Citation : 2021 Latest Caselaw 1344 Chatt
Judgement Date : 26 July, 2021
1
NAFR
HIGH COURT OF CHHATTISGARH, BILASPUR
First Appeal No.67 of 2012
Reserved on 19.07.2021
Pronounced on 26.07.2021
● M/s. J.B. Construction Company, through its Partner Jaspal
Sethi, aged about 55 years, S/o Late Gurdas (Correct name is
Gurudayal) Sethi, R/o Tikra Para, Bilaspur, Distt. Bilaspur (C.G.)
---- Appellant/Plaintiff
Versus
1. Union of India, Through Divisional Engineer 'North', S.E.C.
Railway, Senior Divisional Office 'North', S.E.C. Railway, Bilaspur
(C.G.)
2. The General Manager, S.E.C.Railway, Bilaspur (C.G.)
---- Respondents/Defendants
For Appellant :Shri Ravindra Agrawal along with Shri Abhijeet Mishra, Advocate.
For Respondents :Shri Pratik Sinha, Advocate.
Hon'ble Shri Justice Sanjay S. Agrawal
C.A.V. Judgment/Order
1. This appeal has been preferred by the Plaintiff under Section 96
of the Code of Civil Procedure, 1908 (hereinafter referred to as
the CPC) questioning the legality and propriety of the judgment
and decree dated 12.01.2012 passed in Civil Suit No.16-B/2010
whereby the learned trial Court has dismissed the suit holding it
to be not maintainable.
2. Briefly stated the facts of the case are that the Plaintiff being a
partner of M/s. J.B.Construction Company instituted a suit
claiming refund of 432 number of fish plates or refund of
Rs.1,30,000/- in lieu thereof by submitting, inter alia, that he is
the railway contractor and has entered into an agreement with
the Defendants, Railway Department, on 22.11.2002 for the
completion of work of execution of various pathway works in
connection with 18 kms. CTR/TSR (16 kms. With Track Relaying
Train and 2 kms. Manually) and other miscellaneous works
worth Rs.41,17,405/- and the dispute, which has arisen between
the parties was decided by the arbitrator vide its award dated
12.02.2007. According to the Plaintiff, the alleged fish plates
(432 in number) have already been deposited by him with the
Railway Department prior to passing of the alleged award on
21.11.2006, yet a sum of Rs.1,30,032/- has been recovered from
him owing to non-deposit of the same. Further contention of him
is that despite the issuance of notice on 04.12.2008 seeking
refund of those fish plates or in lieu thereof for recovery of
Rs.1,32,032/-, recovered illegally from him based upon the said
award, no reply was ever given by the Railway Department,
which compelled him for the institution of the suit in the instant
nature, instituted on 05.05.2009.
3. While contesting the aforesaid claim, it is pleaded by the
Defendants that since the arbitrator has already passed the
award on 12.02.2007 after considering the dispute raised by the
Plaintiff as per the terms and conditions stipulated in the alleged
agreement and since the same has already attained its finality
and, as the Plaintiff has failed to question the same under
Section 34 of the Arbitration and Conciliation Act, 1996 (for
brevity, the 'Act of 1996'), therefore, the suit as framed is not
maintainable and deserves to be dismissed.
4. After considering the evidence led by the parties, it was held by
the trial Court that the alleged fish plates have been returned by
the Plaintiff vide receipt memo dated 21.11.2006, i.e., prior to
passing of the arbitral award dated 12.02.2007 and held further
that since the dispute as alleged herein was already decided by
the arbitrator vide its award dated 12.02.2007 and which has
neither been sought to be questioned nor has been assailed by
the Plaintiff as provided under Sections 33 and 34 of the Act of
1996, therefore, the claim of him cannot be held to be
maintainable. As a consequence of it, the suit has been
dismissed holding it to be not maintainable, which has been
impugned by way of this appeal.
5. Learned counsel for the Appellant/Plaintiff submits that the
finding of the Court below holding the suit to be not maintainable
under Sections 33 and 34 of the Act of 1996 is apparently
contrary to law. According to him, since 432 fish plates have
already been deposited with the Railway Department, therefore,
non-returning the same or its cost is thus a dispute of civil nature
and the trial Court has, therefore, committed a serious illegality
in holding the suit to be not maintainable. The judgment and
decree under appeal is, therefore, liable to be set aside.
6. On the other hand, learned counsel for Respondents/Defendants
has supported the judgment and decree under appeal as passed
by the trial Court.
7. I have heard learned counsel for the parties and perused the
entire record carefully.
8. The main question which arises for determination in this appeal
is as to whether the suit as framed seeking return of alleged 432
fish plates or its cost thereof from the Railway Department has
rightly been held to be not maintainable based upon the arbitral
award dated 12.02.2007?
9. From perusal of the record, it appears that by virtue of an
agreement (Ex.P.1), the Plaintiff, a partner of M/s. J.B.
Construction Company, was awarded the work for the
completion of the work of execution of various pathway works in
connection with 18 kms. CTR/TSR (16 kms. with Track Relaying
Train and 2 kms. Manually) along with other miscellaneous
works under the terms and conditions stipulated therein.
Admittedly and according to the general condition of contract
and rules, a dispute, which has arisen between the parties, was
referred to the arbitrator on the basis of the application made by
the Plaintiff and, one of the disputes considered by the arbitrator
was in relation to cost of 432 fish plates worth Rs.3,30,912/-.
10. After considering the aforesaid dispute, it was observed by the
arbitrator vide its award dated 12.02.2007 (Ex.P.4) that they (432
fish plates) were not returned by the Plaintiff and that by
considering the cost of it to the tune of Rs.1,32,032/- has
directed for its recovery from the Plaintiff.
11. According to the Plaintiff, the alleged 432 fish plates have
already been returned on 21.11.2006, i.e., prior to passing of the
said award on 12.02.2007 and has succeeded to establish the
said fact by producing the receipt memo (Ex.P.2) in this regard.
But, it appears, as observed herein above, that the dispute as
raised herein by the Plaintiff was one of the subject matters
before the arbitrator and which has already been decided
therein. Therefore, in view of said background, the alleged
award, as passed by the arbitrator was to be questioned by the
Plaintiff as per the provisions prescribed under Section 34 of the
Act of 1996. Having failed to assail the same, the Plaintiff
cannot be permitted to re-agitate the same in the instant suit and
the trial Court has, therefore, rightly held that the suit as framed
is not maintainable and I do not find any infirmity in the same.
12. Consequently, the appeal, being devoid of merits, is accordingly
dismissed. No order as to costs.
13. A decree be drawn accordingly.
Sd/-
(Sanjay S. Agrawal) Judge
Anjani
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!