Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Kanchan Creation Ltd vs Chhattisgarh State Power ...
2021 Latest Caselaw 3219 Chatt

Citation : 2021 Latest Caselaw 3219 Chatt
Judgement Date : 18 November, 2021

Chattisgarh High Court
M/S Kanchan Creation Ltd vs Chhattisgarh State Power ... on 18 November, 2021
                                           1



                                                                                NAFR
                 HIGH COURT OF CHHATTISGARH, BILASPUR
                                WPC No. 4670 of 2021

M/s Kanchan Creation Ltd. A Company Registered Under The Provisions
Companies Act 1956, Having Its Registered Office At 30 Jail Road, Indore
M.P. Through Its Authorized Signatory Representative Namely Shri Mubarik
Khan Ghouri, S/o Late Mahammad Khan Aged About 78 Years, R/o Nurani
Chowk, Raja Talab, Raipur, District Raipur Chhattisgarh

                                                                        ---- Petitioner

                                       Versus

1.    Chhattisgarh       State     Power       Transmission     Company       Limited
      Chhattisgarh      State    Power     Transmission       Company     Limited    A
      Government Of Chhattisgarh Undertaking, Through Its Managing
      Director, Chhattisgrh State Power Transmission Company Limited,
      Vidyut Sewa Bhawan, Daganiya Raipur, District Raipur Chhattisgarh

2.    Chief Engineer, Chhattisgarh State Power Transmission Company
      Limited, Shed No. 4 Daganiya Raipur, District Raipur Chhattisgarh

3.    M/s Effective Enterpries, A Partnership Firm Registered Under The
      Partnership Act, 1932 Having Its Registered Office At Shop No. 131 E
      Market Sector - 6 Bhilai District Durg Chhhattisgrh Through Its One Of
      The Partner Namely Vijay Ashish Sharma S/o M.D. Sharma Aged
      About 53 Years, R/o Quarter No. 5-A Street No. 38 Sector 4 Bhilai
      District Durg Chhattisgrh

4.    Bank Of Baroda, Through Its Branch Manager, Bank Of Baroda,
      Choubey Coloney Branch, Raipur District Raipur Chhattisgarh

                                                                  ---- Respondents

(Cause-title taken from Case Information System)

For Petitioner : Mr. Manoj Paranjpe, Advocate

Hon'ble Shri Arup Kumar Goswami, Chief Justice

Hon'ble Shri Goutam Bhaduri, Judge

Order on Board

Per Arup Kumar Goswami, Chief Justice

18.11.2021

Heard Mr. Manoj Paranjpe, learned counsel for the petitioner.

2. Chhattisgarh State Power Transmission Company Limited issued a

Tender No.S/S-O&M-12/21-24/72 dated 30.04.2021 on the subject of

"Operation (including cleaning, watch and ward) Work of 31 Nos.220/132 KV

Sub-stations of CG State". The last date and time of sale of tender

documents was fixed on 29.05.2021 at 17.00 Hrs. The last date and time of

submission of tender was fixed on 31.05.2021 at 11.30 Hrs and the last date

and time of opening of tender (techno-commercial) was fixed on 29.05.2021

at 17.00 Hrs.

3. The petitioner along with three others participated in the aforesaid

tender process. While the petitioner was declared as L-3 bidder, the

respondent No.3 was declared as L-1 bidder and one M/s. Jai Enterprises

was declared as L-2 bidder.

4. Clause 1.17 of the tender is on the subject of "Criteria for Placement of

Order" and it provides that the tendering authority reserves the right to

distribute entire tendered quantity amongst 03 No. (maximum) bidders as per

rules of the tendering authority. The distribution ratio is also indicated therein

in a tabular form. It envisages distribution of work from L-1 to L-3 bidder by

counter offered rate of L-1 bidder. In case, any bidder refuses to accept the

counter offered rate, then next rank bidder, will be given chance to accept the

quantity at the counter offered rate of L-1 bidder. In case, L-2 and L-3 bidders

refuse to accept the offer, then the complete quantity will be allotted to L-1

bidder. The quantity distribution to various bidders standing at different

position would be 60% and 40% in respect of L-1 bidder and L-2 bidder,

respectively, in case there are two bidders and 50%, 30% and 20% in

respect of L-1 bidder, L-2 bidder and L-3 bidder, respectively, in case there

are three bidders. There is a note appended to Clause 1.17, but for the

purpose of this case, it is not relevant and therefore, it is not considered

necessary to deal with the stipulations put-forth in the note.

5. Clause 1.19 of the tender is on the subject of "LoI / LoA" and it

provides as follows :

"1.19 LoI / LoA :- Accepted L-1 rate shall be counter offer

to bidders standing up to L-3 position, accordingly

LoI/LoA shall be issued to L-2 and L-3 bidders. The

bidder shall submit acceptance of LoI within 07 days

from its issuance along with one copy of LoI signed by

bidder. In case of acceptance of LoIs is not received in

time, the allotted quantity shall be distributed to the other

bidder as per the distribution ratio mentioned in the table

above."

6. Clause 1.20 of the tender is on the subject of "Agreement" and it

provides as follows :

"1.20 Agreement :- The contractor will execute an

agreement on non-judicial stamp paper worth Rs.300/-

with revenue stamp of Rs.01 (one) affixed on it, as per

the Annexure-I enclosed with this tender document. The

cost of stamp paper etc. shall be borne by the

contractor. The agreement shall be executed within 07

days from the date of issue of detailed order for

execution of contract."

7. The petitioner being L-3 bidder, having accepted offered rate of L-1

bidder, was allotted Letter of Intent ('LoI') by the respondent No.2 on

24.09.2021 and after acceptance of LoI, Letter of Acceptance ('LoA') was

issued to it on 30.09.2021.

8. By the said LoI dated 24.09.2021, the petitioner was requested to

comply with the Security Deposit clause of tender within 30 days (i.e. up to

23.10.2021) of issuance of LoI, further indicating that the amount of Security

Deposit is Rs.42,47,900/-, being 10% of contract value. It was also indicated

that if the petitioner fails to submit Security Deposit / Bank Guarantee within

30 days (i.e. up to 23.10.2021) from the date of issuance of the letter dated

24.09.2021, the work that may be allotted to the petitioner might be

distributed among other bidders as per tender clause.

9. Mr. Manoj Pranajpe, learned counsel appearing for the petitioner

submits that in order to comply with the requirement of making deposit of

Security Deposit, petitioner had taken steps for obtaining Bank Guarantee,

but for reasons beyond his control, formalities for obtaining the Bank

Guarantee could not be completed due to technical reasons and as such, by

letter dated 29.10.2021, the petitioner had informed the Chief Engineer, i.e.,

respondent No. 2 that the Bank Gurantee will be submitted by 20.11.2021.

Even the Bank had issued a letter dated 29.10.2021 informing the

respondent No. 2, that issuance of Bank Gurantee will take 10-15 days

more, but without responding to the said request, the work order was issued

in favour of respondent No.3 on 29.10.2021 for the balance work in addition

to the work which was earlier allotted to him being 50% of total 31 Nos. of

220/132 KV Sub-stations. Learned counsel has drawn the attention of the

Court to Clause 1.21 of the tender on the subject of "Security Deposit" to

contend that the Bank Guarantee is to be submitted normally within 30 days

from the date of issue of LoI / LoA and therefore, when the petitioner had

requested for extension of time, the respondent authorities were obligated to

consider the request of the petitioner for extension of period of time for

furnishing Bank Guarantee and they having not done so, allotment of work

meant for the petitioner in favour of respondent No.3 is not sustainable in

law.

10. By an order dated 29.10.2021, respondent No.3 has been alloted 12

Nos. of 220/132 KV Sub-stations in addition to an order dated 29.10.2021,

which Mr. Paranjpe submits was towards allotted quantity of the respondent

No. 3 being the L-1 bidder. 50% of 31 Sub-stations works out to be 15 or 16.

The total Sub-stations allotted to respondent No.3 does not add up to 31 as

the two orders dated 29.10.2021 add up to only 27 or 28. Be that as it may.

11. To appreciate the contention advanced by Mr. Paranjpe, it would be

appropriate to quote Clause 1.21 in its entirety :

"1.21 Security Deposit :- The contractor shall furnish

security deposit either in the form of DD drawn in favour

of Manager (RAO-HQ), CSPTCL, Raipur or in the form of

Bank Guarantee issued by Nationalized/Scheduled Bank

for faithful performance of the order and to cover the

contract period. The contractor shall be required to pay

security deposit for an amount of 10% of contract value

(including GST/Cess etc, if any).

The bank guarantee shall be submitted normally within

30 days from the date of issue of LoI / LoA and shall be

kept valid for complete contract period including 06

Month claim period. The bank guarantee shall be

submitted on stamp paper worth Rs.250/- or as per the

prevailing legal requirements/ any other amount as per

the C.G. Stamp Duty Act. No interest shall be paid by

CSPTCL on the security deposit. In case of non-

fulfillment of contractual obligations by the supplier the

security deposit shall be forfeited.

If bidder fails to submit Security Deposit/Bank Guarantee

within 30 days from the date of issue of LoA/LoI, the

work allotted to them may be distributed among other

bidders as per company's rule. In the event of extension

of completion date, the validity of the bank guarantee

shall also be suitably extended.

Note : 1) Without acceptance of security deposit by

order placing authority, no payment will be released to

the contractor.

However, it shall be the sole responsibility of the

bidder to ensure the payment to their staff within 07

days after the end of each calendar month.

2) The security deposit shall be released only after

satisfactory completion of the work duly certified by the

concerned OIC."

12. According to the own case of the petitioner, the request was made to

the respondent No.2 to extend the period of time for furnishing Bank

Guarantee on 29.10.2021. The LoI to which reference is made in the earlier

part of the judgment, goes to show that the petitioner was required to make

Security Deposit on or before 23.10.2021. Therefore, the request was

beyond the prescribed period of time. That apart, it is not that the bidder was

required to furnish only Bank Guarantee as it is made explicitly clear in

Clause 1.21 that the contractor shall furnish Security Deposit either in the

form of Demand Draft or in the form of Bank Guarantee. If for any reason,

there was any difficulty in obtaining the Bank Guarantee, nothing prevented

the petitioner to furnish Demand Draft within the stipulated period of time. No

doubt, it is also indicated that the Bank Guarantee is normally to be

submitted within a period of 30 days from the date of issue of LoI / LoA. But it

is to be noticed that it was also indicated that if the bidder fails to submit

Security Deposit/Bank Guarantee within 30 days from the date of issue of

LoI / LoA, the work allotted to them might be distributed among other bidders

as per rules of the tendering authority. Therefore, if a bidder does not submit

the Bank Guarantee within a period of 30 days (in the present case, 30 days

from issuance of LoI), he runs the risk of his work being allotted to others at

the discretion of the tendering authority. In the instant case, the petitioner

had accepted the LoI wherein Security Deposit was directed to be furnished

within 30 days.

13. In view of the above discussion, we are of the considered opinion that

the respondents No.1 and 2 did not act arbitrarily or illegally in allotting the

work of the petitioner in favour of the L-1 bidder. Accordingly, the writ petition

is dismissed at the motion stage in limine. No cost.

                        Sd/-                                           Sd/-
                (Arup Kumar Goswami)                             (Goutam Bhaduri)
                      Chief Justice                                   Judge


Anu
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter