1 - M/s R.K. Enterprises A Proprietorship Through Its Power Of

                    Attorney Mr. R.K. Roy S/o Late H.L. Ray, Aged About 62 Years, For

                    Proprietor Mrs. Vandana Roy W/o Shri R.K. Roy Office Address

                    Vandaniya Vv-46, Parthivi Province Integrated Township, Province

                    Sarona, Raipur, District- Raipur ( C.G. ).

                                                                              ... Petitioner(s)



                                                        versus



                    1 - Chhattisgarh State Industrial Development Corporation ( A

                    Government Of Chhattisgarh Undertaking ) Through- Its Managing

                    Director, First Floor, Udyog Bhawan, Ring Road, No. 1 Telibandha,

                    Raipur District- Raipur ( C.G. ).



                    2   -   The   Executive    Director       Chhattisgarh   State   Industrial

                    Development Corporation First Floor, Udyog Bhawan, Ring Road No.

                    1, Telibandha, Raipur District- Raipur ( C.G. ).
                                      2

3 - The Regional Project Director National Highways Authority Of

India ( C.G. ).

                                                       ... Respondent(s)

(Cause title taken from CIS)

For Petitioner(s) : Shri Rahul Jha, Advocate. For Respondent No. 1 : Shri Kashif Shakeel, Advocate. For Respondent/State : Shri Sangharsh Pandey, Govt. Advocate. For Respondent No. 3 : Shri Dhiraj Kumar Wankhede, Advocate.

Hon'ble Shri Ramesh Sinha, Chief Justice

Hon'ble Shri Bibhu Datta Guru, Judge

Judgment on Board

Per Ramesh Sinha, Chief Justice

22.08.2025

1. Heard Mr. Rahul Jha, learned counsel for the petitioner. Also

heard Shri Kashif Shakeel, learned counsel for the

respondent no. 1 as well as Shri Sangharsh Pandey, Govt.

Advocate, learned counsel for the Respondent/State and

Shri Dhiraj Kumar Wankhede, learned counsel for the

respondent No. 3.

2. By way of this petition, the petitioner has prayed for

following reliefs:-

"10.1 The Hon'ble Court may kindly be pleased to call

the entire records of the case pertaining to the loan

agreement availed by the petitioner.

10.2. That the Hon'ble Court may be pleased to quash

the impugned communication dated 02.05.2025

(Annexure P/12).

10.3. The Hon'ble Court may be pleased to direct the

respondents to release the 20% withheld amount from

the final bill amounting Rs. 9,49,000/- and the amount

of security deposit amounting Rs. 1876810/- with

commercial rate of interest.

10.4. To grant any other relief which the Hon'ble court

may deem fit and proper in the interest of justice."

3. The respondent no.1 entered into agreement with the

petitioner for execution of contract namely "Providing and

Laying of DI Pipe Line for Shifting of existing Pipe Line of

CSIDC along the National Highway (NH- 30) at Industrial

Area Phase-I and Phase-II Raipur (C.G.)" and work order to

this effect was issued on 10.03.2021. According to the

Specifications of Items the petitioner executed the work

with receipt of five running account bills. The Sixth and final

bill was prepared on 03.06.2024 but to the utter surprise the

release of final bill amount was only 80% of the final

amount and 50% of the security deposit amount which

ought to have been released with final bill was also not

released. According to the terms of agreement the entire

security amount ought to have been released within four

months after final bill. Thus an amount of Rs.9,49,320/-

which amounts 20% of final bill has been withheld as also

an amount of Rs. 18,76,810/- towards security amount have

been withheld, hence this petition.

4. Learned counsel for the petitioner submits that the

respondents have illegally and arbitrarily withheld the 20%

amount from the final bill and have illegally withheld the

security deposit of the petitioner. It is further contended

that the acts of the respondents is illegal and arbitrary in so

far as the respondents are contradicting their own stand as

on the one hand they are accepting the design effect and

have decided to replace the pipeline with specifications

provided in the contract agreement with the pipeline of

specifications advised by the expert consultants and on the

contrary is alleging the petitioner that the petitioner has not

completed the work because testing part falls in the scope

of work and the petitioner has not completed the testing

part. He further submits that that the respondents have

illegally withheld the due amount of the petitioner and are

unjustly and unfairly justifying their illegality by shifting the

onus upon the petitioner in the garb of testing of pipeline

whereas it is manifest that the testing is not possible in the

existing circumstances which has arisen due to the fault on

the part of respondents. The petitioner is not responsible

for the defects in the design nor is petitioner responsible for

the flow of drain and sewerage water along with the

industrial units water. The petitioner is not responsible for

the accumulation of water up to height of one metre in the

culvert. He further submits that the petitioner has been

illegally and arbitrarily deprived from the due amount of

contract therefore the respondents are obligated under law

to release the withheld amount and the withheld security

deposit with commercial rate of interest on such amount.

5. On the other hand, learned counsel for the respondents

opposes the submissions made by the learned counsel for

the petitioner and pointed out that arbitration clause exists

for redressal of the grievance of the petitioner and without

taking recourse to the same, approached this Court by filing

this writ petition.

6. We have heard learned counsel for the parties and perused

the impugned order and other documents appended with

the writ petition.

7. There is an arbitration clause No. 28, which reads as

under :-

"Arbitration Clause :

Clause 28 - Except as otherwise provided in this

contract all question and dispute relating to the

meaning of the specification designs, drawings and

instruction herein before mentioned as to thing

whatsoever in any way arising out of or relating to the

contract designs, drawings, specifications, estimate,

concerning the works, or the execution of failure to

execute the same, whether arising during the progress

of the work or a after the abandonment there of shall

be referred to the E.D./M.D. for his decision, within a

period 30 (thirty) days of such an occurrence(s)

thereupon the E.D./M.D. shall give his written

instructions and/or decisions, after hearing the

contractor and Executive Engineer within a period of

15 (fifteen) days of such request. This period can be

extended by mutual consent of parties.

Upon receipt of written instructions or decisions of

Executive Engineer, the parties shall promptly proceed

without delay to comply such instructions or decisions.

If the Executive Engineer fails to give his instruction or

decisions in writing within a period of 15 (fifteen) days

or mutually agreed time after being requested and /or,

if the party(es) is/or aggrieved against the decision of

the Executive Engineer, the aggrieved party may within

30 days prefer an appeal to the E.D/M.D. who shall

afford an opportunity to the parties of being heard

and to offer evidence in support of his appeal. The

Managing Director will give his decision within 30

(thirty) days or such mutually agreed period.

If any party is not satisfied with the decision of the

Managing Director he can file the petition for resolving

the dispute through arbitration in the arbitration

tribunal.

A reference to arbitration tribunal shall be no ground

for not continuing the work on the part of the

Contractor. Payment as per original terms and

conditions of the agreement shall be continued by the

Executive Engineer in accordance with clause - 8

above.

8. From perusal of the above arbitration clause, it appears that

the petitioner has an alternate remedy available under the

arbitration clause mentioned in the agreement executed

between the petitioner and the respondents.

9. Considering the submissions advanced by learned counsel

for the parties, further considering the arbitration clause of

the agreement executed between the parties, so we do not

find any good ground to entertain this writ petition.

10. Accordingly, the writ petition being devoid of merit is liable

to be and is hereby dismissed. However, liberty is reserved

in favour of the petitioner to take recourse to other

alternate remedies available to him under the law, if so

wishes. No cost(s).

                Sd/-                                           Sd/-


          (Bibhu Datta Guru)                            (Ramesh Sinha)
               Judge                                      Chief Justice




Shoaib
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter